Project Time Management Overview
10 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the primary purpose of Resource Leveling?

  • To develop a project budget
  • To create a project schedule
  • To optimize resource allocation (correct)
  • To estimate activity durations

What is an output of the Estimate Activity Durations process?

  • Project schedule
  • Activity durations (correct)
  • Activity list
  • Resource allocation plan

What is the Critical Path Method used for?

  • To estimate activity durations
  • To identify the critical path in a project (correct)
  • To develop a project schedule
  • To allocate resources

What is the purpose of a Data Flow Diagram?

<p>To show the flow of data between processes (D)</p> Signup and view all the answers

What is an input to the Develop Schedule process?

<p>Activity durations (D)</p> Signup and view all the answers

What is the purpose of Activity Sequencing?

<p>To determine the order of activities (D)</p> Signup and view all the answers

What is a Tool and Technique of the Estimate Activity Durations process?

<p>Three-Point Estimation (B)</p> Signup and view all the answers

What is an output of the Develop Schedule process?

<p>Project schedule (B)</p> Signup and view all the answers

What is the purpose of Critical Chain Method?

<p>To manage dependencies and constraints (C)</p> Signup and view all the answers

What is a Data Flow Diagram used to illustrate?

<p>The flow of data between processes (A)</p> Signup and view all the answers