Chapter 4

FreshestSparrow avatar
FreshestSparrow
·
·
Download

Start Quiz

Study Flashcards

80 Questions

What is the technique used to plan the project work at various levels of detail depending upon the availability of information?

Progressive elaboration

What do you call a WBS component at the bottom level of a branch of the WBS hierarchy for which some planning can be performed?

Planning component

In rolling wave planning, work to be performed in the near future is planned at what level of the WBS?

Low level

When decomposing a work package into activities, who should be involved according to the text?

Individuals familiar with the work packages or responsible for them

What makes the core of a project according to the text?

Activities

What is the primary purpose of the resource leveling technique?

To address the resource needs of activities with specific delivery dates

What does resource leveling involve?

Taking resources from one activity and assigning them to another

In project management, what does a what-if scenario analysis typically focus on?

Calculating the effects of specific scenarios on the schedule

When is risk planning often initiated during project management?

Following a what-if scenario analysis

Which project management method factors in resource uncertainty?

Critical chain method

What is the major task of the Define Activities process?

Generating the activity list by decomposing work packages

What is the purpose of fast tracking in project management?

To decrease the project duration by performing phases or activities in parallel that would normally be done in sequence

In project management, what does changing the quantity of a resource committed to an activity affect?

The duration estimate for the activity

Which technique analyzes cost and schedule tradeoffs to decrease project duration with minimal additional cost?

Crashing

When measuring activity duration, what is the difference between work units and calendar units?

Work units exclude holidays, while calendar units include them.

In project management, what is an example of crashing?

Approving overtime for the project team

What serves as a baseline for tracking project progress in project time management?

Approved project schedule

What is the main limitation of crashing as a schedule compression technique?

It may increase the cost and risk of the project

Which process in project management involves determining dependencies among the activities in the activity list?

Sequence Activities

Why is it important to guard against misconceptions when applying crashing in project management?

Misconceptions can lead to incorrect resource allocation decisions

What is the first step towards schedule planning after creating the WBS?

Activity definition

What serves as the starting point for defining activities in project management?

Work packages in the WBS

Which project management component provides key elements like deliverables, assumptions, and constraints useful in defining activities?

Project scope baseline

In project management, what is needed to define activities properly?

WBS and WBS dictionary

What technique plans project work at different levels of detail based on information availability?

Rolling wave planning

What is the purpose of crashing in project management?

To reduce the project duration by adding more resources

In project management, what does fast tracking involve?

Conducting activities in parallel that were originally planned in sequence

What is the role of rolling wave planning in project management?

Iteratively planning and detailing activities as the project progresses

When defining activities in a project, what is the purpose of creating a Work Breakdown Structure (WBS)?

To identify all the tasks required to complete the project scope

In resource allocation, what is an important consideration for a project manager dealing with a limited budget?

Reducing the project scope

What is the purpose of decomposing a work package into activities?

To break down the scope into smaller manageable components

What is a key constraint for sequencing activities in a project schedule?

Dependencies among activities

What is the main focus of project time management?

Time management

In project management, what does WBS stand for?

Work Breakdown Structure

Which technique plans project work at various levels based on the availability of information?

Rolling Wave Planning

What is the consequence of not considering activity dependencies in project scheduling?

Resource overallocation

How are work packages transformed into activities in project planning?

By decomposing them further into smaller components

What role does rolling wave planning play in project management?

Planning high-level activities first and detailed planning later

What is the primary focus when estimating activity resource requirements?

Resource optimization

Why is it important to control the project schedule once it has been developed and approved?

To keep the project on track

Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.

True

The project schedule is a static document that does not change throughout the project execution.

False

Root cause analysis is conducted to identify the causes of schedule variance.

True

Change requests for schedule-related corrective actions do not need to go through integrated change control for approval.

False

Schedule data is used to develop the project schedule, and it is a one-time process without any iterations.

False

The schedule baseline is a dynamic version of the project schedule that changes frequently during the project execution phase.

False

A schedule change at the project level is called a schedule revision.

True

Updates to project documents may include changes to resource requirements and project calendar.

True

All significant schedule changes must be reported only to the project team, not to stakeholders.

False

Crashing is a schedule compression technique that involves increasing the project duration with minimal additional cost.

False

The schedule performance analysis and progress report review cannot result in change requests to the project schedule baseline.

False

Fast tracking in project management involves completing activities in sequence to reduce project risk.

False

Lessons learned from the schedule control process cannot be documented for future projects.

False

Change requests in project management can impact the project schedule, requiring adjustments to the timeline.

True

The schedule management plan is not updated to reflect changes during the schedule control process.

False

Approved change requests can update the schedule baseline.

True

Progress reports play a key role in monitoring and controlling the project schedule.

True

Performance reviews use Earned Value Management (EVM) and Schedule Performance Index (SPI) to measure the schedule performance of a project.

True

Performance measurement techniques are used to analyze the schedule performance of a project.

True

Progress reports provide information on missed planned dates in a project.

True

Project management software may include a schedule change control system to evaluate and process schedule changes.

True

Performance measurements like schedule variance (SV) and schedule performance index (SPI) should not be documented or communicated to stakeholders.

False

Corrective actions in project management are solely focused on fixing past mistakes.

False

The output items of the schedule control process do not include recommendations for actions based on measurements and progress reports.

False

Schedule compression techniques, leads and lags adjustment, what-if scenario analysis are tools used in project scheduling.

True

Crashing and fast tracking are two techniques used in time-management processes to compress the project schedule.

True

Schedule data is not used in the development of the project schedule.

False

Performance measurements are not part of schedule control processes.

False

Change requests related to schedule modifications do not need to go through integrated change control for approval.

False

In project management, crashing involves adding additional resources to speed up activities and reduce project duration.

False

The approved project schedule is used as a baseline to track the project progress.

True

The schedule development process continues throughout project execution due to approved changes and risk occurrences.

True

Schedule data is used to develop the project schedule in a one-time process without any iterations.

False

Schedule baseline is a static document that never changes once approved.

False

Change requests for schedule-related corrective actions don't need to go through integrated change control for approval.

False

All significant schedule changes must only be reported to the project team, not stakeholders.

False

Fast tracking in project management involves completing activities out of sequence to reduce project risk.

False

Expedite the execution is one of the actions taken to bring future schedule performance in line with the schedule baseline.

True

The project schedule is a dynamic document that frequently changes during the project execution phase.

True

The main limitation of crashing as a schedule compression technique is that it increases the project duration with minimal additional cost.

False

Study Notes

  • When decomposing work packages into activities, involve individuals familiar with the work or responsible for them.
  • Rolling wave planning is used for high-level scheduling when information is limited, planning work in detail based on availability of information.
  • Expert judgment can be used to create project schedules by compressing project duration through techniques like fast tracking and crashing.
  • Crashing involves cost and schedule tradeoffs to shorten project duration, while fast tracking involves performing activities in parallel.
  • Resource leveling is used to address resource needs by reallocating resources between activities to meet specific delivery dates.
  • What-if scenario analysis is used to assess the impact of specific scenarios on the project schedule, leading to risk planning.
  • The Define Activities process involves identifying project activities starting from work packages in the WBS, broken down into individual activities.
  • The project schedule is developed by identifying activities, estimating resources, and determining activity durations based on available resources.
  • The critical path method is used to develop a schedule for given resources, while the critical chain method considers uncertainty in resource availability.

Learn about the key steps involved in creating a project schedule, including defining activities, arranging them in the correct order, and estimating required resources. This quiz provides insights into the foundational aspects of planning a project schedule.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Mastering Project Schedule Management
7 questions

Mastering Project Schedule Management

WellIntentionedDalmatianJasper avatar
WellIntentionedDalmatianJasper
Project Management: Schedule Baseline
15 questions
Use Quizgecko on...
Browser
Browser