Project Schedule & Framework

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which of the following is the MOST accurate definition of 'free float' in project schedule management?

  • The time an activity can be delayed without delaying the project finish date.
  • The difference between the early start and late start dates of an activity.
  • The amount of time an activity can be delayed without affecting resource availability.
  • The time an activity can be delayed without delaying the early start of any immediately following activity. (correct)

What is the primary purpose of resource leveling in project schedule management?

  • To shorten the project duration by assigning more resources to critical activities.
  • To balance the workload and resource allocation over the course of the project. (correct)
  • To identify and resolve resource overallocation.
  • To calculate the project's critical path more accurately.

A project manager discovers that the original project schedule is no longer realistic due to unforeseen delays. What would be the MOST effective initial step to take?

  • Review the project's constraints and assumptions to evaluate their impact on the schedule. (correct)
  • Immediately implement schedule compression techniques to catch up.
  • Reallocate resources from less critical activities to critical ones.
  • Distribute an updated schedule to the project team without further analysis.

In the context of project schedule management, what does 'fast-tracking' primarily involve?

<p>Performing project activities in parallel that would normally be done in sequence. (B)</p> Signup and view all the answers

When would a project manager MOST likely use a 'what-if scenario analysis' during project schedule development?

<p>To predict the impact of potential risks and delays on the project schedule. (B)</p> Signup and view all the answers

Which of the following is a key characteristic of the Critical Path Method?

<p>It calculates one early and late start and finish date for each activity. (B)</p> Signup and view all the answers

What is the significance of a project schedule baseline?

<p>It is the final, approved version of the project schedule used for measuring performance. (C)</p> Signup and view all the answers

What is the primary purpose of schedule compression techniques in project management?

<p>To shorten the project schedule without changing the project scope. (C)</p> Signup and view all the answers

In project scheduling, what does the acronym 'ES' stand for?

<p>Early Start (C)</p> Signup and view all the answers

During the Develop Schedule process, which of the following is typically considered an output?

<p>Project schedule (A)</p> Signup and view all the answers

A project manager notices that several activities have been completed ahead of schedule. What should they do NEXT?

<p>Analyze the impact on the critical path and overall schedule. (C)</p> Signup and view all the answers

A project is currently running behind schedule. The project manager is considering adding additional resources to critical path activities. What is this technique called?

<p>Crashing (D)</p> Signup and view all the answers

What is the BEST description of a 'milestone chart' in project management?

<p>A high-level summary of project milestones and their target completion dates. (B)</p> Signup and view all the answers

Which of the following actions is MOST important when establishing a schedule baseline?

<p>Securing approval from all project stakeholders. (A)</p> Signup and view all the answers

In project scheduling, what does 'DU' typically represent?

<p>Duration (B)</p> Signup and view all the answers

Which of the following BEST describes 'schedule variance' (SV)?

<p>The difference between earned value and planned value. (A)</p> Signup and view all the answers

Which of the following is NOT a typical input to the 'Control Schedule' process?

<p>Risk management plan (C)</p> Signup and view all the answers

What is the objective of 'schedule network analysis'?

<p>To calculate the theoretical early and late start and finish dates for project activities. (C)</p> Signup and view all the answers

What is the MOST important reason for using Earned Value Management (EVM) on a project?

<p>To track and report project performance against planned costs and schedule. (D)</p> Signup and view all the answers

In EVM, if the Schedule Performance Index (SPI) is less than 1, what does this indicate?

<p>The project is behind schedule. (A)</p> Signup and view all the answers

What does 'crashing' a project schedule involve?

<p>Adding resources to critical path activities to shorten their duration. (D)</p> Signup and view all the answers

If a project's Earned Value (EV) is $50,000 and its Planned Value (PV) is $60,000, what is the Schedule Variance (SV)?

<p>-$10,000 (A)</p> Signup and view all the answers

What is the main purpose of 'resource calendars' in project management scheduling?

<p>To manage resource availability and working hours. (D)</p> Signup and view all the answers

A project manager needs to present the project schedule to senior management. Which type of schedule format is MOST suitable for this purpose?

<p>A milestone chart summarizing key project deliverables and target dates. (A)</p> Signup and view all the answers

During project execution, the project manager identifies a new risk that could delay the project. What is the FIRST step they should take?

<p>Analyze the impact of the risk on the project schedule. (B)</p> Signup and view all the answers

In project schedule management, which of the following refers to the sequencing of project activities?

<p>Sequencing Activities (B)</p> Signup and view all the answers

What is the BEST definition of 'total float' in project schedule management?

<p>The time an activity can be delayed without delaying the project finish date. (C)</p> Signup and view all the answers

What is the MOST significant difference between the Critical Path Method (CPM) and the Critical Chain Method (CCM)?

<p>CCM considers resource constraints, while CPM does not. (C)</p> Signup and view all the answers

Which of the following is the MOST accurate definition of 'Lead'?

<p>The amount of time a successor activity can be advanced with respect to a predecessor activity. (D)</p> Signup and view all the answers

Which of the following is the CORRECT formula for the Schedule Performance Index (SPI)?

<p>SPI = Earned Value / Planned Value (D)</p> Signup and view all the answers

Which of the following is NOT a recommended action when controlling the project schedule?

<p>Skipping performance measurement techniques if the project appears to be on track. (B)</p> Signup and view all the answers

What is the purpose of 'adjusting leads and lags' in project schedule development?

<p>To modify the dependencies between activities to achieve desired start and finish times. (B)</p> Signup and view all the answers

Which of the following is MOST important to consider when deciding whether to 'crash' a project schedule activity?

<p>The cost-benefit trade-off of shortening the activity duration. (D)</p> Signup and view all the answers

In project management, what is 'performance reviews' used for in monitoring and controlling the schedule?

<p>To assess progress and identify variances from the schedule baseline. (B)</p> Signup and view all the answers

In project schedule management, what is a schedule baseline primarily used for?

<p>Monitoring progress and identifying variances. (D)</p> Signup and view all the answers

What is a typical characteristic of activities on the critical path?

<p>They have zero float. (D)</p> Signup and view all the answers

Which of the following constraints are considered under the Critical Chain Method?

<p>Resource constraints (A)</p> Signup and view all the answers

Which of the following is required when using Schedule Network Analysis?

<p>Critical Path Method (A)</p> Signup and view all the answers

Flashcards

Project Schedule

It's a plan for starting and finishing project activities on specific dates and in a defined sequence.

Develop Schedule Process

Defines the specific start and end dates for each project activity and is a key part of project time management.

ES (Early Start)

Earliest time an activity can start.

EF (Early Finish)

Earliest time an activity can finish.

Signup and view all the flashcards

LF (Late Finish)

The latest time an activity can finish without delaying the project completion.

Signup and view all the flashcards

LS (Late Start)

The latest time an activity can start without delaying the project.

Signup and view all the flashcards

DU (Duration)

Number of work periods needed to complete the activity.

Signup and view all the flashcards

Critical Path

It's the path with the longest total duration; determines the shortest time to complete the project.

Signup and view all the flashcards

Float

It's the amount of time an activity can be delayed without delaying the project finish date.

Signup and view all the flashcards

Total Float

Total amount of time an activity can be delayed without delaying the project finish date.

Signup and view all the flashcards

Free Float

The amount of time an activity can be delayed without delaying the start of any successor activities.

Signup and view all the flashcards

Schedule Network Analysis

Method to calculate theoretical early and late start/finish dates for project activities.

Signup and view all the flashcards

Critical Path Method (CPM)

A schedule network analysis using one duration estimate.

Signup and view all the flashcards

Critical Chain Method

A schedule network analysis method which Considers resource limitations, adjusts the schedule, then plans and manages resources to mitigate possible cost and schedule risks.

Signup and view all the flashcards

What-If Scenario Analysis

Considering different scenarios and their impact on the project schedule.

Signup and view all the flashcards

Resource Leveling

A technique to analyze the schedule model and readjust work appropriately is used to address scheduling activities. Done after the critical path is initially identified.

Signup and view all the flashcards

Bar Chart

Shows start/end dates, duration and order, presents percentage completion and can show the project precedence.

Signup and view all the flashcards

Milestone Chart

Summary of project's milestones, Uses icons/symbols and shows overall schedule.

Signup and view all the flashcards

Project Schedule Network Diagram

Assigns start and finish dates to the project activities.

Signup and view all the flashcards

Draft A Project Schedule

Perform mathematical analysis, evaluate assumptions, consider resources, and assign dates.

Signup and view all the flashcards

Critical Activities

They are the activities on the critical path.

Signup and view all the flashcards

Identify the Critical Path

Path with zero float where ES = LS and EF = LF.

Signup and view all the flashcards

Schedule Compression

Shortening the project schedule without impacting project scope.

Signup and view all the flashcards

Fast-Tracking

Compressing total project duration by performing sequential activities concurrently.

Signup and view all the flashcards

Crashing

Analyzes cost and schedule trade-offs, allocate more resources to activities on the critical path.

Signup and view all the flashcards

Optimize the Project Schedule

Consider resource leveling, analyze Activities on the critical path and recalculate the critical path after.

Signup and view all the flashcards

Crash Cost Plotting Methods

Techniques for crash cost analysis using visuals.

Signup and view all the flashcards

Schedule Baselines

The management-approved schedule from the schedule network analysis. It's also a basis for measuring schedule performance.

Signup and view all the flashcards

Establish a Schedule Baseline

Gather preliminary schedule, distribute proposed baseline, incorporate changes from management, or follow change control

Signup and view all the flashcards

Control Schedule Process

The process of monitoring schedule performance and controlling changes.

Signup and view all the flashcards

EVM (Earned Value Management)

Calculates three independent variables to assess/monitor project cost and schedule progress.

Signup and view all the flashcards

Planned Value (PV)

The budgeted portion of the approved cost estimate for scheduled work during a specific period.

Signup and view all the flashcards

Earned Value

Measures work accomplished in relation to scheduled cost/time

Signup and view all the flashcards

Actual Cost (AC)

Costs to do the work.

Signup and view all the flashcards

Schedule Variance (SV)

Tool to show in monetary terms if Project is ahead or behind. SV = EV - PV

Signup and view all the flashcards

Schedule Performance Index (SPI)

Shows efficient schedule (ratio). SPI = EV / PV, If over 1 the project is ahead and less than 1 behind.

Signup and view all the flashcards

Control The Project Schedule

Process of implementing a schedule change control system,evaluating change requests and use performance measurement techniques.

Signup and view all the flashcards

Schedule Performance Measurement

A technique for determine project time compared to plan. Schedule Variance (SV), Schedule Performance Index (SPI), trend analysis, Variance analysis are all include.

Signup and view all the flashcards

Study Notes

  • Developing and controlling a project schedule involves drafting a schedule, identifying the critical path, optimizing the schedule, establishing a baseline, and controlling the schedule.

Project Management Framework

  • Project Integration Management covers developing the project charter, management plan, directing project execution, monitoring project work, and closing the project.
  • Project Scope Management includes collecting requirements, defining project scope, creating a WBS, verifying scope, and controlling scope.
  • Project Time Management involves defining project activities, sequencing activities, estimating activity resources and durations, developing the schedule, and controlling the schedule.
  • Project Cost Management includes estimating costs and determining the budget, as well as controlling costs.
  • Project Quality Management covers planning quality, performing quality assurance, and controlling quality.
  • Project Human Resource Management includes developing the human resource plan, acquiring the project team, developing the team, and managing the team.
  • Project Communications Management involves identifying stakeholders, planning communications, distributing information, managing stakeholder expectations, and reporting performance.
  • Project Risk Management includes planning risk management, identifying risks, performing qualitative and quantitative risk analysis, planning risk responses, and monitoring and controlling risks.
  • Project Procurement Management covers planning procurements, conducting procurements, administering procurements, and closing procurements.

Project Schedules

  • Project schedules serve as plans that define when activities starts and ends in a sequence.
  • Schedules coordinate activities into a single, comprehensive master plan leading to successful scheduling performance.

The Develop Schedule Process

  • Defining start and end dates for project activities is an important part
  • Inputs to the process include:
    • Activity list and attributes
    • Project schedule network diagrams
    • Activity resource requirements and resource calendars
    • Activity duration estimates
    • Project scope statement and Enterprise environmental factors
    • Organizational process assets such as defined schedules.
  • Common tools and techniques are:
    • Schedule network analysis
    • Critical path method
    • Critical chain method
    • Resource leveling
    • "What-if" scenario analysis
    • Applying leads and lags
    • Schedule compression
    • Scheduling tool is also used
  • Outputs include a completed Project schedule, schedule baseline, updated data, and updates to existing project documents to reflect scheduling outcomes.

Standard Schedule Diagramming Notations

  • ES stands for early start, The earliest time an activity can start
  • EF stands for early finish, the earliest time an activity can finish
  • LF stands for late finish, The latest time an activity can finish
  • LS stands for late start, The latest time an activity can start
  • DU is duration and the number of work periods required for activity completion

The Critical Path

  • A critical path represents the path with the longest total duration.
  • This path has no scheduling flexibility meaning activities along this path must be completed as planned to meet deadlines.
  • Schedule management can be performed by ensuring activities are completed on time

Float

  • Float shows the total time an activity can be delayed from its early start (ES) without delaying the project finish date or consecutive activities
  • Two kinds of floats are:
    • Total float
    • Free float

Schedule Network Analysis

  • Schedule network analysis calculates the theoretical early and late start and finish dates for all project activities.
  • Four main methods include:
    • Critical Path Method (CPM)
    • Critical chain method
    • What-if scenario
    • Resource leveling

Critical Path Method (CPM)

  • Critical Path Method (CPM) is a popular schedule network analysis method, commonly used in the business world.
  • CPM uses sequential finish-to-start network logic to effectively manage time
  • Calculates one early and late start and finish date for each activity.
  • CPM uses a single duration estimate

The Critical Chain Method

  • The Critical Chain Method adjusts project schedules based on resource considerations.
  • This is done by considering:
    • Resource limitations
    • Adjustments to schedule
    • Planning for reserves
    • Mitigation of cost and schedule risks
  • It does so by analyzing the critical path alongside available resources.

What-If Scenario Analysis

  • Used to consider different situations that might occur and influence the schedule.
  • Computes different schedules based on potential delays.
  • Simulated outcomes can be used in risk response plans.
  • Helps select the optimum plan.

Resource Leveling

  • Used to analyze the schedule model to readjust work assignments.
  • It helps address scheduling activities after the critical path has been identified
  • Found in many types of project management software.

Schedule Formats

  • The Bar chart format offers,
    • start and end dates,
    • duration,
    • order.
  • It shows precedence relationships and completion percentage
  • A Bar Chart is useful for presenting the project status to management
  • The Milestone Chart is suitable for presenting a summary of the project and includes
    • The project's milestones
    • Icons/Symbold
    • Overall schedule
  • Network Diagram format.
    • Assigns activities to start and finish dates
    • It also Communicates project status in terms of activity precedence relationships.

Drafting a Project Schedule

  • Steps to drafting a project schedule:
    • Perform a mathematical analysis to determine durations of time for resource limits, and other constraints.
    • Evaluate possible constraints for schedule development.
    • Assess resource availability.
    • Consult project calendars and assign dates to activities.
    • Calculate potential project durations under different constraints.
    • Consider external resource date constraints, if applicable.
    • Select project management software that suits needs and budget.
    • Review schedule drafts with the project team and customer.
    • Choose the publishing format.
    • Disseminate the preliminary schedule for approval.
    • Baseline the schedule after its approved.

Completed Project Schedule

  • Project Start Date: May 11, 2009
  • Work Package: TRN0001

Critical Activities

  • Indicate activities on the critical path.
  • Exhibit the same early start and late start dates, and early finish with late finish dates.

Identify the Criticall Path

  • Steps include:
    • Conduct forward pass to determine the Earliest State time and Earliest Finish for each activity
    • Conduct backward pass to determine the Latest State time and Latest Finish for each activity
    • Calculate float
    • Identify the critical path by the longest total and zero float

Schedule Compression

  • Schedule compression shortens the schedule without affecting the scope.
  • The two primary methods for schedule compression are fast-tracking and crashing.

Fast-Tracking

  • Fast-tracking compresses the project's total duration by performing otherwise sequential activities concurrently.
  • Project duration shortens.

Crashing

  • Crashing optimizes cost versus schedule tradeoffs.
  • It allocates maximum resources to activities on the critical path.

Schedule Baseline

  • The schedule baseline defines the project plan approved by management.
  • It measures and reports schedule performance.

Control Schedule Process

  • The control schedule process monitors performance and controls changes in the schedule.
  • Important actions include getting stakeholder feedback and creating a schedule baseline.
  • Key inputs include project management plan, project schedule, work performance information, and organizational/process assets.
  • Used tools performance reviews, variance analysis, project management software resource levelling, "what if analysis", schedule compression, and scheduling tools.
  • Outputs include work progress reports, along with any updates to project management plans, and documents.

Earned Value Management (EVM)

  • EVM measures project progress as well as costs.
  • It compares actual schedule and cost performance against the planned performance.
  • It is important to understand the financial cost of the project you're performing.

EVM Measures

  • Calculates three independent variables to assess and monitor performance progress
    • Planned Value (PV)
    • Earned Value (EV)
    • Actual Cost (AC)
  • These variables provide measures of work accomplished.
  • Forecasts the project cost at completion

Planned Value (PV)

  • Represents the budgeted cost is designated for project work during a given time

Earned Value (EV)

  • Composite measurement of the performance based on schedule and the total cost.
  • It is calculated using the percentage of work completed times the budgeted cost.

Actual Cost (AC)

  • Total costs to date that have been incurred while accomplishing work performed.

EVM Measures

  • Schedule Variance (SV) measures deviations from the planned schedule, calculated by the formula SV = EV - PV.
  • Schedule Performance Index (SPI) gauges the efficiency of work completed versus planned, with SPI = EV / PV.
  • Cost Variance (CV) identifies budget deviations, determined by CV = EV - AC.
  • Cost Performance Index (CPI) assesses the efficiency of costs, calculated by CPI = EV / AC.

Schedule Performance Measurement

  • Used to determine how a project is performing based on time versus it's planned performance
  • Indicates the variance of actual work performed and work scheduled
  • Performance measurement techniques:
    • Schedule Variance (SV)
    • Schedule Performance Index (SPI)
    • Variance-and-Trend Analysis
  • Determines detrimental risk and plans corrective actions

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Mastering Project Schedule Management
7 questions

Mastering Project Schedule Management

WellIntentionedDalmatianJasper avatar
WellIntentionedDalmatianJasper
Mastering Project Schedule Management
10 questions
Project Schedule Management Overview
30 questions
Use Quizgecko on...
Browser
Browser