What takes precedence in case of a discrepancy between the figures written on drawings and the scaled drawings themselves?

  • The owner's approval
  • The figures written on drawings (correct)
  • The scaled drawings
  • The contractor's interpretation

Where shall any disputes arising from the contract be litigated?

  • Through arbitration
  • In the courts of the Philippines (correct)
  • In the courts of the contractor's location
  • In the courts of the owner's location

What is the basis for the interpretation of the contract?

  • The contractor's agreements
  • The laws of the Republic of the Philippines (correct)
  • The owner's specifications
  • The laws of the country where the contractor is located

What shall the contractor conform to in all respects?

<p>The provisions of all statutes, ordinances, and laws (A)</p> Signup and view all the answers

What is the responsibility of the contractor in case of breach of statutes, ordinances, and laws?

<p>The contractor shall keep the owner indemnified (A)</p> Signup and view all the answers

What is applicable to all government projects?

<p>Presidential Decree 1594 and its implementing rules and regulations (A)</p> Signup and view all the answers

Who shall make surveys to estimate quantities for progress payments?

<p>The Contractor and the Owner (C)</p> Signup and view all the answers

What is the purpose of inspecting the works?

<p>To make a complete and detailed inspection (B)</p> Signup and view all the answers

What is the primary purpose of Republic Act No. 1582?

<p>To repeal and replace Section 24 of Republic Act 544 (D)</p> Signup and view all the answers

What happens to defective work found prior to final acceptance?

<p>It is removed and replaced to conform with the Plan and Specifications (D)</p> Signup and view all the answers

What is the requirement for admission to the practice of civil engineering?

<p>Individual, personal qualifications (C)</p> Signup and view all the answers

Who gives notice to the Owner when work is ready for examination?

<p>The Contractor (A)</p> Signup and view all the answers

What is the limitation on the formation of a firm, partnership, or association for civil engineering?

<p>Only licensed civil engineers and architects can form a firm, partnership, or association (B)</p> Signup and view all the answers

What is subject to inspection?

<p>All materials and equipment furnished under the provisions of the Specifications (D)</p> Signup and view all the answers

What is the responsibility of individual members of a firm, partnership, or association for civil engineering?

<p>Individual responsibility for their own respective acts (C)</p> Signup and view all the answers

Who shall be allowed access to all parts of the Works at all times?

<p>Only the Owner and his authorized representatives (B)</p> Signup and view all the answers

What is the limitation on the work and services of civil engineers in a firm, partnership, or association?

<p>They can only work on civil engineering projects (A)</p> Signup and view all the answers

What is the requirement for a person to be a member or partner of a firm, partnership, or association for civil engineering?

<p>They must be a duly licensed civil engineer or architect (B)</p> Signup and view all the answers

What is the contractor's responsibility regarding claims of infringement?

<p>To render harmless and indemnify the owner (C)</p> Signup and view all the answers

Who is responsible for paying compensation for materials required for permanent works?

<p>The contractor (B)</p> Signup and view all the answers

What is the percentage of Value Added Tax (VAT) the contractor shall pay?

<p>10% (B)</p> Signup and view all the answers

What is included in the costs the contractor shall bear?

<p>All costs, duties, fees, and other charges (C)</p> Signup and view all the answers

Who is responsible for securing necessary permits and licenses?

<p>The contractor (B)</p> Signup and view all the answers

What type of insurance shall the contractor pay for?

<p>Insurance arising out of the contract (A)</p> Signup and view all the answers

What is a ground for termination of contracts in case of procurement of goods?

<p>Failure to deliver at least 10% of the contract price (C)</p> Signup and view all the answers

What can be a result of collusion between public officers, Procuring Entity employees, or BAC and bidders?

<p>Restricting, suppressing, or nullifying competition (B)</p> Signup and view all the answers

What is a ground for termination of contracts in case of infrastructure?

<p>Negative slippage of 15% or more while project is ongoing (A)</p> Signup and view all the answers

What is a reason for contract termination in contracts for Consulting Services?

<p>Failure to deliver or perform the Outputs and Deliverables within the period (C)</p> Signup and view all the answers

What is another ground for contract termination?

<p>Insolvency of the supplier, contractor or consultant (A)</p> Signup and view all the answers

What is another ground for termination of contracts?

<p>Splitting of government project for convenience (C)</p> Signup and view all the answers