Podcast
Questions and Answers
What was the primary purpose of the Critical Path Method (CPM) when it was first developed?
What was the primary purpose of the Critical Path Method (CPM) when it was first developed?
Which of the following accurately defines the Forward Pass in CPM?
Which of the following accurately defines the Forward Pass in CPM?
How is the Early Start (ES) determined in a Predecessor Activity Case?
How is the Early Start (ES) determined in a Predecessor Activity Case?
What type of representation does CPM rely on to depict activities and their relationships?
What type of representation does CPM rely on to depict activities and their relationships?
Signup and view all the answers
What does the term 'Critical Path' in CPM refer to?
What does the term 'Critical Path' in CPM refer to?
Signup and view all the answers
What is the output of the Backward Pass in CPM?
What is the output of the Backward Pass in CPM?
Signup and view all the answers
In which industry was the Critical Path Method initially used?
In which industry was the Critical Path Method initially used?
Signup and view all the answers
What is the equation used to calculate Early Finish (EF)?
What is the equation used to calculate Early Finish (EF)?
Signup and view all the answers
How is Early Finish (EF) calculated for an activity that has multiple predecessor activities?
How is Early Finish (EF) calculated for an activity that has multiple predecessor activities?
Signup and view all the answers
What does Late Finish (LF) represent in project scheduling?
What does Late Finish (LF) represent in project scheduling?
Signup and view all the answers
What is the formula for calculating Late Start (LS) for an activity?
What is the formula for calculating Late Start (LS) for an activity?
Signup and view all the answers
When calculating Early Finish for an activity related to only one other activity, which equation is used?
When calculating Early Finish for an activity related to only one other activity, which equation is used?
Signup and view all the answers
What is the final activity's Late Finish (LF) in scheduling?
What is the final activity's Late Finish (LF) in scheduling?
Signup and view all the answers
In project scheduling, how should Late Finish (LF) be determined for an activity with multiple succeeding activities?
In project scheduling, how should Late Finish (LF) be determined for an activity with multiple succeeding activities?
Signup and view all the answers
When working on Early Finish calculations, which aspect is considered when multiple predecessor activities are involved?
When working on Early Finish calculations, which aspect is considered when multiple predecessor activities are involved?
Signup and view all the answers
To calculate the Early Start (ES) of an activity linked to more than one other activity, which equation applies?
To calculate the Early Start (ES) of an activity linked to more than one other activity, which equation applies?
Signup and view all the answers
Study Notes
CPM Historical Background
- The Critical Path Method (CPM) was developed in the late 1950s by Morgan, Walker, and Kelley at Dupont Company in Detroit.
- CPM's primary purpose was to analyze and plan large projects, specifically for identifying critical paths in the automotive industry.
CPM Definition
- CPM is a method for analyzing and planning projects, used to identify critical paths, estimate early/late timings, analyze activity sequence, and prioritize high-priority tasks.
- It relies on graphical representation to depict activity sequences and relationships, assisting in estimating project completion durations and identifying the critical path.
Stages of Completing CPM
- The CPM is calculated in two stages:
Forward Pass
- Calculates the earliest start (ES) and earliest finish (EF) times for each activity.
- Starts from the project’s beginning date and moves forward through the network diagram, considering activity durations and dependencies.
Early Times types
- Early Start (ES): Earliest possible start time for an activity, determined by the earliest finish time of its preceding activities.
- Early Finish (EF): Earliest possible finish time for an activity, calculated based on its early start time and duration.
Calculating early times
- Initial Activity Case: Early Start (ES) is equal to the initial time (0). Early Finish (EF) is calculated using the equation: EF = ES + Duration.
- Predecessor Activity Case: Early Start (ES) is equal to the maximum of the early finish times of all preceding activities. Early Finish (EF) is calculated using the equation: EF = Maximum of Early Finish Times of predecessor Activities.
- Calculation Method: Begin with identifying the initial activity. For each subsequent activity, calculate the early start and early finish using the above equations. Determine the early start and early finish for all activities sequentially to reach the endpoint.
Early Time Equations
- If an activity is related to more than one activity: the ES of activity J is the maximum of the sum of the EF of predecessors A, B, and C plus their respective durations.
- If an activity is related to only one other activity: the ES of activity J is the sum of the EF of predecessor A plus its duration.
Backward Pass
- Calculates the latest finish (LF) and latest start (LS) times for each activity.
- Starts from the project’s end date and moves backward through the network diagram, considering activity durations and dependencies.
Late Times types
- Late Finish (LF): Latest possible finish time for an activity, determined by the latest start time of its succeeding activities.
- Late Start (LS): Latest possible start time for an activity, calculated based on its late finish time and duration.
Calculating late times
- Final Activity Case: Late Finish (LF) is equal to the project end time. Late Start (LS) is calculated using the equation: LS = LF – Activity Duration.
- Successor Activity Case: Late Finish (LF) is equal to the minimum of the late start times of all succeeding activities. Late Start (LS) is calculated using the equation :LS = Minimum of Late Start Times of Successor Activities – Activity Duration.
- Calculation Method: Start with identifying the final activity. For each preceding activity, calculate the late finish and late start using the above equations. Determine the late finish and late start for all activities sequentially to reach the starting point.
Late Time Equations
- If an activity is linked to more than one other activity from the end: The LF of activity J is the minimum of the LS of all succeeding activities.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.