Project Time Management Overview
10 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the primary purpose of Resource Leveling?

  • To develop a project budget
  • To create a project schedule
  • To optimize resource allocation (correct)
  • To estimate activity durations
  • What is an output of the Estimate Activity Durations process?

  • Project schedule
  • Activity durations (correct)
  • Activity list
  • Resource allocation plan
  • What is the Critical Path Method used for?

  • To estimate activity durations
  • To identify the critical path in a project (correct)
  • To develop a project schedule
  • To allocate resources
  • What is the purpose of a Data Flow Diagram?

    <p>To show the flow of data between processes</p> Signup and view all the answers

    What is an input to the Develop Schedule process?

    <p>Activity durations</p> Signup and view all the answers

    What is the purpose of Activity Sequencing?

    <p>To determine the order of activities</p> Signup and view all the answers

    What is a Tool and Technique of the Estimate Activity Durations process?

    <p>Three-Point Estimation</p> Signup and view all the answers

    What is an output of the Develop Schedule process?

    <p>Project schedule</p> Signup and view all the answers

    What is the purpose of Critical Chain Method?

    <p>To manage dependencies and constraints</p> Signup and view all the answers

    What is a Data Flow Diagram used to illustrate?

    <p>The flow of data between processes</p> Signup and view all the answers