Podcast
Questions and Answers
What is the purpose of regulating equipment in an overhead equipment system?
What is the purpose of regulating equipment in an overhead equipment system?
- To support the suspension system at higher altitudes.
- To prevent electrical current leakage between sections.
- To increase the overall voltage of the overhead lines.
- To maintain the tension of OHE conductors constant under varying temperatures. (correct)
What does the term 'stagger' refer to in the context of overhead equipment?
What does the term 'stagger' refer to in the context of overhead equipment?
- The angle at which the contact wire must be installed.
- The vertical alignment of the traction mast to the catenary wire.
- The distance between two adjacent supporting masts.
- The horizontal distance of the contact wire from a specified vertical plane. (correct)
What is a section insulator used for in overhead equipment?
What is a section insulator used for in overhead equipment?
- To regulate the voltage supplied to the contacting wire.
- To insulate two electrical sections while enabling continuous pantograph operation. (correct)
- To allow for the maintenance of the contact wire without affecting current flow.
- To connect multiple feeding posts to a single overhead line.
What is the significance of 'setting distance' in overhead equipment installation?
What is the significance of 'setting distance' in overhead equipment installation?
What components are typically found in a supply control post?
What components are typically found in a supply control post?
What defines the term 'suspension distance' in the context of catenary systems?
What defines the term 'suspension distance' in the context of catenary systems?
What is considered a 'span' in an overhead equipment system?
What is considered a 'span' in an overhead equipment system?
What is the maximum suspension distance for a bracket assembly designed without additional specifications?
What is the maximum suspension distance for a bracket assembly designed without additional specifications?
In which scenarios may the minimum setting distance of masts from the center line of the tangent track be reduced?
In which scenarios may the minimum setting distance of masts from the center line of the tangent track be reduced?
What type of insulators should be utilized in heavily polluted areas such as tunnels and near chemical plants?
What type of insulators should be utilized in heavily polluted areas such as tunnels and near chemical plants?
What is the standard setting distance for mast placement on broad gauge tangent track?
What is the standard setting distance for mast placement on broad gauge tangent track?
What should be added to the setting distance on curves to determine the minimum setting distance of masts?
What should be added to the setting distance on curves to determine the minimum setting distance of masts?
What is the wind pressure for structures in the yellow zone according to the specified standards?
What is the wind pressure for structures in the yellow zone according to the specified standards?
How is the total projected area for fabricated structures calculated for wind loading?
How is the total projected area for fabricated structures calculated for wind loading?
What is the recommended method for measuring spans on a curve for an odd number of tracks?
What is the recommended method for measuring spans on a curve for an odd number of tracks?
What is the maximum allowed wind pressure for safety checks at 4 degree C temperature?
What is the maximum allowed wind pressure for safety checks at 4 degree C temperature?
Which diagram number corresponds with the standard spans for regulated tramway OHE?
Which diagram number corresponds with the standard spans for regulated tramway OHE?
How much are wind pressures for structures under 30 meters reduced as per the amendment issued in 1971?
How much are wind pressures for structures under 30 meters reduced as per the amendment issued in 1971?
What should be taken into consideration when determining the length of the span?
What should be taken into consideration when determining the length of the span?
What type of screens should be used for protection when clearance is not obtained?
What type of screens should be used for protection when clearance is not obtained?
When calculating wind loading for conductors and other circular members, what area is considered?
When calculating wind loading for conductors and other circular members, what area is considered?
What type of masts can be used in lieu of K-series masts?
What type of masts can be used in lieu of K-series masts?
In the context of masts for single OHE applications, what wind pressure level corresponds with Drg.No.ETI/C/0702?
In the context of masts for single OHE applications, what wind pressure level corresponds with Drg.No.ETI/C/0702?
What is used in lieu of 200x150 RSJ as specified in mast employment schedules?
What is used in lieu of 200x150 RSJ as specified in mast employment schedules?
What should be considered when designing masts for locations such as turnouts and diamond crossings?
What should be considered when designing masts for locations such as turnouts and diamond crossings?
For heavy wind pressure, which drawing number is referenced?
For heavy wind pressure, which drawing number is referenced?
What is the permissible bending moment for masts found in?
What is the permissible bending moment for masts found in?
What should NOT be considered for masts on long bridges or near their abutments?
What should NOT be considered for masts on long bridges or near their abutments?
What is the tension in each conductor for Composite OHE masts?
What is the tension in each conductor for Composite OHE masts?
Which drawing number is used for medium wind pressure applications?
Which drawing number is used for medium wind pressure applications?
What type of wire is mentioned for use in standard mast applications?
What type of wire is mentioned for use in standard mast applications?
What is the minimum distance that masts should be located from a signal post?
What is the minimum distance that masts should be located from a signal post?
Where should masts not be located according to safety regulations?
Where should masts not be located according to safety regulations?
What type of support is recommended for overhead equipment in tunnels?
What type of support is recommended for overhead equipment in tunnels?
What materials are specified for the cantilever bracket assembly?
What materials are specified for the cantilever bracket assembly?
What should be done if masts need to be located in areas of bad formations?
What should be done if masts need to be located in areas of bad formations?
What is the role of the distance between masts and level crossings?
What is the role of the distance between masts and level crossings?
What should be done with core holes on piers that are not used for foundation?
What should be done with core holes on piers that are not used for foundation?
What is the minimum distance for the location of masts on bridges?
What is the minimum distance for the location of masts on bridges?
What is a necessary condition for providing independent masts on multi-track sections?
What is a necessary condition for providing independent masts on multi-track sections?
What should be considered when arranging cantilevers on platforms?
What should be considered when arranging cantilevers on platforms?
What is the primary function of the 10 KVA LT supply transformer in substations?
What is the primary function of the 10 KVA LT supply transformer in substations?
How are LT supply transformers protected on the primary side?
How are LT supply transformers protected on the primary side?
In the context of mast and rail bonds, what bonding is required for traction masts?
In the context of mast and rail bonds, what bonding is required for traction masts?
What type of wiring is specified for the 63 A fuse on the secondary side of LT supply transformers?
What type of wiring is specified for the 63 A fuse on the secondary side of LT supply transformers?
What transformer capacity is specified for providing power to filtration plants at substations?
What transformer capacity is specified for providing power to filtration plants at substations?
What is a characteristic feature of a regulated OHE system?
What is a characteristic feature of a regulated OHE system?
What is the main function of a sectioning and paralleling post (SP)?
What is the main function of a sectioning and paralleling post (SP)?
How is 'span' defined in the context of overhead equipment?
How is 'span' defined in the context of overhead equipment?
What does the stagger of the contact wire directly influence?
What does the stagger of the contact wire directly influence?
Which of the following accurately describes 'suspension distance' in a catenary system?
Which of the following accurately describes 'suspension distance' in a catenary system?
What distinguishes a supply control post from a regular post?
What distinguishes a supply control post from a regular post?
What does the term 'setting distance' specifically refer to during installation?
What does the term 'setting distance' specifically refer to during installation?
What percentage reduction in wind pressures applies to structures under 30 meters in height according to amendments issued in 1971?
What percentage reduction in wind pressures applies to structures under 30 meters in height according to amendments issued in 1971?
When calculating wind loading, what percentage of the projected area is considered for fabricated structures?
When calculating wind loading, what percentage of the projected area is considered for fabricated structures?
What is the designated wind pressure in the red zone for structural design?
What is the designated wind pressure in the red zone for structural design?
Which condition must be checked for the safety of masts during wind loading calculations?
Which condition must be checked for the safety of masts during wind loading calculations?
For what purpose should spans be accurately measured using a steel tape?
For what purpose should spans be accurately measured using a steel tape?
What type of wind load is applied in the yellow zone for structural safety?
What type of wind load is applied in the yellow zone for structural safety?
Which drawing corresponds to the standard spans for composite OHE?
Which drawing corresponds to the standard spans for composite OHE?
What is the influence of curvature on the length of the spans for overhead equipment?
What is the influence of curvature on the length of the spans for overhead equipment?
What safety measure is required if clearance is not obtained?
What safety measure is required if clearance is not obtained?
What is the minimum static clearance from an earthed structure for the return conductor?
What is the minimum static clearance from an earthed structure for the return conductor?
In complicated track layouts, how should the route of the return conductor be determined?
In complicated track layouts, how should the route of the return conductor be determined?
What is the minimum required vertical clearance between the return conductor and overhead equipment?
What is the minimum required vertical clearance between the return conductor and overhead equipment?
Where should the return conductor be connected to the buried rail?
Where should the return conductor be connected to the buried rail?
What should be avoided when routing the return conductor in station areas?
What should be avoided when routing the return conductor in station areas?
What is required at all booster stations for the return conductors?
What is required at all booster stations for the return conductors?
What is the purpose of connecting the return conductor in series with the secondary winding of the booster transformer?
What is the purpose of connecting the return conductor in series with the secondary winding of the booster transformer?
What relationship does the return conductor have with subsidiary lines such as sidings or loops?
What relationship does the return conductor have with subsidiary lines such as sidings or loops?
What is defined as the mid-point of the return conductor?
What is defined as the mid-point of the return conductor?
How should return conductors be terminated at masts?
How should return conductors be terminated at masts?
What is the recommended encumbrance for a 54.0 m span under an over-line structure?
What is the recommended encumbrance for a 54.0 m span under an over-line structure?
What is the largest permissible adjacent span for both 63.0 m and 58.5 m under over-line structures?
What is the largest permissible adjacent span for both 63.0 m and 58.5 m under over-line structures?
If the encumbrance cannot be increased beyond 1.40 m from the value given for a 54.0 m span, what is the applicable condition noted?
If the encumbrance cannot be increased beyond 1.40 m from the value given for a 54.0 m span, what is the applicable condition noted?
What is the recommended encumbrance for a span of 36.0 m under an over-line structure?
What is the recommended encumbrance for a span of 36.0 m under an over-line structure?
For a 31.5 m span, what is the recommended encumbrance under an over-line structure?
For a 31.5 m span, what is the recommended encumbrance under an over-line structure?
What is the recommended encumbrance for a span of 49.5 m under an over-line structure?
What is the recommended encumbrance for a span of 49.5 m under an over-line structure?
What is the discrepancy in encumbrance recommended between spans of 63.0 m and 58.5 m under over-line structures?
What is the discrepancy in encumbrance recommended between spans of 63.0 m and 58.5 m under over-line structures?
What is the relationship between the span of a structure and its recommended encumbrance?
What is the relationship between the span of a structure and its recommended encumbrance?
Which encumbrance value is recommended for spans shorter than 27.0 m under over-line structures?
Which encumbrance value is recommended for spans shorter than 27.0 m under over-line structures?
Across different spans, what is the maximum encumbrance value observed for spans ranging from 1 m to 63 m under over-line structures?
Across different spans, what is the maximum encumbrance value observed for spans ranging from 1 m to 63 m under over-line structures?
Flashcards
Structure Protection
Structure Protection
If clearance isn't achieved, use earthed metallic screens or warning boards.
Return Conductor
Return Conductor
A conductor that carries current from the tracks to a substation in a booster transformer system.
Wind Load Design (Masts/Spans)
Wind Load Design (Masts/Spans)
Based on IS: 875-1964 (updated 1971). Wind pressure varies by zone (Green, Yellow, Red).
Regulating Equipment
Regulating Equipment
Signup and view all the flashcards
Setting Distance (Implantation)
Setting Distance (Implantation)
Signup and view all the flashcards
Wind Pressure Zones
Wind Pressure Zones
Signup and view all the flashcards
Suspension Distance
Suspension Distance
Signup and view all the flashcards
Wind Load Calculation
Wind Load Calculation
Signup and view all the flashcards
Mast/Portal Safety Check
Mast/Portal Safety Check
Signup and view all the flashcards
Span
Span
Signup and view all the flashcards
Span Measurement
Span Measurement
Signup and view all the flashcards
Stagger (Contact Wire)
Stagger (Contact Wire)
Signup and view all the flashcards
Standard Span
Standard Span
Signup and view all the flashcards
Stagger (Catenary)
Stagger (Catenary)
Signup and view all the flashcards
Section Insulator
Section Insulator
Signup and view all the flashcards
Span Considerations
Span Considerations
Signup and view all the flashcards
Supply Control Post
Supply Control Post
Signup and view all the flashcards
Feeding Post (FP)
Feeding Post (FP)
Signup and view all the flashcards
Sectioning and Paralleling Post (SP)
Sectioning and Paralleling Post (SP)
Signup and view all the flashcards
Sub-sectioning and Paralleling Post (SSP)
Sub-sectioning and Paralleling Post (SSP)
Signup and view all the flashcards
Sub-sectioning Post (SSP)
Sub-sectioning Post (SSP)
Signup and view all the flashcards
Mast Selection
Mast Selection
Signup and view all the flashcards
Mast Employment Schedules
Mast Employment Schedules
Signup and view all the flashcards
Conventional OHE
Conventional OHE
Signup and view all the flashcards
Composite OHE
Composite OHE
Signup and view all the flashcards
Wind Pressure Zones
Wind Pressure Zones
Signup and view all the flashcards
B-series Masts
B-series Masts
Signup and view all the flashcards
Mast Implantation
Mast Implantation
Signup and view all the flashcards
Standard Setting Distances
Standard Setting Distances
Signup and view all the flashcards
Long Bridges
Long Bridges
Signup and view all the flashcards
Permissible Bending Moments
Permissible Bending Moments
Signup and view all the flashcards
OHE Mast Location - Station Entrances
OHE Mast Location - Station Entrances
Signup and view all the flashcards
OHE Mast Location - Trolley Refuges
OHE Mast Location - Trolley Refuges
Signup and view all the flashcards
Signal Post Distance Rule
Signal Post Distance Rule
Signup and view all the flashcards
Level Crossing and Bridges
Level Crossing and Bridges
Signup and view all the flashcards
Multiple Track Masts
Multiple Track Masts
Signup and view all the flashcards
Bad Formations Mast Placement
Bad Formations Mast Placement
Signup and view all the flashcards
Tunnel OHE Support
Tunnel OHE Support
Signup and view all the flashcards
Bridge Mast Erection
Bridge Mast Erection
Signup and view all the flashcards
Petroleum Siding Wiring
Petroleum Siding Wiring
Signup and view all the flashcards
Cantilever Arrangement
Cantilever Arrangement
Signup and view all the flashcards
Cantilever Arrangement Factors
Cantilever Arrangement Factors
Signup and view all the flashcards
Platform Cantilever Location
Platform Cantilever Location
Signup and view all the flashcards
Bridge & Tunnel Bracket Assembly
Bridge & Tunnel Bracket Assembly
Signup and view all the flashcards
Bracket Chair Limit
Bracket Chair Limit
Signup and view all the flashcards
Polluted Area Insulators
Polluted Area Insulators
Signup and view all the flashcards
Tangent Track Mast Setting (Broad Gauge)
Tangent Track Mast Setting (Broad Gauge)
Signup and view all the flashcards
Tangent Track Mast Setting (Meter Gauge)
Tangent Track Mast Setting (Meter Gauge)
Signup and view all the flashcards
Portal/Multiple OHE Mast Setting
Portal/Multiple OHE Mast Setting
Signup and view all the flashcards
Curve Mast Setting
Curve Mast Setting
Signup and view all the flashcards
Broad Gauge Curve Setting Minimum (Outside Curves)
Broad Gauge Curve Setting Minimum (Outside Curves)
Signup and view all the flashcards
Return Conductor
Return Conductor
Signup and view all the flashcards
Regulating Equipment
Regulating Equipment
Signup and view all the flashcards
Setting Distance (Implantation)
Setting Distance (Implantation)
Signup and view all the flashcards
Suspension Distance
Suspension Distance
Signup and view all the flashcards
Span
Span
Signup and view all the flashcards
Stagger (Contact Wire)
Stagger (Contact Wire)
Signup and view all the flashcards
Section Insulator
Section Insulator
Signup and view all the flashcards
Supply Control Post
Supply Control Post
Signup and view all the flashcards
Feeding Post (FP)
Feeding Post (FP)
Signup and view all the flashcards
Sectioning and Paralleling Post (SP)
Sectioning and Paralleling Post (SP)
Signup and view all the flashcards
Wind Pressure Zones
Wind Pressure Zones
Signup and view all the flashcards
Wind Load Calculation
Wind Load Calculation
Signup and view all the flashcards
Mast/Portal Safety Check
Mast/Portal Safety Check
Signup and view all the flashcards
Span Measurement
Span Measurement
Signup and view all the flashcards
Standard Span
Standard Span
Signup and view all the flashcards
Span Considerations
Span Considerations
Signup and view all the flashcards
Structure Protection
Structure Protection
Signup and view all the flashcards
Wind Load Design
Wind Load Design
Signup and view all the flashcards
Reduced Encumbrance (Overhead Equip.)
Reduced Encumbrance (Overhead Equip.)
Signup and view all the flashcards
Recommended Encumbrances (Table)
Recommended Encumbrances (Table)
Signup and view all the flashcards
Span Length (m)
Span Length (m)
Signup and view all the flashcards
Largest Permissible Adjacent Spans (m)
Largest Permissible Adjacent Spans (m)
Signup and view all the flashcards
Over-line Structure
Over-line Structure
Signup and view all the flashcards
Encumbrance Values (Table)
Encumbrance Values (Table)
Signup and view all the flashcards
Special Case for Encumbrances
Special Case for Encumbrances
Signup and view all the flashcards
Return Conductor Purpose
Return Conductor Purpose
Signup and view all the flashcards
Return Conductor Proximity
Return Conductor Proximity
Signup and view all the flashcards
Return Conductor Clearance
Return Conductor Clearance
Signup and view all the flashcards
Return Conductor Static Clearance
Return Conductor Static Clearance
Signup and view all the flashcards
Return Conductor Dynamic Clearance
Return Conductor Dynamic Clearance
Signup and view all the flashcards
Return Conductor Over-Bridges
Return Conductor Over-Bridges
Signup and view all the flashcards
Return Conductors in Complicated Areas
Return Conductors in Complicated Areas
Signup and view all the flashcards
Return Conductor Termination
Return Conductor Termination
Signup and view all the flashcards
Booster Transformer Connections
Booster Transformer Connections
Signup and view all the flashcards
Return Conductor Mid-point Connection
Return Conductor Mid-point Connection
Signup and view all the flashcards
Inexceptional Circumstances Rail Links
Inexceptional Circumstances Rail Links
Signup and view all the flashcards
LT Supply Transformer
LT Supply Transformer
Signup and view all the flashcards
LT Transformer Capacity
LT Transformer Capacity
Signup and view all the flashcards
LT Transformer Protection
LT Transformer Protection
Signup and view all the flashcards
LT Transformer Mounting
LT Transformer Mounting
Signup and view all the flashcards
Substation LT Transformer
Substation LT Transformer
Signup and view all the flashcards
Structure Bonds
Structure Bonds
Signup and view all the flashcards
Rail Bonds
Rail Bonds
Signup and view all the flashcards
Cross Bonds
Cross Bonds
Signup and view all the flashcards
Study Notes
Principles for Layout Plans and Sectioning Diagrams for 25kV AC Traction
- These principles standardize and guide railway electrification projects
- Some principles are mandatory, others provide guidance for standardization and efficiency
- Design prioritizes proper contact wire height for pantograph operation
- Key terms have specific meanings defined in the traction manual unless otherwise specified
Definitions
- Bond: An electrical connection across a rail joint, maintaining continuity
- Bond, continuity: Maintains continuity of the rail circuit at crossings and junctions
- Bond, cross: Connects together rails of a track or adjacent tracks
- Bond impedance: A specific rail bond bridging insulated rail joints in AC track circuited sections
- Bond rail: An electrical connection across a joint between adjacent rail lengths for the track return
- Bond, structure: Connects track structures/bridges with the overhead equipment to the track return
- Cantilever assembly: A structural member comprising steel tubes supporting the catenary system to facilitate current collection by the pantograph at all speeds
- Stay arm: A component with diameter 28.4/33.7 mm, with an adjuster for bracket tube position, insulated from mast by stay arm insulator
- Bracket tube: A component with diameter 40/49 mm (small) or 30/38 mm (standard), insulated by bracket insulator
- Register Arm: A 28.4x33.7 mm tube for registering the contact wire's position with steady arm assistance
- Crossings: Electrically live members/conductors passing over other live members without physical contact
- Power line crossing: An overhead transmission/distribution line or underground cable across railway tracks, for electrical energy transmission.
- Crossing OHE: Crossing of two OHE conductors without physical contact.
- Dropper: A fitting supporting contact wire from catenary
- Electrical Clearance: The air distance between live equipment and the nearest grounded part
- Encumbrance: The axial distance on a vertical plane between catenary and contact wire at the support
- Feeder: A conductor connecting substation with feeding post or feeding post with OHE
- Height of contact wire: The vertical distance from rail level to the underside of the contact wire
- Interruptor: A single-phase vacuum SF6/oil circuit breaker used in circuit closure in case of a fault
- Bridging Interruptor: Provides connection between substations in emergencies
- Sectioning Interruptor: Connects adjacent sectors for continuity of supply
- Paralleling Interruptor: Joins overhead equipment of different tracks for voltage reduction
- Jumper: A conductor providing electrical continuity between two conductors or equipment
- Mast: A vertical post supporting overhead equipment (OHE) assembly
- Neutral Section: Short section of insulated dead OHE separating sectors fed by two adjacent substations.
- Overhead Equipment (OHE): Electrical conductors, fittings for overhead electrical systems
- Overlap: OHE arrangement spanning a short distance to facilitate pantograph movement
- Pantograph: Collapsible device on rolling stock for collecting current from OHE
- Return Conductor: A conductor carrying current from tracks to substation
- Regulating Equipment: Maintains constant tension in OHE conductors at varying temperature
- Setting Distance: Horizontal distance from the traction mast to the track center line
- Span: Horizontal distance between supporting masts for OHE
- Stagger: Horizontal distance of a wire/catenary from a vertical plane through pantograph center
- Section Insulator: In OHE, isolates sections to prevent current flow between sections
- Sector: Part of an OHE energized by a feeder circuit breaker at the substation
- Sub-sector: Smallest section of an OHE isolated remotely by interruptors
- Elementary Section: Smallest section of an OHE isolated manually.
- Tension Length: Length of conductor stretched between two anchor points
- Versine: Maximum offset of the rail, relating to curved track's chord
- Clearance: Minimum distance between live parts and earthed parts in various conditions
- Span Measurement: Measuring spans accurately using a steel tape.
Spans
- Spans measurement guidelines: different methods based on the track configuration (single vs. multiple) and location
- Standards for calculating spans: references to drawings, with variations for regulated/conventional OHE, and different OHE types.
- Restrictions apply to different scenarios. These restrictions limit span lengths under various conditions (e.g., over-line structures or locations with restricted clearances)
Masts, Portals, and Foundations
- Mast types: various designs and materials (e.g., rolled sections, fabricated, concrete spun poles)
- Descriptions of specific mast designs (150x150 BFB, 200x150 RSJ, K-series, B-series )
- Selection of masts based on wind pressure zones
Over-line Structures
- Clearance considerations: clearance standards and required calculations based on various locations
Contact Wire Height
- Standard height: minimum 5.5 m above the track in all conditions
- Reduced height permissible for over-line structures after clearance considerations
- Special requirements near electric locomotives or inspection areas
Stagger
- Tangent and curved tracks: Different stagger values for different track types
- Stagger at support and mid-span
Droppers
- Standard arrangement designs
- Special dropper arrangements for unusual locations
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.