Software Project Planning Quiz
10 Questions
2 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the objective of software project planning?

  • To undertake various activities for project development
  • To implement mathematical techniques for project estimation
  • To provide a framework for estimating resources, cost, and schedule (correct)
  • To conduct a feasibility study of the project
  • When is the estimation of effort, cost, and project duration typically done?

  • During the feasibility study
  • After the completion of project planning
  • At the end of the project
  • At the beginning of the software project (correct)
  • What is the feasibility study's role in project planning?

  • To estimate the resources required for the project
  • To analyze the project progress
  • To schedule the project activities
  • To determine if the project is feasible before undertaking project planning (correct)
  • How often should the estimates made at the beginning of the software project be updated?

    <p>Regularly as the project progresses</p> Signup and view all the answers

    What is the role of project managers in estimating project parameters?

    <p>Utilize various techniques to estimate effort, cost, and project duration</p> Signup and view all the answers

    What is the objective of software project planning?

    <p>The objective of software project planning is to provide a framework that enables the manager to make reasonable estimates of resources, cost, and schedule.</p> Signup and view all the answers

    When is the estimation of effort, cost, and project duration typically done?

    <p>The estimation of effort, cost, and project duration is typically done within a limited time frame at the beginning of the software project.</p> Signup and view all the answers

    What activities are done during project planning?

    <p>Various activities are done during project planning, including the feasibility study of the project and the estimation of effort, cost, and project duration.</p> Signup and view all the answers

    How often should the estimates made at the beginning of the software project be updated?

    <p>The estimates made at the beginning of the software project should be updated regularly as the project progresses.</p> Signup and view all the answers

    What is the role of the feasibility study in project planning?

    <p>The feasibility study is done before the planning of any project, and if the project is found to be feasible, then the software project manager will undertake project planning.</p> Signup and view all the answers