What is the first step in preparing to start a steam boiler?

  • Checking the pressure settings of the operating and high limit controls
  • Ensuring the boiler has a valid inspection certificate (correct)
  • Ensuring the deaerator and feedwater make-up system are filled to operating levels
  • Reviewing the manufacturer's recommendations for the startup of the boiler
  • What should be done if the piping system is going to be warmed up with the boiler?

  • Ensuring the fresh air supply to the boiler room is unobstructed
  • Opening the suction and discharge valves on the vacuum or condensate pumps (correct)
  • Reviewing the manufacturer's recommendations for the startup of the boiler
  • Checking the pressure settings of the operating and high limit controls
  • What should be ensured in relation to fuel before starting a steam boiler?

  • The deaerator and feedwater make-up system are filled to operating levels
  • Opening the fresh air supply to the boiler room
  • All parameters are within expected range (correct)
  • Ensuring fuel oil lines are clean and well-maintained
  • What should be reviewed before starting a steam boiler?

    <p>Reviewing the manufacturer's recommendations for the startup of the boiler</p> Signup and view all the answers

    What should be checked to ensure safety before starting a steam boiler?

    <p>Checking the pressure settings of the operating and high limit controls</p> Signup and view all the answers