EASY What is the first step in the general startup preparation of a steam boiler?

Make sure the boiler has a valid inspection certificate.

What should be done with the suction and discharge valves on the vacuum or condensate pumps?

Open them to warm up the piping system.

What should be done with the fuel supply lines?

Open the stop valve in the return line.

What should be done with the fresh air supply to the boiler room?

Ensure it is unobstructed.

What should be done with the pressure settings of the operating and high limit controls?

Check them to ensure they are set correctly.

What is the purpose of the low water fuel cut-off and/or high limit control?

To shut off the fuel supply if the water level is too low.

What should be done with the boiler control switch on the panel?

Turn it to the “off” position.

What is the final step before starting the boiler?

Check the boiler and auxiliary equipment thoroughly.

MEDIUM Why is it essential to review the manufacturer's recommendations for the startup of the boiler?

To understand the specific requirements for the boiler's startup procedure

What should be done with the water supply to the feeder valve?

Opened to allow water to flow into the boiler

Why is it important to ensure the fresh air supply to the boiler room is unobstructed?

To ensure proper combustion and ventilation

What is the purpose of setting the control switch on the panel to 'low' on boilers with a high-low firing rate control?

To reduce the boiler's firing rate

Why is it essential to check the pressure settings of the operating and high limit controls?

To prevent the boiler from overheating

What should be done with the boiler control switch on the panel before startup?

Set to 'off' to ensure the boiler is ready for startup

Why is it important to ensure the deaerator and feedwater make-up system are filled to the operating/startup levels?

To ensure a smooth startup and efficient operation

What is the purpose of pushing the reset button on the low water fuel cut-off and/or high limit control?

To reset the safety controls after checking the boiler and auxiliary equipment

HARD What is the primary purpose of reviewing the manufacturer's recommendations for boiler startup?

To understand specific startup procedures

Why is it essential to ensure the deaerator and feedwater make-up system are filled to the operating/startup levels?

To ensure proper boiler operation and safety

What is the purpose of setting the manual-automatic switch to 'manual' on boilers with fully modulating firing rate control?

To allow for manual control during startup

Why is it important to ensure the fresh air supply to the boiler room is unobstructed?

To reduce the risk of explosion

What is the purpose of pushing the reset button on the low water fuel cut-off and/or high limit control?

To reset the control system after a trip

What should be done with the fuel supply lines before startup?

Open the stop valves to ensure fuel availability

What is the purpose of checking the pressure settings of the operating and high limit controls?

To ensure safety and prevent overpressure

Why is it essential to ensure the boiler has a valid inspection certificate?

To comply with regulatory requirements

Match the following steps with the correct actions during the general startup preparation of a steam boiler:

Step 1 = Ensure the boiler has a valid inspection certificate Step 3 = Open the suction and discharge valves on the vacuum or condensate pumps Step 5 = Ensure the fuel supply lines are available to the stop valves Step 7 = Verify that the fresh air supply to the boiler room is unobstructed

Match the following components with the correct actions during the general startup preparation of a steam boiler:

Deaerator = Filled to the operating/startup levels Feedwater make-up system = Verified to be ready to operate Fuel pump = Checked to ensure it is operating within expected range Vacuum or condensate pumps = Set in the 'auto' or 'on' position

Match the following controls with the correct actions during the general startup preparation of a steam boiler:

Boiler control switch = Set to 'off' position Manual-automatic switch = Set to 'manual' on boilers with fully modulating firing rate control High limit control = Checked to ensure pressure settings are correct Flame control switch = Set to 'low' on boilers with fully modulating firing rate control

Match the following systems with the correct actions during the general startup preparation of a steam boiler:

Fuel system = Verified to ensure fuel is available to the stop valves Water supply system = Opened to the feeder valve Steam system = Verified to ensure all parameters are within expected range Air supply system = Verified to ensure it is unobstructed

Match the following steps with the correct reasons during the general startup preparation of a steam boiler:

Reviewing the manufacturer's recommendations = To ensure the boiler is started correctly Checking the pressure settings of the operating and high limit controls = To ensure the boiler operates safely Ensuring the fresh air supply to the boiler room is unobstructed = To prevent overheating Pushing the reset button on the low water fuel cut-off and/or high limit control = To reset the system after a shutdown

Match the following components with the correct reasons for checking during the general startup preparation of a steam boiler:

Deaerator = To ensure it is filled to the operating/startup levels Fuel pump = To ensure it is operating within expected range Low water fuel cut-off and/or high limit control = To ensure it is reset after a shutdown Feedwater make-up system = To ensure it is ready to operate

Match the following steps with the correct purposes during the general startup preparation of a steam boiler:

Setting the control switch on the panel to 'low' = To reduce the firing rate Opening the suction and discharge valves on the vacuum or condensate pumps = To warm up the piping system Ensuring the fuel supply lines are available to the stop valves = To ensure the boiler has a fuel supply Verifying that the boiler has a valid inspection certificate = To ensure the boiler is safe to operate

Match the following systems with the correct purposes during the general startup preparation of a steam boiler:

Fuel system = To provide fuel to the boiler Water supply system = To fill the boiler with water Steam system = To distribute steam to the system Air supply system = To provide oxygen for combustion

Study Notes

Preparing to Start a Steam Boiler

  • Ensure the boiler has a valid inspection certificate, and it has been properly checked, cleaned, filled with water, closed, and tightened, with all auxiliary systems prepared.
  • Review the manufacturer's recommendations for startup to ensure compliance with specific guidelines.

Preparing Piping and Fuel Systems

  • If warming up the piping system with the boiler, open suction and discharge valves on vacuum or condensate pumps, and set pump switches to "auto" or "on".
  • Open the water supply to the feeder valve, if equipped, and ensure the deaerator and feedwater make-up system are filled to operating levels.
  • Ensure fuel availability to stop valves in pilot and main burner supply lines, and open the return line stop valve if using fuel oil.
  • Verify that fuel lines, filter, and fuel pump are operating as expected, with all parameters within expected range.

Final Checks

  • Ensure unobstructed fresh air supply to the boiler room.
  • Check pressure settings of operating and high limit controls.
  • Verify the boiler control switch on the panel is in the "off" position.
  • Set the control switch to "low" on boilers with high-low firing rate control, and to "manual" and low-fire position on boilers with fully modulating firing rate control.
  • If equipped with a mechanical reset, push the reset button on the low water fuel cut-off and/or high limit control.

Preparing to Start a Steam Boiler

  • Ensure the boiler has a valid inspection certificate, and it has been properly checked, cleaned, filled with water, closed, and tightened, with all auxiliary systems prepared.
  • Review the manufacturer's recommendations for startup to ensure compliance with specific guidelines.

Preparing Piping and Fuel Systems

  • If warming up the piping system with the boiler, open suction and discharge valves on vacuum or condensate pumps, and set pump switches to "auto" or "on".
  • Open the water supply to the feeder valve, if equipped, and ensure the deaerator and feedwater make-up system are filled to operating levels.
  • Ensure fuel availability to stop valves in pilot and main burner supply lines, and open the return line stop valve if using fuel oil.
  • Verify that fuel lines, filter, and fuel pump are operating as expected, with all parameters within expected range.

Final Checks

  • Ensure unobstructed fresh air supply to the boiler room.
  • Check pressure settings of operating and high limit controls.
  • Verify the boiler control switch on the panel is in the "off" position.
  • Set the control switch to "low" on boilers with high-low firing rate control, and to "manual" and low-fire position on boilers with fully modulating firing rate control.
  • If equipped with a mechanical reset, push the reset button on the low water fuel cut-off and/or high limit control.

Preparing to Start a Steam Boiler

  • Ensure the boiler has a valid inspection certificate, and it has been properly checked, cleaned, filled with water, closed, and tightened, with all auxiliary systems prepared.
  • Review the manufacturer's recommendations for startup to ensure compliance with specific guidelines.

Preparing Piping and Fuel Systems

  • If warming up the piping system with the boiler, open suction and discharge valves on vacuum or condensate pumps, and set pump switches to "auto" or "on".
  • Open the water supply to the feeder valve, if equipped, and ensure the deaerator and feedwater make-up system are filled to operating levels.
  • Ensure fuel availability to stop valves in pilot and main burner supply lines, and open the return line stop valve if using fuel oil.
  • Verify that fuel lines, filter, and fuel pump are operating as expected, with all parameters within expected range.

Final Checks

  • Ensure unobstructed fresh air supply to the boiler room.
  • Check pressure settings of operating and high limit controls.
  • Verify the boiler control switch on the panel is in the "off" position.
  • Set the control switch to "low" on boilers with high-low firing rate control, and to "manual" and low-fire position on boilers with fully modulating firing rate control.
  • If equipped with a mechanical reset, push the reset button on the low water fuel cut-off and/or high limit control.

Preparing to Start a Steam Boiler

  • Ensure the boiler has a valid inspection certificate, and it has been properly checked, cleaned, filled with water, closed, and tightened, with all auxiliary systems prepared.
  • Review the manufacturer's recommendations for startup to ensure compliance with specific guidelines.

Preparing Piping and Fuel Systems

  • If warming up the piping system with the boiler, open suction and discharge valves on vacuum or condensate pumps, and set pump switches to "auto" or "on".
  • Open the water supply to the feeder valve, if equipped, and ensure the deaerator and feedwater make-up system are filled to operating levels.
  • Ensure fuel availability to stop valves in pilot and main burner supply lines, and open the return line stop valve if using fuel oil.
  • Verify that fuel lines, filter, and fuel pump are operating as expected, with all parameters within expected range.

Final Checks

  • Ensure unobstructed fresh air supply to the boiler room.
  • Check pressure settings of operating and high limit controls.
  • Verify the boiler control switch on the panel is in the "off" position.
  • Set the control switch to "low" on boilers with high-low firing rate control, and to "manual" and low-fire position on boilers with fully modulating firing rate control.
  • If equipped with a mechanical reset, push the reset button on the low water fuel cut-off and/or high limit control.

Learn the essential steps to prepare a steam boiler for startup, from inspection certification to system preparation. Understand the general guidelines to ensure a safe and efficient startup process.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Steam Systems and Multiple Boilers
20 questions
Steam Boiler Operation and Safety Quiz
20 questions
Boiler Water Management Quiz
24 questions
4BE3.5 U4 C2 Obj 3 EMH
69 questions

4BE3.5 U4 C2 Obj 3 EMH

WholesomeMaroon avatar
WholesomeMaroon
Use Quizgecko on...
Browser
Browser