Podcast
Questions and Answers
What is the technique used to plan the project work at various levels of detail depending upon the availability of information?
What is the technique used to plan the project work at various levels of detail depending upon the availability of information?
What do you call a WBS component at the bottom level of a branch of the WBS hierarchy for which some planning can be performed?
What do you call a WBS component at the bottom level of a branch of the WBS hierarchy for which some planning can be performed?
In rolling wave planning, work to be performed in the near future is planned at what level of the WBS?
In rolling wave planning, work to be performed in the near future is planned at what level of the WBS?
When decomposing a work package into activities, who should be involved according to the text?
When decomposing a work package into activities, who should be involved according to the text?
Signup and view all the answers
What makes the core of a project according to the text?
What makes the core of a project according to the text?
Signup and view all the answers
What is the primary purpose of the resource leveling technique?
What is the primary purpose of the resource leveling technique?
Signup and view all the answers
What does resource leveling involve?
What does resource leveling involve?
Signup and view all the answers
In project management, what does a what-if scenario analysis typically focus on?
In project management, what does a what-if scenario analysis typically focus on?
Signup and view all the answers
When is risk planning often initiated during project management?
When is risk planning often initiated during project management?
Signup and view all the answers
Which project management method factors in resource uncertainty?
Which project management method factors in resource uncertainty?
Signup and view all the answers
What is the major task of the Define Activities process?
What is the major task of the Define Activities process?
Signup and view all the answers
What is the purpose of fast tracking in project management?
What is the purpose of fast tracking in project management?
Signup and view all the answers
In project management, what does changing the quantity of a resource committed to an activity affect?
In project management, what does changing the quantity of a resource committed to an activity affect?
Signup and view all the answers
Which technique analyzes cost and schedule tradeoffs to decrease project duration with minimal additional cost?
Which technique analyzes cost and schedule tradeoffs to decrease project duration with minimal additional cost?
Signup and view all the answers
When measuring activity duration, what is the difference between work units and calendar units?
When measuring activity duration, what is the difference between work units and calendar units?
Signup and view all the answers
In project management, what is an example of crashing?
In project management, what is an example of crashing?
Signup and view all the answers
What serves as a baseline for tracking project progress in project time management?
What serves as a baseline for tracking project progress in project time management?
Signup and view all the answers
What is the main limitation of crashing as a schedule compression technique?
What is the main limitation of crashing as a schedule compression technique?
Signup and view all the answers
Which process in project management involves determining dependencies among the activities in the activity list?
Which process in project management involves determining dependencies among the activities in the activity list?
Signup and view all the answers
Why is it important to guard against misconceptions when applying crashing in project management?
Why is it important to guard against misconceptions when applying crashing in project management?
Signup and view all the answers
What is the first step towards schedule planning after creating the WBS?
What is the first step towards schedule planning after creating the WBS?
Signup and view all the answers
What serves as the starting point for defining activities in project management?
What serves as the starting point for defining activities in project management?
Signup and view all the answers
Which project management component provides key elements like deliverables, assumptions, and constraints useful in defining activities?
Which project management component provides key elements like deliverables, assumptions, and constraints useful in defining activities?
Signup and view all the answers
In project management, what is needed to define activities properly?
In project management, what is needed to define activities properly?
Signup and view all the answers
What technique plans project work at different levels of detail based on information availability?
What technique plans project work at different levels of detail based on information availability?
Signup and view all the answers
What is the purpose of crashing in project management?
What is the purpose of crashing in project management?
Signup and view all the answers
In project management, what does fast tracking involve?
In project management, what does fast tracking involve?
Signup and view all the answers
What is the role of rolling wave planning in project management?
What is the role of rolling wave planning in project management?
Signup and view all the answers
When defining activities in a project, what is the purpose of creating a Work Breakdown Structure (WBS)?
When defining activities in a project, what is the purpose of creating a Work Breakdown Structure (WBS)?
Signup and view all the answers
In resource allocation, what is an important consideration for a project manager dealing with a limited budget?
In resource allocation, what is an important consideration for a project manager dealing with a limited budget?
Signup and view all the answers
What is the purpose of decomposing a work package into activities?
What is the purpose of decomposing a work package into activities?
Signup and view all the answers
What is a key constraint for sequencing activities in a project schedule?
What is a key constraint for sequencing activities in a project schedule?
Signup and view all the answers
What is the main focus of project time management?
What is the main focus of project time management?
Signup and view all the answers
In project management, what does WBS stand for?
In project management, what does WBS stand for?
Signup and view all the answers
Which technique plans project work at various levels based on the availability of information?
Which technique plans project work at various levels based on the availability of information?
Signup and view all the answers
What is the consequence of not considering activity dependencies in project scheduling?
What is the consequence of not considering activity dependencies in project scheduling?
Signup and view all the answers
How are work packages transformed into activities in project planning?
How are work packages transformed into activities in project planning?
Signup and view all the answers
What role does rolling wave planning play in project management?
What role does rolling wave planning play in project management?
Signup and view all the answers
What is the primary focus when estimating activity resource requirements?
What is the primary focus when estimating activity resource requirements?
Signup and view all the answers
Why is it important to control the project schedule once it has been developed and approved?
Why is it important to control the project schedule once it has been developed and approved?
Signup and view all the answers
Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.
Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.
Signup and view all the answers
The project schedule is a static document that does not change throughout the project execution.
The project schedule is a static document that does not change throughout the project execution.
Signup and view all the answers
Root cause analysis is conducted to identify the causes of schedule variance.
Root cause analysis is conducted to identify the causes of schedule variance.
Signup and view all the answers
Change requests for schedule-related corrective actions do not need to go through integrated change control for approval.
Change requests for schedule-related corrective actions do not need to go through integrated change control for approval.
Signup and view all the answers
Schedule data is used to develop the project schedule, and it is a one-time process without any iterations.
Schedule data is used to develop the project schedule, and it is a one-time process without any iterations.
Signup and view all the answers
The schedule baseline is a dynamic version of the project schedule that changes frequently during the project execution phase.
The schedule baseline is a dynamic version of the project schedule that changes frequently during the project execution phase.
Signup and view all the answers
A schedule change at the project level is called a schedule revision.
A schedule change at the project level is called a schedule revision.
Signup and view all the answers
Updates to project documents may include changes to resource requirements and project calendar.
Updates to project documents may include changes to resource requirements and project calendar.
Signup and view all the answers
All significant schedule changes must be reported only to the project team, not to stakeholders.
All significant schedule changes must be reported only to the project team, not to stakeholders.
Signup and view all the answers
Crashing is a schedule compression technique that involves increasing the project duration with minimal additional cost.
Crashing is a schedule compression technique that involves increasing the project duration with minimal additional cost.
Signup and view all the answers
The schedule performance analysis and progress report review cannot result in change requests to the project schedule baseline.
The schedule performance analysis and progress report review cannot result in change requests to the project schedule baseline.
Signup and view all the answers
Fast tracking in project management involves completing activities in sequence to reduce project risk.
Fast tracking in project management involves completing activities in sequence to reduce project risk.
Signup and view all the answers
Lessons learned from the schedule control process cannot be documented for future projects.
Lessons learned from the schedule control process cannot be documented for future projects.
Signup and view all the answers
Change requests in project management can impact the project schedule, requiring adjustments to the timeline.
Change requests in project management can impact the project schedule, requiring adjustments to the timeline.
Signup and view all the answers
The schedule management plan is not updated to reflect changes during the schedule control process.
The schedule management plan is not updated to reflect changes during the schedule control process.
Signup and view all the answers
Approved change requests can update the schedule baseline.
Approved change requests can update the schedule baseline.
Signup and view all the answers
Progress reports play a key role in monitoring and controlling the project schedule.
Progress reports play a key role in monitoring and controlling the project schedule.
Signup and view all the answers
Performance reviews use Earned Value Management (EVM) and Schedule Performance Index (SPI) to measure the schedule performance of a project.
Performance reviews use Earned Value Management (EVM) and Schedule Performance Index (SPI) to measure the schedule performance of a project.
Signup and view all the answers
Performance measurement techniques are used to analyze the schedule performance of a project.
Performance measurement techniques are used to analyze the schedule performance of a project.
Signup and view all the answers
Progress reports provide information on missed planned dates in a project.
Progress reports provide information on missed planned dates in a project.
Signup and view all the answers
Project management software may include a schedule change control system to evaluate and process schedule changes.
Project management software may include a schedule change control system to evaluate and process schedule changes.
Signup and view all the answers
Performance measurements like schedule variance (SV) and schedule performance index (SPI) should not be documented or communicated to stakeholders.
Performance measurements like schedule variance (SV) and schedule performance index (SPI) should not be documented or communicated to stakeholders.
Signup and view all the answers
Corrective actions in project management are solely focused on fixing past mistakes.
Corrective actions in project management are solely focused on fixing past mistakes.
Signup and view all the answers
The output items of the schedule control process do not include recommendations for actions based on measurements and progress reports.
The output items of the schedule control process do not include recommendations for actions based on measurements and progress reports.
Signup and view all the answers
Schedule compression techniques, leads and lags adjustment, what-if scenario analysis are tools used in project scheduling.
Schedule compression techniques, leads and lags adjustment, what-if scenario analysis are tools used in project scheduling.
Signup and view all the answers
Crashing and fast tracking are two techniques used in time-management processes to compress the project schedule.
Crashing and fast tracking are two techniques used in time-management processes to compress the project schedule.
Signup and view all the answers
Schedule data is not used in the development of the project schedule.
Schedule data is not used in the development of the project schedule.
Signup and view all the answers
Performance measurements are not part of schedule control processes.
Performance measurements are not part of schedule control processes.
Signup and view all the answers
Change requests related to schedule modifications do not need to go through integrated change control for approval.
Change requests related to schedule modifications do not need to go through integrated change control for approval.
Signup and view all the answers
In project management, crashing involves adding additional resources to speed up activities and reduce project duration.
In project management, crashing involves adding additional resources to speed up activities and reduce project duration.
Signup and view all the answers
The approved project schedule is used as a baseline to track the project progress.
The approved project schedule is used as a baseline to track the project progress.
Signup and view all the answers
The schedule development process continues throughout project execution due to approved changes and risk occurrences.
The schedule development process continues throughout project execution due to approved changes and risk occurrences.
Signup and view all the answers
Schedule data is used to develop the project schedule in a one-time process without any iterations.
Schedule data is used to develop the project schedule in a one-time process without any iterations.
Signup and view all the answers
Schedule baseline is a static document that never changes once approved.
Schedule baseline is a static document that never changes once approved.
Signup and view all the answers
Change requests for schedule-related corrective actions don't need to go through integrated change control for approval.
Change requests for schedule-related corrective actions don't need to go through integrated change control for approval.
Signup and view all the answers
All significant schedule changes must only be reported to the project team, not stakeholders.
All significant schedule changes must only be reported to the project team, not stakeholders.
Signup and view all the answers
Fast tracking in project management involves completing activities out of sequence to reduce project risk.
Fast tracking in project management involves completing activities out of sequence to reduce project risk.
Signup and view all the answers
Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.
Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.
Signup and view all the answers
The project schedule is a dynamic document that frequently changes during the project execution phase.
The project schedule is a dynamic document that frequently changes during the project execution phase.
Signup and view all the answers
The main limitation of crashing as a schedule compression technique is that it increases the project duration with minimal additional cost.
The main limitation of crashing as a schedule compression technique is that it increases the project duration with minimal additional cost.
Signup and view all the answers
Study Notes
- When decomposing work packages into activities, involve individuals familiar with the work or responsible for them.
- Rolling wave planning is used for high-level scheduling when information is limited, planning work in detail based on availability of information.
- Expert judgment can be used to create project schedules by compressing project duration through techniques like fast tracking and crashing.
- Crashing involves cost and schedule tradeoffs to shorten project duration, while fast tracking involves performing activities in parallel.
- Resource leveling is used to address resource needs by reallocating resources between activities to meet specific delivery dates.
- What-if scenario analysis is used to assess the impact of specific scenarios on the project schedule, leading to risk planning.
- The Define Activities process involves identifying project activities starting from work packages in the WBS, broken down into individual activities.
- The project schedule is developed by identifying activities, estimating resources, and determining activity durations based on available resources.
- The critical path method is used to develop a schedule for given resources, while the critical chain method considers uncertainty in resource availability.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Learn about the key steps involved in creating a project schedule, including defining activities, arranging them in the correct order, and estimating required resources. This quiz provides insights into the foundational aspects of planning a project schedule.