quiz image

Railway Maintenance

SolicitousOklahomaCity avatar
SolicitousOklahomaCity
·
·
Download

Start Quiz

Study Flashcards

40 Questions

What should be removed in time to avoid short-circuiting?

Metal burrs at the end

Why should ballast be clean in the vicinity of glued insulated joints?

To ensure efficient packing and drainage

What happens in case of failure of glued joints?

The fishplates crack or break

What should be kept free from brake dust, dirt, sand, rust, etc.?

Rail ends

How should PSC Sleepers be laid and maintained?

Square to the rails on straights and radially on curves

What is recommended while carrying out track renewals with concrete sleepers?

Relaying with Mechanical Equipment

What should be kept clean with efficient drainage?

The track at glued joint and its vicinity

What is the purpose of heaping up of ballast in the tamping zone?

To ensure effective packing

What is the purpose of refurbishing a glued joint?

To repair the damaged glued joint

What is done to hogged joints before tamping?

Attention is given to them

What is done to broken and damaged sleepers?

They are renewed

Why are obstructions such as signal rods, cables, pipes, level crossing check rails, etc., removed?

To avoid damage by the tampers

What should be marked on every second/third sleeper?

The slew, super elevation and lift value

What should be the tamping depth during tamping?

15 mm to 20 mm

Why is it important to ensure that tamping tools are inserted centrally between the sleepers?

To avoid damage to the sleepers

Who should be informed about the beginning and end of transitions?

The tamping machine operator

What is the recommended minimum depth of clean ballast cushion below the bottom of sleepers for proper functioning of tie tampers?

150 mm

What is the purpose of deep screening of ballast?

To ensure adequate ballast in the shoulders and cribs

Who is responsible for providing adequate time for economical working of tamping machines?

Both the Operating Department and the Engineering Department

What is the purpose of pre-tamping attention?

To achieve good results from tamping

What should be done before taking up the tamping?

Carry out the preparatory work such as ballasting

What should be followed during packing in LWR/CWR track?

Part D of Chapter 3

Why should small track machines be deployed?

For carrying out various operations

What should be done to ensure that adequate time is available for economical working of tamping machines?

Provide time allowance in the working timetable

What should be done to plan the deployment of tamping machines for plain track and Points & Crossings?

All of the above

What should the Gang Mate and Track Maintainers do during the passage of trains?

Stand on the cess and observe the movement of sleepers

Why is firm and uniform packing necessary?

For good track maintenance

What is the purpose of systematic tamping of plain track and Points & Crossings?

To maintain the track in good condition

What is the purpose of systematic overhauling?

To overhaul the entire track section within a specific period

What should be shifted to shoulders for screening by the machine?

Crib ballast

How often should loop lines be shallow screened/overhauled?

Once in 7 years

What is the first operation in the sequence of overhauling?

Shallow screening and making up of ballast

What is the ratio of sleepers in the turnout portion for a 1 in 8½ turnout?

1 to 13

How should the sleepers in the crossing portion be placed?

Perpendicular to the bisector line of the crossing angle

What is the purpose of the approach sleepers in advance of the switch portion?

To provide a smooth transition to the turnout

How should the complete assembled turnout be inserted in position?

By using a T-28 machine or cranes or rollers

What should be done to ensure the alignment and level of the sleepers during manual insertion?

Check the alignment and level at no time beyond permissible limits

What should be provided behind the crossing portion to introduce rail slope?

Exit sleepers

What is the recommended way to provide motor housing in the switch portion?

By placing long sleepers in the reverse direction

What is the recommended way to break down the complete assembled turnout for insertion?

Into three panels

Study Notes

Maintenance of Rail Joints

  • Metal burrs at the end of rail joints should be removed in time to avoid short-circuiting.
  • Fish bolts at insulated joints must be kept tight, and sleepers packed well in the vicinity of joints.
  • Rail ends should be kept free from brake dust, dirt, sand, rust, and other foreign materials.

Maintenance of Glued Insulated Joints

  • Ballast used in track in the vicinity of glued insulated joints should be clean to ensure efficient packing and drainage.
  • Care should be taken to ensure that the ballast is clear of rails and rail fastenings.
  • In glued joints, no relative movement occurs between rails and fishplates; if failure occurs, the damaged joint shall be refurbished/replaced.

Laying of PSC Plain Track Sleepers

  • PSC Sleepers shall be laid and maintained square to the rails on straights and radially on curves, and rail joints should be suspended.
  • Relaying with Mechanical Equipment should be adopted while carrying out track renewals with concrete sleepers.
  • The preliminary work prior to relaying at site, the actual relaying process, and the post-relaying operations are described in detail in “IRTMM”.

Systematic Tamping of Plain Track and Points & Crossings

  • Systematic tamping of plain track and Points & Crossings should be planned on long continuous lengths based on results of TRC/OMS.
  • Deployment of Tamping Machines should be based on results of TRC/OMS, past history of deterioration of track, traffic GMT, type of formation, condition of track and its components.

Pre-requisites to Introduction of Mechanical Maintenance

  • A minimum depth of 150 mm of clean ballast cushion below the bottom of the sleepers is recommended for the proper functioning of the tie tampers.
  • Adequate ballast should be available in the shoulders and cribs.
  • Time allowance for working the machines should be provided in the working timetable.
  • It is the responsibility of both the Operating Department and the Engineering Department to ensure provision of adequate time for economical working of machines.

Pre-tamping Attention

  • Ballasting where there is a shortage of ballast.
  • Heaping up of ballast in the tamping zone to ensure effective packing.
  • Making up of low cess.
  • Cleaning of pumping joints and providing additional clean ballast, where necessary.
  • Attention to hogged joints before tamping.
  • Tightening of all fittings and fastenings like fish bolts and elastic fastenings and replacement of worn-out fittings.
  • Renewing broken and damaged sleepers.
  • Squaring of sleepers and spacing adjustment; re-gauging to be done as necessary.
  • Adjusting creep and expansion gap in rails.
  • Examination of rails for cracks, sleepers, and fastenings, etc.
  • Survey for Realignment of curves, which are badly out of alignment.
  • Clearing of ballast on sleepers to make them visible to the operator.
  • All obstructions such as signal rods, cables, pipes, level crossing check rails, joggled fish plates, etc., likely to be damaged by the tampers should be preferably removed.

Observance of Sleepers under Passage of Traffic

  • Gang Mate and Track Maintainers should stand on the cess each about one rail-length apart on either side of the portion of track they are attending to, and observe the movement of sleepers under load.
  • Immediately after the passing of the train, loose sleepers should be marked, packed uniformly, and the packing tested.

Systematic Overhauling

  • The length of the section to be overhauled shall be such that complete overhauling of track will be accomplished within a specific period (normally 3 to 5 years).
  • Overhauling should be done using SBCM for cleaning of shoulder ballast.
  • The crib ballast should also be shifted to shoulders for screening by the machine, which should again be put back in crib portion.

This quiz covers the maintenance of railway tracks, including the removal of metal burrs, tightening of fish bolts, and cleaning of rail ends.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Railway Track Maintenance and Machine Operations
118 questions
Railway Maintenance Procedures
40 questions

Railway Maintenance Procedures

SolicitousOklahomaCity avatar
SolicitousOklahomaCity
Railway Track Maintenance Types
40 questions

Railway Track Maintenance Types

SolicitousOklahomaCity avatar
SolicitousOklahomaCity
Railway Track Maintenance and Alignment
38 questions
Use Quizgecko on...
Browser
Browser