In Hot-standby mode, what happens to track vacancy detection in case of failure of one DP?
In Hot-standby mode, what happens to track vacancy detection in case of failure of one DP?
What is the purpose of providing redundancy in Track circuits/Axle Counters in the Automatic Section?
What is the purpose of providing redundancy in Track circuits/Axle Counters in the Automatic Section?
What is the purpose of Supervisory track sections?
What is the purpose of Supervisory track sections?
What is the purpose of the resetting facility in individual track sections?
What is the purpose of the resetting facility in individual track sections?
Signup and view all the answers
How many track sections are covered by a single Supervisory track section?
How many track sections are covered by a single Supervisory track section?
Signup and view all the answers
What connects the main DPS of UP and DOWN direction?
What connects the main DPS of UP and DOWN direction?
Signup and view all the answers
What is the purpose of providing a Track Indicator in Automatic Signalling on Single Line?
What is the purpose of providing a Track Indicator in Automatic Signalling on Single Line?
Signup and view all the answers
What is the purpose of media diversity in Axle Counters?
What is the purpose of media diversity in Axle Counters?
Signup and view all the answers
What is the purpose of COM-AdC board in MSDACs?
What is the purpose of COM-AdC board in MSDACs?
Signup and view all the answers
What happens if one COM-AdC board fails?
What happens if one COM-AdC board fails?
Signup and view all the answers
What is the purpose of the 'A' marker on an Automatic Stop Signal?
What is the purpose of the 'A' marker on an Automatic Stop Signal?
Signup and view all the answers
What is the purpose of the ethernet switch in Fig. 4?
What is the purpose of the ethernet switch in Fig. 4?
Signup and view all the answers
What is the purpose of the enamelled yellow disc with letters 'G' in black on a Semi-Automatic Stop Signal?
What is the purpose of the enamelled yellow disc with letters 'G' in black on a Semi-Automatic Stop Signal?
Signup and view all the answers
What is the purpose of the 'A' marker light on a Semi-Automatic Stop Signal interlocked with a level-crossing?
What is the purpose of the 'A' marker light on a Semi-Automatic Stop Signal interlocked with a level-crossing?
Signup and view all the answers
Where are the Vital Relays (ACPRs) of each track section picked up?
Where are the Vital Relays (ACPRs) of each track section picked up?
Signup and view all the answers
What is the purpose of providing individual track sections in each direction with resetting facility?
What is the purpose of providing individual track sections in each direction with resetting facility?
Signup and view all the answers
What is the primary purpose of providing track status information at stations?
What is the primary purpose of providing track status information at stations?
Signup and view all the answers
What is the main function of supervisory track sections in automatic signalling?
What is the main function of supervisory track sections in automatic signalling?
Signup and view all the answers
What is the primary purpose of manual reset procedures in automatic signalling?
What is the primary purpose of manual reset procedures in automatic signalling?
Signup and view all the answers
What is the primary function of axle counters in automatic signalling?
What is the primary function of axle counters in automatic signalling?
Signup and view all the answers
What is the primary purpose of automatic reset systems in individual track sections?
What is the primary purpose of automatic reset systems in individual track sections?
Signup and view all the answers
What is the primary purpose of track section management in automatic signalling?
What is the primary purpose of track section management in automatic signalling?
Signup and view all the answers
What is the primary purpose of level crossing gates in automatic signalling?
What is the primary purpose of level crossing gates in automatic signalling?
Signup and view all the answers
What is the primary purpose of providing LED signal lamps in automatic signalling?
What is the primary purpose of providing LED signal lamps in automatic signalling?
Signup and view all the answers
What is the purpose of the L-I automatic reset feature?
What is the purpose of the L-I automatic reset feature?
Signup and view all the answers
What happens when a supervisory track section is clear according to the L-II automatic reset feature?
What happens when a supervisory track section is clear according to the L-II automatic reset feature?
Signup and view all the answers
What is the condition for a track section to be reset using the L-II automatic reset feature?
What is the condition for a track section to be reset using the L-II automatic reset feature?
Signup and view all the answers
What is the purpose of the L-III manual reset feature?
What is the purpose of the L-III manual reset feature?
Signup and view all the answers
What happens to a track section under reset using the L-I automatic reset feature?
What happens to a track section under reset using the L-I automatic reset feature?
Signup and view all the answers
What is required for a track section to be reset using the L-II automatic reset feature with a supervisory track section?
What is required for a track section to be reset using the L-II automatic reset feature with a supervisory track section?
Signup and view all the answers
What is the condition for manual reset to be carried out?
What is the condition for manual reset to be carried out?
Signup and view all the answers
What is the purpose of the supervisory track section in the L-II automatic reset feature?
What is the purpose of the supervisory track section in the L-II automatic reset feature?
Signup and view all the answers
What is the minimum frequency of testing for Track Circuit control on signal and aspect control by signals in advance?
What is the minimum frequency of testing for Track Circuit control on signal and aspect control by signals in advance?
Signup and view all the answers
What should be done after every track renewal work to ensure proper working of track circuits/Axle counters?
What should be done after every track renewal work to ensure proper working of track circuits/Axle counters?
Signup and view all the answers
What should be done to the 'A' marker of the Advanced Starter Signal of the station in rear and Home signal of the station in advance during abnormal conditions?
What should be done to the 'A' marker of the Advanced Starter Signal of the station in rear and Home signal of the station in advance during abnormal conditions?
Signup and view all the answers
What is the purpose of the Interlocking equipments and circuits for level crossings and points?
What is the purpose of the Interlocking equipments and circuits for level crossings and points?
Signup and view all the answers
What should be done to failures reported by the Loco Pilots/Motor man?
What should be done to failures reported by the Loco Pilots/Motor man?
Signup and view all the answers
What is the purpose of the Axle Counter resetting circuits?
What is the purpose of the Axle Counter resetting circuits?
Signup and view all the answers
What should be done to the Power Supply system?
What should be done to the Power Supply system?
Signup and view all the answers
What should be done to the Cables system?
What should be done to the Cables system?
Signup and view all the answers
What is the purpose of L-I automatic reset feature?
What is the purpose of L-I automatic reset feature?
Signup and view all the answers
What is required for a track section to be reset using the L-II automatic reset feature?
What is required for a track section to be reset using the L-II automatic reset feature?
Signup and view all the answers
What happens to a track section under reset using the L-I automatic reset feature?
What happens to a track section under reset using the L-I automatic reset feature?
Signup and view all the answers
What is the condition for manual reset to be carried out?
What is the condition for manual reset to be carried out?
Signup and view all the answers
What is the purpose of the L-III manual reset feature?
What is the purpose of the L-III manual reset feature?
Signup and view all the answers
What happens when a supervisory track section is clear according to the L-II automatic reset feature?
What happens when a supervisory track section is clear according to the L-II automatic reset feature?
Signup and view all the answers
What is the primary purpose of the automatic reset systems in individual track sections?
What is the primary purpose of the automatic reset systems in individual track sections?
Signup and view all the answers
What is the condition for a track section to be reset using the L-II automatic reset feature with a supervisory track section?
What is the condition for a track section to be reset using the L-II automatic reset feature with a supervisory track section?
Signup and view all the answers
What should be the design principle of fail-safe circuits?
What should be the design principle of fail-safe circuits?
Signup and view all the answers
What is the primary purpose of double cutting arrangements in external circuits?
What is the primary purpose of double cutting arrangements in external circuits?
Signup and view all the answers
When a signal is working as an automatic signal, what is the condition for the illuminated 'A' marker to light up?
When a signal is working as an automatic signal, what is the condition for the illuminated 'A' marker to light up?
Signup and view all the answers
What should happen to the signal if a lamp of the aspect displayed fails?
What should happen to the signal if a lamp of the aspect displayed fails?
Signup and view all the answers
What should happen to a signal which must display a red aspect if it does not do so for any reason?
What should happen to a signal which must display a red aspect if it does not do so for any reason?
Signup and view all the answers
What should be done to ensure the correct setting and locking of the points as required?
What should be done to ensure the correct setting and locking of the points as required?
Signup and view all the answers
What should be done to the circuit for illuminated 'A' marker of a Semi-Automatic Signal?
What should be done to the circuit for illuminated 'A' marker of a Semi-Automatic Signal?
Signup and view all the answers
What is the primary purpose of providing LED signal lamps in automatic signalling?
What is the primary purpose of providing LED signal lamps in automatic signalling?
Signup and view all the answers
What is the primary requirement for cables in signalling?
What is the primary requirement for cables in signalling?
Signup and view all the answers
What is the primary requirement for power supply in signalling?
What is the primary requirement for power supply in signalling?
Signup and view all the answers
What is the primary purpose of manual reset with line verification?
What is the primary purpose of manual reset with line verification?
Signup and view all the answers
What is the primary purpose of automatic resetting?
What is the primary purpose of automatic resetting?
Signup and view all the answers
How frequently should Track Circuit control on signal and aspect control by signals in advance be tested?
How frequently should Track Circuit control on signal and aspect control by signals in advance be tested?
Signup and view all the answers
What should be done after every track renewal work?
What should be done after every track renewal work?
Signup and view all the answers
What should be done to the 'A' marker of the Advanced Starter Signal of the station in rear and Home signal of the station in advance during abnormal conditions?
What should be done to the 'A' marker of the Advanced Starter Signal of the station in rear and Home signal of the station in advance during abnormal conditions?
Signup and view all the answers
What should be done to failures reported by the Loco Pilots/Motor man?
What should be done to failures reported by the Loco Pilots/Motor man?
Signup and view all the answers
What is the voltage range required for MSDAC to operate?
What is the voltage range required for MSDAC to operate?
Signup and view all the answers
What is the purpose of the Mini IPS at each AG location?
What is the purpose of the Mini IPS at each AG location?
Signup and view all the answers
What type of cable is used to connect the MSDAC evaluator to each DP?
What type of cable is used to connect the MSDAC evaluator to each DP?
Signup and view all the answers
What is the condition for manual reset to be carried out?
What is the condition for manual reset to be carried out?
Signup and view all the answers
What is the purpose of the reset box at the train sending station?
What is the purpose of the reset box at the train sending station?
Signup and view all the answers
What is the purpose of the Line Verification (LV) box at the other station?
What is the purpose of the Line Verification (LV) box at the other station?
Signup and view all the answers
What is the input supply voltage for the Mini IPS?
What is the input supply voltage for the Mini IPS?
Signup and view all the answers
What is the purpose of the cable from AG to Half location box?
What is the purpose of the cable from AG to Half location box?
Signup and view all the answers
What is the primary purpose of providing a Track Indicator in Automatic Signalling on Single Line?
What is the primary purpose of providing a Track Indicator in Automatic Signalling on Single Line?
Signup and view all the answers
What is the purpose of providing media diversity in Axle Counters?
What is the purpose of providing media diversity in Axle Counters?
Signup and view all the answers
What is the primary purpose of providing redundancy in Track circuits/Axle Counters in the Automatic Section?
What is the primary purpose of providing redundancy in Track circuits/Axle Counters in the Automatic Section?
Signup and view all the answers
What is the primary purpose of automatic reset systems in individual track sections?
What is the primary purpose of automatic reset systems in individual track sections?
Signup and view all the answers
What is the primary purpose of providing individual track sections in each direction with resetting facility?
What is the primary purpose of providing individual track sections in each direction with resetting facility?
Signup and view all the answers
What is the purpose of the 'A' marker on an Automatic Stop Signal?
What is the purpose of the 'A' marker on an Automatic Stop Signal?
Signup and view all the answers
What is the purpose of the enamelled yellow disc with letters 'G' in black on a Semi-Automatic Stop Signal?
What is the purpose of the enamelled yellow disc with letters 'G' in black on a Semi-Automatic Stop Signal?
Signup and view all the answers
What is the primary purpose of manual reset with line verification?
What is the primary purpose of manual reset with line verification?
Signup and view all the answers
Study Notes
Automatic Block Signalling
- Design of Axle Counters between two adjacent stations allows for individual track sections in each direction to have resetting facility from dispatching end station master in case of failure of equipment.
- Redundancy may be provided in Track circuits/Axle Counters in the Automatic Section to improve availability.
- Media diversity shall preferably be provided for Axle Counters.
- Track indicator for Automatic Signalling on Single Line: an indicator shall be provided at each station to indicate whether the block section is occupied or clear.
Markers
- Each Automatic Stop Signal shall be identified by its number and provided with a Marker consisting of a white disc with letter ‘A’ in black.
- A Semi-Automatic Stop Signal shall be provided with a Marker which shall show a white illuminated letter ‘A’ against a black background when the signal works as an Automatic Stop Signal.
- A Signal interlocked with a level-crossing shall be provided with a yellow disc with letters ‘G’ in black and an ‘A’ marker light.
Track Sections and Supervisory Track Sections
- No separate track section has been made for overlap portion of auto-sections.
- A single track section includes route as well as overlap of a signal.
- Supervisory track sections have been formed using the DPs of track sections for automatically resetting the track sections.
- Each supervisory track section covers two (02) track sections.
- Supervisory track sections have overlapping boundaries.
Evaluator (EV) and OFC
- Two evaluators (EVs) (M&R) are provided in each AG as well as adjacent stations.
- The main DPS of UP and DOWN direction are connected to EV(M) and redundant(R) DPs of UP and DOWN direction are connected to EV(R).
- The MSDACs used in the present scheme have one dedicated COM-AdC board with ethernet port to communicate with adjacent EVs.
Reset Features of MSDAC
- Reset arrangement is proposed at three levels using Track Sections and Supervisory Track Sections, two of which are automatic reset arrangements and one is manual reset.
- L-I: Automatic reset with redundant track section.
- L-II: Automatic reset with Supervisory track section.
- L-III: Manual Reset with Line verification.
Testing and Maintenance
- The following shall be tested by the SSE/JE (Signal) at least once in a year:
- Track Circuit control on signal and aspect control by signals in advance.
- Automatic Cutting-in of the next restrictive aspect when the LED aspect of the main signal fails.
- Interlocking equipments and circuits for level crossings and points.
- The circuits that establish the direction of traffic in Single Line and prevent clearing of conflicting signals on sections provided with Automatic block Signalling on Single Line.
- Axle Counter resetting circuits, if provided.
- All failures reported by the Loco Pilots/Motor man shall be promptly attended.
- Adequate precautions should be taken after every track renewal work to ensure proper working of track circuits/Axle counters.
Power Supply, Cables, and Installation
- Provisions contained in Chapter 16 of SEM shall be adhered to for Power Supply.
- Provisions contained in Chapter 15 of SEM shall be adhered to for Cables.
- Provisions contained in Chapter 17 of SEM shall be adhered to for Track Circuits.
- Provisions contained in Chapter 22 of SEM shall be adhered to for Installation in 25 KV AC electrified areas.
- Extant guidelines on Installation, Testing & Commissioning shall be adhered to.
Modified Semi-Automatic Signalling Working
- Under special instructions, one of the automatic stop signals between two stations in the automatic block signalling territory on Double Line may be made as modified semi-automatic stop signal in each direction.
- The relevant information of Automatic Signalling gears in section should be available/visible at station like Signals Aspects, track status information, Axle Counter reset information, and gate information.
Automatic Block Signalling
- The status of vital relays is read by OCs (Operation Control) and transmitted to the Central Interlocking Unit for logic processing.
- The status of aspects is sent back to corresponding OCs for driving Automatic Signals.
- Reset features of MSDAC (Microprocessor-based Signalling and Digital Axle Counter) include:
- Automatic reset with redundant track section (L-I)
- Automatic reset with Supervisory track section (L-II)
- Manual reset with Line verification (L-III)
Reset Features
- L-I: Automatic reset with redundant track section
- Once the train has cleared both track sections, and any one of the track sections is in failure state, the track section in clear condition will reset the one in fail condition.
- The track section under reset is kept in preparatory mode, and the clear track section information is used to clear the signal.
- L-II: Automatic reset with Supervisory track section
- When a supervisory track section is clear, all the track sections falling completely within the jurisdiction of that supervisory track section can be assumed to be clear.
- If any track section fails and its corresponding supervisory track section is clear, it will automatically reset the failed track section.
- L-III: Manual reset with Line verification
- In case of failure of Level-1 and Level-2 reset, manual resetting has to be carried out, which resets all the track sections in the section under consideration.
Fail-Safe Circuits
- All fail-safe circuits shall work on continuously energized principle.
- Any open circuit in wiring, relay contacts, etc., or loss of power supplies shall not cause an unsafe condition.
Signal Display
- An automatic signal on a double line/single line shall require all tracks to be clear up to the next signal and an adequate distance beyond, before it can display 'OFF' position.
- In case of Single Line, direction of traffic shall also be established.
LED Signals
- LED signals of approved type by RDSO (Research, Designs and Standards Organisation) shall be used.
- All external circuits shall be provided with double cutting arrangements.
Circuit Design
- The circuits shall be so designed that, if the lamp of the aspect displayed fails, the signal shall immediately assume the next restrictive aspect.
- If a signal which must display red aspect does not do so for any reason, the signal in rear shall display a red aspect.
'A' Marker and 'AG' Marker
- The circuit for illuminated 'A' marker of a Semi-Automatic Signal shall be such that the 'A' marker lights up only when the signal is working as an automatic signal.
- The circuit for illuminated 'AG' marker where provided shall be such that the 'AG' marker lights up only when the conditions for 'A' Marker to light up are satisfied except for the level crossing gate which may either be open to road traffic or may have failed.
Power Supply Arrangement
- Each AG is provided with a Mini IPS, for which the input supply of 230 V AC is from UP AT and DN AT at each location.
- The necessary power supplies for EI OCs and MSDAC are derived from the Mini IPS.
- MSDAC works on a voltage range of 19-72 V DC.
- Hence, 24 V DC supply with suitable current capacity from Mini IPS serves the purpose.
Cable Requirement
- Signaling Cable: In the stations, Home & Advance starter signals are directly fed from the EI/Relay room with standard signaling cable, with aspect repeating relays at signal locations.
- Automatic Signals at AG are directly fed using a 12 x 1.5 Sq.mm signaling cable from AG, without any repeater relay at site, as the distance is not more than 200 meters.
- Quad Cable: MSDAC evaluator to each DP requires 1 quad of 4 conductor.
- A separate 6 quad cable is used for each DP of dual detection (main + Stand-by) from the nearest Half location box provided for Signal cable termination at signal location.
Testing and Maintenance
- The following shall be tested by the SSE/JE (Signal) at least once in a year:
- Track Circuit control on signal and aspect control by signals in advance.
- Automatic Cutting-in of the next restrictive aspect when the LED aspect of the main signal fails.
- Interlocking equipments and circuits for level crossings and points.
- The circuits that establish the direction of traffic in Single Line and prevent clearing of conflicting signals on sections provided with Automatic block Signalling on Single Line.
- Axle Counter resetting circuits, if provided.
- All failures reported by the Loco Pilots/Motor man shall be promptly attended.
- Track Circuits/Axle Counter Maintenance:
- Adequate precautions should be taken after every track renewal work to ensure proper working of track circuits/Axle counters.
- Provisions contained in Chapter 17 of SEM shall be adhered to.
Modified Semi-Automatic Signalling Working
- Under special instructions, one of the automatic stop signals between two stations in the automatic block signalling territory on Double Line may be made as modified semi-automatic stop signal in each direction.
- During abnormal conditions like fog, bad weather impairing visibility, Modified Semi-Automatic Signal may be worked by extinguishing ‘A’ marker in the manner prescribed under special instructions.
- The design of the Axle Counters between two adjacent stations shall be such that individual track sections in each direction shall have resetting facility from dispatching end station master in case of failure of equipment, with co-operation of receiving end station master for verification of last vehicle.
- Redundancy may be provided in Track circuits/Axle Counters in the Automatic Section to improve availability.
- Media diversity shall preferably be provided for Axle Counters.
- Track indicator for Automatic Signalling on Single Line: An indicator shall be provided at each station to indicate whether the block section is occupied or clear.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the design and operation of track circuits and axle counters in railway signaling systems, including their functionality and failure recovery.