Which process involves identifying and documenting relationships among project activities?
Which process involves identifying and documenting relationships among project activities?
- Sequence Activities (correct)
- Estimate Activity Duration
- Plan Schedule Management
- Define Activities
Which process involves analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule?
Which process involves analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule?
- Plan Schedule Management
- Develop Schedule (correct)
- Control Schedule
- Define Activities
Which process involves establishing policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule?
Which process involves establishing policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule?
- Estimate Activity Duration
- Control Schedule
- Plan Schedule Management (correct)
- Define Activities