What is the total duration allocated for the casting of columns during the project?
What is the total duration allocated for the casting of columns during the project?
- 19 days (correct)
- 18 days
- 12 days
- 15 days
On which date was the slab casting scheduled for the first floor?
On which date was the slab casting scheduled for the first floor?
- 04-01-24
- 13-02-24
- 05-01-24 (correct)
- 24-01-24
Which phase takes the longest time according to the schedule?
Which phase takes the longest time according to the schedule?
- Casting of Lift Walls
- Casting of Staircase
- Shuttering work for slab
- Third Floor construction (correct)
When will the shuttering work for the slab be completed?
When will the shuttering work for the slab be completed?
Which task was scheduled last in the timeline provided?
Which task was scheduled last in the timeline provided?
What is the total duration for the Superstructure phase?
What is the total duration for the Superstructure phase?
Which task follows the completion of the Compound Wall Preparation/Fencing?
Which task follows the completion of the Compound Wall Preparation/Fencing?
How long does the Reinforcement works for footings and columns take?
How long does the Reinforcement works for footings and columns take?
What is the scheduled start date for the Anti-termite & Waterproofing layer?
What is the scheduled start date for the Anti-termite & Waterproofing layer?
Which task is scheduled to begin immediately after Excavating Foundation?
Which task is scheduled to begin immediately after Excavating Foundation?
What is the planned duration for the Casting of Staircase?
What is the planned duration for the Casting of Staircase?
On which day does the Substructure phase officially finish?
On which day does the Substructure phase officially finish?
What is the predecessor task for Casting of Columns on the First Floor?
What is the predecessor task for Casting of Columns on the First Floor?
Flashcards
Demolition Duration
Demolition Duration
The time required to complete demolition and site clearance.
Substructure Duration
Substructure Duration
The time spent on substructure tasks such as foundation excavation and concrete pouring.
Superstructure Duration
Superstructure Duration
The period involved in constructing the upper part of the building above the foundation.
Foundation Excavation Duration
Foundation Excavation Duration
Signup and view all the flashcards
Slab Casting Duration
Slab Casting Duration
Signup and view all the flashcards
Column Casting Duration
Column Casting Duration
Signup and view all the flashcards
Site Clearance Duration
Site Clearance Duration
Signup and view all the flashcards
Wall Casting Duration
Wall Casting Duration
Signup and view all the flashcards
Slab Casting Schedule
Slab Casting Schedule
Signup and view all the flashcards
Staircase Casting Date
Staircase Casting Date
Signup and view all the flashcards
Lift Wall Casting
Lift Wall Casting
Signup and view all the flashcards
Floor Casting Duration
Floor Casting Duration
Signup and view all the flashcards
Study Notes
Project Schedule
-
General Work duration is 6 days, starting 06-11-23 and finishing 13-11-23
-
Demolition, Site Clearance takes 4 days, starting 06-11-23 and finishing 09-11-23
-
Compound Wall Preparation/Fencing is 2 days, beginning 10-11-23 and ending 13-11-23
-
Lineout takes 2 days (09-11-23 to 10-11-23), dependent on a prior activity with 3SS-1 day.
-
Substructure work spans 13 days, from 13-11-23 to 29-11-23.
-
Foundation work is also 13 days, starting on 13-11-23 and concluding on 29-11-23.
-
Excavate Foundation duration is 3 days, starting 13-11-23 and ending 15-11-23, preceding activity is task 4.
-
P.C.C. for all footings is 1 day (16-11-23).
-
Reinforcement works for footings and columns spans 6 days (17-11-23 to 24-11-23).
-
Soiling (Backfilling) takes 2 days (22-11-23 to 23-11-23).
-
Prepare and pour concrete for floor is 3 days, from 24-11-23 to 28-11-23
-
Anti-termite & Waterproofing layer is 1 day, finishing on 29-11-23
-
Superstructure project duration is 52 days, starting 30-11-23 and ending 13-02-24
-
Ground Floor is 52 days, with a start date of 30-11-23 and end of 13-02-24
-
Casting of Columns takes 6 days (30-11-23 to 07-12-23).
-
Casting of Lift Walls is 1 day (07-12-23), dependent on 15FS-3 days preceding task.
-
Casting of Staircase is 1 day (13-02-24).
-
Shuttering work for slab is 6 days (08-12-23 to 15-12-23).
-
Slab Casting is 1 day (18-12-23).
-
First Floor takes 39 days, starting 19-12-23 and completing 13-02-24
-
Casting of Columns (First Floor) is 6 days (19-12-23 to 26-12-23).
-
Casting of Lift Walls (First Floor) is 1 day (26-12-23).
-
Casting of Staircase (First Floor) is 1 day (13-02-24).
-
Shuttering work for slab (First Floor) is 6 days (27-12-23 to 04-01-24).
-
Slab Casting (First Floor) is 1 day (05-01-24).
-
Second Floor takes 26 days (08-01-24 to 13-02-24)
-
Casting of Columns (Second Floor) takes 6 days (08-01-24 to 15-01-24)
-
Casting of Lift Walls (Second Floor) takes 1 day (15-01-24)
-
Casting of Staircase (Second Floor) is 1 day (13-02-24).
-
Shuttering work for slab (Second Floor) takes 6 days (16-01-24 to 23-01-24).
-
Slab Casting (Second Floor) takes 1 day (24-01-24).
-
Third Floor takes 13 days (25-01-24 to 13-02-24)
-
Casting of Columns (Third Floor) takes 6 days (25-01-24 to 02-02-24),
-
Casting of Lift Walls (Third Floor) takes 1 day (02-02-24)
-
Casting of Staircase (Third Floor) takes 1 day (13-02-24).
-
Shuttering work for slab (Third Floor) takes 6 days (05-02-24 to 12-02-24).
-
Slab Casting (Third Floor) takes 1 day (13-02-24).