Questions and Answers
What is the total duration allocated for the casting of columns during the project?
What is the total duration allocated for the casting of columns during the project?
On which date was the slab casting scheduled for the first floor?
On which date was the slab casting scheduled for the first floor?
Which phase takes the longest time according to the schedule?
Which phase takes the longest time according to the schedule?
When will the shuttering work for the slab be completed?
When will the shuttering work for the slab be completed?
Signup and view all the answers
Which task was scheduled last in the timeline provided?
Which task was scheduled last in the timeline provided?
Signup and view all the answers
What is the total duration for the Superstructure phase?
What is the total duration for the Superstructure phase?
Signup and view all the answers
Which task follows the completion of the Compound Wall Preparation/Fencing?
Which task follows the completion of the Compound Wall Preparation/Fencing?
Signup and view all the answers
How long does the Reinforcement works for footings and columns take?
How long does the Reinforcement works for footings and columns take?
Signup and view all the answers
What is the scheduled start date for the Anti-termite & Waterproofing layer?
What is the scheduled start date for the Anti-termite & Waterproofing layer?
Signup and view all the answers
Which task is scheduled to begin immediately after Excavating Foundation?
Which task is scheduled to begin immediately after Excavating Foundation?
Signup and view all the answers
What is the planned duration for the Casting of Staircase?
What is the planned duration for the Casting of Staircase?
Signup and view all the answers
On which day does the Substructure phase officially finish?
On which day does the Substructure phase officially finish?
Signup and view all the answers
What is the predecessor task for Casting of Columns on the First Floor?
What is the predecessor task for Casting of Columns on the First Floor?
Signup and view all the answers
Study Notes
Project Schedule
-
General Work duration is 6 days, starting 06-11-23 and finishing 13-11-23
-
Demolition, Site Clearance takes 4 days, starting 06-11-23 and finishing 09-11-23
-
Compound Wall Preparation/Fencing is 2 days, beginning 10-11-23 and ending 13-11-23
-
Lineout takes 2 days (09-11-23 to 10-11-23), dependent on a prior activity with 3SS-1 day.
-
Substructure work spans 13 days, from 13-11-23 to 29-11-23.
-
Foundation work is also 13 days, starting on 13-11-23 and concluding on 29-11-23.
-
Excavate Foundation duration is 3 days, starting 13-11-23 and ending 15-11-23, preceding activity is task 4.
-
P.C.C. for all footings is 1 day (16-11-23).
-
Reinforcement works for footings and columns spans 6 days (17-11-23 to 24-11-23).
-
Soiling (Backfilling) takes 2 days (22-11-23 to 23-11-23).
-
Prepare and pour concrete for floor is 3 days, from 24-11-23 to 28-11-23
-
Anti-termite & Waterproofing layer is 1 day, finishing on 29-11-23
-
Superstructure project duration is 52 days, starting 30-11-23 and ending 13-02-24
-
Ground Floor is 52 days, with a start date of 30-11-23 and end of 13-02-24
-
Casting of Columns takes 6 days (30-11-23 to 07-12-23).
-
Casting of Lift Walls is 1 day (07-12-23), dependent on 15FS-3 days preceding task.
-
Casting of Staircase is 1 day (13-02-24).
-
Shuttering work for slab is 6 days (08-12-23 to 15-12-23).
-
Slab Casting is 1 day (18-12-23).
-
First Floor takes 39 days, starting 19-12-23 and completing 13-02-24
-
Casting of Columns (First Floor) is 6 days (19-12-23 to 26-12-23).
-
Casting of Lift Walls (First Floor) is 1 day (26-12-23).
-
Casting of Staircase (First Floor) is 1 day (13-02-24).
-
Shuttering work for slab (First Floor) is 6 days (27-12-23 to 04-01-24).
-
Slab Casting (First Floor) is 1 day (05-01-24).
-
Second Floor takes 26 days (08-01-24 to 13-02-24)
-
Casting of Columns (Second Floor) takes 6 days (08-01-24 to 15-01-24)
-
Casting of Lift Walls (Second Floor) takes 1 day (15-01-24)
-
Casting of Staircase (Second Floor) is 1 day (13-02-24).
-
Shuttering work for slab (Second Floor) takes 6 days (16-01-24 to 23-01-24).
-
Slab Casting (Second Floor) takes 1 day (24-01-24).
-
Third Floor takes 13 days (25-01-24 to 13-02-24)
-
Casting of Columns (Third Floor) takes 6 days (25-01-24 to 02-02-24),
-
Casting of Lift Walls (Third Floor) takes 1 day (02-02-24)
-
Casting of Staircase (Third Floor) takes 1 day (13-02-24).
-
Shuttering work for slab (Third Floor) takes 6 days (05-02-24 to 12-02-24).
-
Slab Casting (Third Floor) takes 1 day (13-02-24).
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the timeline and phases of a construction project, detailing tasks such as demolition, site clearance, and foundation work. Participants will learn about the duration and dependencies of various activities involved in the construction process. Assess your understanding of scheduling in project management.