Construction Project Schedule Overview
13 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the total duration allocated for the casting of columns during the project?

  • 19 days (correct)
  • 18 days
  • 12 days
  • 15 days
  • On which date was the slab casting scheduled for the first floor?

  • 04-01-24
  • 13-02-24
  • 05-01-24 (correct)
  • 24-01-24
  • Which phase takes the longest time according to the schedule?

  • Casting of Lift Walls
  • Casting of Staircase
  • Shuttering work for slab
  • Third Floor construction (correct)
  • When will the shuttering work for the slab be completed?

    <p>23-01-24</p> Signup and view all the answers

    Which task was scheduled last in the timeline provided?

    <p>Casting of Staircase</p> Signup and view all the answers

    What is the total duration for the Superstructure phase?

    <p>52 days</p> Signup and view all the answers

    Which task follows the completion of the Compound Wall Preparation/Fencing?

    <p>Lineout</p> Signup and view all the answers

    How long does the Reinforcement works for footings and columns take?

    <p>6 days</p> Signup and view all the answers

    What is the scheduled start date for the Anti-termite & Waterproofing layer?

    <p>29-11-23</p> Signup and view all the answers

    Which task is scheduled to begin immediately after Excavating Foundation?

    <p>P.C.C.for all footings</p> Signup and view all the answers

    What is the planned duration for the Casting of Staircase?

    <p>1 day</p> Signup and view all the answers

    On which day does the Substructure phase officially finish?

    <p>29-11-23</p> Signup and view all the answers

    What is the predecessor task for Casting of Columns on the First Floor?

    <p>Casting of Lift Walls</p> Signup and view all the answers

    Study Notes

    Project Schedule

    • General Work duration is 6 days, starting 06-11-23 and finishing 13-11-23

    • Demolition, Site Clearance takes 4 days, starting 06-11-23 and finishing 09-11-23

    • Compound Wall Preparation/Fencing is 2 days, beginning 10-11-23 and ending 13-11-23

    • Lineout takes 2 days (09-11-23 to 10-11-23), dependent on a prior activity with 3SS-1 day.

    • Substructure work spans 13 days, from 13-11-23 to 29-11-23.

    • Foundation work is also 13 days, starting on 13-11-23 and concluding on 29-11-23.

    • Excavate Foundation duration is 3 days, starting 13-11-23 and ending 15-11-23, preceding activity is task 4.

    • P.C.C. for all footings is 1 day (16-11-23).

    • Reinforcement works for footings and columns spans 6 days (17-11-23 to 24-11-23).

    • Soiling (Backfilling) takes 2 days (22-11-23 to 23-11-23).

    • Prepare and pour concrete for floor is 3 days, from 24-11-23 to 28-11-23

    • Anti-termite & Waterproofing layer is 1 day, finishing on 29-11-23

    • Superstructure project duration is 52 days, starting 30-11-23 and ending 13-02-24

    • Ground Floor is 52 days, with a start date of 30-11-23 and end of 13-02-24

    • Casting of Columns takes 6 days (30-11-23 to 07-12-23).

    • Casting of Lift Walls is 1 day (07-12-23), dependent on 15FS-3 days preceding task.

    • Casting of Staircase is 1 day (13-02-24).

    • Shuttering work for slab is 6 days (08-12-23 to 15-12-23).

    • Slab Casting is 1 day (18-12-23).

    • First Floor takes 39 days, starting 19-12-23 and completing 13-02-24

    • Casting of Columns (First Floor) is 6 days (19-12-23 to 26-12-23).

    • Casting of Lift Walls (First Floor) is 1 day (26-12-23).

    • Casting of Staircase (First Floor) is 1 day (13-02-24).

    • Shuttering work for slab (First Floor) is 6 days (27-12-23 to 04-01-24).

    • Slab Casting (First Floor) is 1 day (05-01-24).

    • Second Floor takes 26 days (08-01-24 to 13-02-24)

    • Casting of Columns (Second Floor) takes 6 days (08-01-24 to 15-01-24)

    • Casting of Lift Walls (Second Floor) takes 1 day (15-01-24)

    • Casting of Staircase (Second Floor) is 1 day (13-02-24).

    • Shuttering work for slab (Second Floor) takes 6 days (16-01-24 to 23-01-24).

    • Slab Casting (Second Floor) takes 1 day (24-01-24).

    • Third Floor takes 13 days (25-01-24 to 13-02-24)

    • Casting of Columns (Third Floor) takes 6 days (25-01-24 to 02-02-24),

    • Casting of Lift Walls (Third Floor) takes 1 day (02-02-24)

    • Casting of Staircase (Third Floor) takes 1 day (13-02-24).

    • Shuttering work for slab (Third Floor) takes 6 days (05-02-24 to 12-02-24).

    • Slab Casting (Third Floor) takes 1 day (13-02-24).

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    This quiz covers the timeline and phases of a construction project, detailing tasks such as demolition, site clearance, and foundation work. Participants will learn about the duration and dependencies of various activities involved in the construction process. Assess your understanding of scheduling in project management.