Podcast
Questions and Answers
Which of the following is the MOST accurate definition of 'free float' in project schedule management?
Which of the following is the MOST accurate definition of 'free float' in project schedule management?
- The time an activity can be delayed without delaying the project finish date.
- The difference between the early start and late start dates of an activity.
- The amount of time an activity can be delayed without affecting resource availability.
- The time an activity can be delayed without delaying the early start of any immediately following activity. (correct)
What is the primary purpose of resource leveling in project schedule management?
What is the primary purpose of resource leveling in project schedule management?
- To shorten the project duration by assigning more resources to critical activities.
- To balance the workload and resource allocation over the course of the project. (correct)
- To identify and resolve resource overallocation.
- To calculate the project's critical path more accurately.
A project manager discovers that the original project schedule is no longer realistic due to unforeseen delays. What would be the MOST effective initial step to take?
A project manager discovers that the original project schedule is no longer realistic due to unforeseen delays. What would be the MOST effective initial step to take?
- Review the project's constraints and assumptions to evaluate their impact on the schedule. (correct)
- Immediately implement schedule compression techniques to catch up.
- Reallocate resources from less critical activities to critical ones.
- Distribute an updated schedule to the project team without further analysis.
In the context of project schedule management, what does 'fast-tracking' primarily involve?
In the context of project schedule management, what does 'fast-tracking' primarily involve?
When would a project manager MOST likely use a 'what-if scenario analysis' during project schedule development?
When would a project manager MOST likely use a 'what-if scenario analysis' during project schedule development?
Which of the following is a key characteristic of the Critical Path Method?
Which of the following is a key characteristic of the Critical Path Method?
What is the significance of a project schedule baseline?
What is the significance of a project schedule baseline?
What is the primary purpose of schedule compression techniques in project management?
What is the primary purpose of schedule compression techniques in project management?
In project scheduling, what does the acronym 'ES' stand for?
In project scheduling, what does the acronym 'ES' stand for?
During the Develop Schedule process, which of the following is typically considered an output?
During the Develop Schedule process, which of the following is typically considered an output?
A project manager notices that several activities have been completed ahead of schedule. What should they do NEXT?
A project manager notices that several activities have been completed ahead of schedule. What should they do NEXT?
A project is currently running behind schedule. The project manager is considering adding additional resources to critical path activities. What is this technique called?
A project is currently running behind schedule. The project manager is considering adding additional resources to critical path activities. What is this technique called?
What is the BEST description of a 'milestone chart' in project management?
What is the BEST description of a 'milestone chart' in project management?
Which of the following actions is MOST important when establishing a schedule baseline?
Which of the following actions is MOST important when establishing a schedule baseline?
In project scheduling, what does 'DU' typically represent?
In project scheduling, what does 'DU' typically represent?
Which of the following BEST describes 'schedule variance' (SV)?
Which of the following BEST describes 'schedule variance' (SV)?
Which of the following is NOT a typical input to the 'Control Schedule' process?
Which of the following is NOT a typical input to the 'Control Schedule' process?
What is the objective of 'schedule network analysis'?
What is the objective of 'schedule network analysis'?
What is the MOST important reason for using Earned Value Management (EVM) on a project?
What is the MOST important reason for using Earned Value Management (EVM) on a project?
In EVM, if the Schedule Performance Index (SPI) is less than 1, what does this indicate?
In EVM, if the Schedule Performance Index (SPI) is less than 1, what does this indicate?
What does 'crashing' a project schedule involve?
What does 'crashing' a project schedule involve?
If a project's Earned Value (EV) is $50,000 and its Planned Value (PV) is $60,000, what is the Schedule Variance (SV)?
If a project's Earned Value (EV) is $50,000 and its Planned Value (PV) is $60,000, what is the Schedule Variance (SV)?
What is the main purpose of 'resource calendars' in project management scheduling?
What is the main purpose of 'resource calendars' in project management scheduling?
A project manager needs to present the project schedule to senior management. Which type of schedule format is MOST suitable for this purpose?
A project manager needs to present the project schedule to senior management. Which type of schedule format is MOST suitable for this purpose?
During project execution, the project manager identifies a new risk that could delay the project. What is the FIRST step they should take?
During project execution, the project manager identifies a new risk that could delay the project. What is the FIRST step they should take?
In project schedule management, which of the following refers to the sequencing of project activities?
In project schedule management, which of the following refers to the sequencing of project activities?
What is the BEST definition of 'total float' in project schedule management?
What is the BEST definition of 'total float' in project schedule management?
What is the MOST significant difference between the Critical Path Method (CPM) and the Critical Chain Method (CCM)?
What is the MOST significant difference between the Critical Path Method (CPM) and the Critical Chain Method (CCM)?
Which of the following is the MOST accurate definition of 'Lead'?
Which of the following is the MOST accurate definition of 'Lead'?
Which of the following is the CORRECT formula for the Schedule Performance Index (SPI)?
Which of the following is the CORRECT formula for the Schedule Performance Index (SPI)?
Which of the following is NOT a recommended action when controlling the project schedule?
Which of the following is NOT a recommended action when controlling the project schedule?
What is the purpose of 'adjusting leads and lags' in project schedule development?
What is the purpose of 'adjusting leads and lags' in project schedule development?
Which of the following is MOST important to consider when deciding whether to 'crash' a project schedule activity?
Which of the following is MOST important to consider when deciding whether to 'crash' a project schedule activity?
In project management, what is 'performance reviews' used for in monitoring and controlling the schedule?
In project management, what is 'performance reviews' used for in monitoring and controlling the schedule?
In project schedule management, what is a schedule baseline primarily used for?
In project schedule management, what is a schedule baseline primarily used for?
What is a typical characteristic of activities on the critical path?
What is a typical characteristic of activities on the critical path?
Which of the following constraints are considered under the Critical Chain Method?
Which of the following constraints are considered under the Critical Chain Method?
Which of the following is required when using Schedule Network Analysis?
Which of the following is required when using Schedule Network Analysis?
Flashcards
Project Schedule
Project Schedule
It's a plan for starting and finishing project activities on specific dates and in a defined sequence.
Develop Schedule Process
Develop Schedule Process
Defines the specific start and end dates for each project activity and is a key part of project time management.
ES (Early Start)
ES (Early Start)
Earliest time an activity can start.
EF (Early Finish)
EF (Early Finish)
Signup and view all the flashcards
LF (Late Finish)
LF (Late Finish)
Signup and view all the flashcards
LS (Late Start)
LS (Late Start)
Signup and view all the flashcards
DU (Duration)
DU (Duration)
Signup and view all the flashcards
Critical Path
Critical Path
Signup and view all the flashcards
Float
Float
Signup and view all the flashcards
Total Float
Total Float
Signup and view all the flashcards
Free Float
Free Float
Signup and view all the flashcards
Schedule Network Analysis
Schedule Network Analysis
Signup and view all the flashcards
Critical Path Method (CPM)
Critical Path Method (CPM)
Signup and view all the flashcards
Critical Chain Method
Critical Chain Method
Signup and view all the flashcards
What-If Scenario Analysis
What-If Scenario Analysis
Signup and view all the flashcards
Resource Leveling
Resource Leveling
Signup and view all the flashcards
Bar Chart
Bar Chart
Signup and view all the flashcards
Milestone Chart
Milestone Chart
Signup and view all the flashcards
Project Schedule Network Diagram
Project Schedule Network Diagram
Signup and view all the flashcards
Draft A Project Schedule
Draft A Project Schedule
Signup and view all the flashcards
Critical Activities
Critical Activities
Signup and view all the flashcards
Identify the Critical Path
Identify the Critical Path
Signup and view all the flashcards
Schedule Compression
Schedule Compression
Signup and view all the flashcards
Fast-Tracking
Fast-Tracking
Signup and view all the flashcards
Crashing
Crashing
Signup and view all the flashcards
Optimize the Project Schedule
Optimize the Project Schedule
Signup and view all the flashcards
Crash Cost Plotting Methods
Crash Cost Plotting Methods
Signup and view all the flashcards
Schedule Baselines
Schedule Baselines
Signup and view all the flashcards
Establish a Schedule Baseline
Establish a Schedule Baseline
Signup and view all the flashcards
Control Schedule Process
Control Schedule Process
Signup and view all the flashcards
EVM (Earned Value Management)
EVM (Earned Value Management)
Signup and view all the flashcards
Planned Value (PV)
Planned Value (PV)
Signup and view all the flashcards
Earned Value
Earned Value
Signup and view all the flashcards
Actual Cost (AC)
Actual Cost (AC)
Signup and view all the flashcards
Schedule Variance (SV)
Schedule Variance (SV)
Signup and view all the flashcards
Schedule Performance Index (SPI)
Schedule Performance Index (SPI)
Signup and view all the flashcards
Control The Project Schedule
Control The Project Schedule
Signup and view all the flashcards
Schedule Performance Measurement
Schedule Performance Measurement
Signup and view all the flashcards
Study Notes
- Developing and controlling a project schedule involves drafting a schedule, identifying the critical path, optimizing the schedule, establishing a baseline, and controlling the schedule.
Project Management Framework
- Project Integration Management covers developing the project charter, management plan, directing project execution, monitoring project work, and closing the project.
- Project Scope Management includes collecting requirements, defining project scope, creating a WBS, verifying scope, and controlling scope.
- Project Time Management involves defining project activities, sequencing activities, estimating activity resources and durations, developing the schedule, and controlling the schedule.
- Project Cost Management includes estimating costs and determining the budget, as well as controlling costs.
- Project Quality Management covers planning quality, performing quality assurance, and controlling quality.
- Project Human Resource Management includes developing the human resource plan, acquiring the project team, developing the team, and managing the team.
- Project Communications Management involves identifying stakeholders, planning communications, distributing information, managing stakeholder expectations, and reporting performance.
- Project Risk Management includes planning risk management, identifying risks, performing qualitative and quantitative risk analysis, planning risk responses, and monitoring and controlling risks.
- Project Procurement Management covers planning procurements, conducting procurements, administering procurements, and closing procurements.
Project Schedules
- Project schedules serve as plans that define when activities starts and ends in a sequence.
- Schedules coordinate activities into a single, comprehensive master plan leading to successful scheduling performance.
The Develop Schedule Process
- Defining start and end dates for project activities is an important part
- Inputs to the process include:
- Activity list and attributes
- Project schedule network diagrams
- Activity resource requirements and resource calendars
- Activity duration estimates
- Project scope statement and Enterprise environmental factors
- Organizational process assets such as defined schedules.
- Common tools and techniques are:
- Schedule network analysis
- Critical path method
- Critical chain method
- Resource leveling
- "What-if" scenario analysis
- Applying leads and lags
- Schedule compression
- Scheduling tool is also used
- Outputs include a completed Project schedule, schedule baseline, updated data, and updates to existing project documents to reflect scheduling outcomes.
Standard Schedule Diagramming Notations
- ES stands for early start, The earliest time an activity can start
- EF stands for early finish, the earliest time an activity can finish
- LF stands for late finish, The latest time an activity can finish
- LS stands for late start, The latest time an activity can start
- DU is duration and the number of work periods required for activity completion
The Critical Path
- A critical path represents the path with the longest total duration.
- This path has no scheduling flexibility meaning activities along this path must be completed as planned to meet deadlines.
- Schedule management can be performed by ensuring activities are completed on time
Float
- Float shows the total time an activity can be delayed from its early start (ES) without delaying the project finish date or consecutive activities
- Two kinds of floats are:
- Total float
- Free float
Schedule Network Analysis
- Schedule network analysis calculates the theoretical early and late start and finish dates for all project activities.
- Four main methods include:
- Critical Path Method (CPM)
- Critical chain method
- What-if scenario
- Resource leveling
Critical Path Method (CPM)
- Critical Path Method (CPM) is a popular schedule network analysis method, commonly used in the business world.
- CPM uses sequential finish-to-start network logic to effectively manage time
- Calculates one early and late start and finish date for each activity.
- CPM uses a single duration estimate
The Critical Chain Method
- The Critical Chain Method adjusts project schedules based on resource considerations.
- This is done by considering:
- Resource limitations
- Adjustments to schedule
- Planning for reserves
- Mitigation of cost and schedule risks
- It does so by analyzing the critical path alongside available resources.
What-If Scenario Analysis
- Used to consider different situations that might occur and influence the schedule.
- Computes different schedules based on potential delays.
- Simulated outcomes can be used in risk response plans.
- Helps select the optimum plan.
Resource Leveling
- Used to analyze the schedule model to readjust work assignments.
- It helps address scheduling activities after the critical path has been identified
- Found in many types of project management software.
Schedule Formats
- The Bar chart format offers,
- start and end dates,
- duration,
- order.
- It shows precedence relationships and completion percentage
- A Bar Chart is useful for presenting the project status to management
- The Milestone Chart is suitable for presenting a summary of the project and includes
- The project's milestones
- Icons/Symbold
- Overall schedule
- Network Diagram format.
- Assigns activities to start and finish dates
- It also Communicates project status in terms of activity precedence relationships.
Drafting a Project Schedule
- Steps to drafting a project schedule:
- Perform a mathematical analysis to determine durations of time for resource limits, and other constraints.
- Evaluate possible constraints for schedule development.
- Assess resource availability.
- Consult project calendars and assign dates to activities.
- Calculate potential project durations under different constraints.
- Consider external resource date constraints, if applicable.
- Select project management software that suits needs and budget.
- Review schedule drafts with the project team and customer.
- Choose the publishing format.
- Disseminate the preliminary schedule for approval.
- Baseline the schedule after its approved.
Completed Project Schedule
- Project Start Date: May 11, 2009
- Work Package: TRN0001
Critical Activities
- Indicate activities on the critical path.
- Exhibit the same early start and late start dates, and early finish with late finish dates.
Identify the Criticall Path
- Steps include:
- Conduct forward pass to determine the Earliest State time and Earliest Finish for each activity
- Conduct backward pass to determine the Latest State time and Latest Finish for each activity
- Calculate float
- Identify the critical path by the longest total and zero float
Schedule Compression
- Schedule compression shortens the schedule without affecting the scope.
- The two primary methods for schedule compression are fast-tracking and crashing.
Fast-Tracking
- Fast-tracking compresses the project's total duration by performing otherwise sequential activities concurrently.
- Project duration shortens.
Crashing
- Crashing optimizes cost versus schedule tradeoffs.
- It allocates maximum resources to activities on the critical path.
Schedule Baseline
- The schedule baseline defines the project plan approved by management.
- It measures and reports schedule performance.
Control Schedule Process
- The control schedule process monitors performance and controls changes in the schedule.
- Important actions include getting stakeholder feedback and creating a schedule baseline.
- Key inputs include project management plan, project schedule, work performance information, and organizational/process assets.
- Used tools performance reviews, variance analysis, project management software resource levelling, "what if analysis", schedule compression, and scheduling tools.
- Outputs include work progress reports, along with any updates to project management plans, and documents.
Earned Value Management (EVM)
- EVM measures project progress as well as costs.
- It compares actual schedule and cost performance against the planned performance.
- It is important to understand the financial cost of the project you're performing.
EVM Measures
- Calculates three independent variables to assess and monitor performance progress
- Planned Value (PV)
- Earned Value (EV)
- Actual Cost (AC)
- These variables provide measures of work accomplished.
- Forecasts the project cost at completion
Planned Value (PV)
- Represents the budgeted cost is designated for project work during a given time
Earned Value (EV)
- Composite measurement of the performance based on schedule and the total cost.
- It is calculated using the percentage of work completed times the budgeted cost.
Actual Cost (AC)
- Total costs to date that have been incurred while accomplishing work performed.
EVM Measures
- Schedule Variance (SV) measures deviations from the planned schedule, calculated by the formula SV = EV - PV.
- Schedule Performance Index (SPI) gauges the efficiency of work completed versus planned, with SPI = EV / PV.
- Cost Variance (CV) identifies budget deviations, determined by CV = EV - AC.
- Cost Performance Index (CPI) assesses the efficiency of costs, calculated by CPI = EV / AC.
Schedule Performance Measurement
- Used to determine how a project is performing based on time versus it's planned performance
- Indicates the variance of actual work performed and work scheduled
- Performance measurement techniques:
- Schedule Variance (SV)
- Schedule Performance Index (SPI)
- Variance-and-Trend Analysis
- Determines detrimental risk and plans corrective actions
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.