Project Products and Specifications Quiz
11 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the purpose of identifying high-level project risks?

  • To speed up project completion
  • To increase the project cost
  • To ignore potential issues
  • To understand 'what could go wrong' and 'what can we do to stop it' (correct)
  • How does selecting the development methodology and life cycle approach impact a project?

  • It has no impact on the project outcome
  • It helps to review overall resource estimates
  • It only depends on past methodologies used by the company
  • It affects how the project progresses and is completed (correct)
  • Why is it important to review overall resource estimates after identifying project risks and selecting an approach?

  • To ignore potential resource shortages
  • To re-estimate efforts and resources based on identified risks and chosen approach (correct)
  • To decrease the project cost
  • To speed up the project without considering resource availability
  • What is a common misconception about project products?

    <p>Only physical items are considered project products.</p> Signup and view all the answers

    Why might specific instances of generic products like 'software modules' be left for later detailed planning?

    <p>Due to the complexity involved in identifying specific instances.</p> Signup and view all the answers

    What is the purpose of a Product Breakdown Structure (PBS) and Process Flow Diagram (PFD)?

    <p>To identify generic products like 'software modules' and 'design questionnaire'.</p> Signup and view all the answers

    Which of the following is NOT a part of the Product Description (PD)?

    <p>Testing results analysis</p> Signup and view all the answers

    What is the purpose of change control in managing a product or system?

    <p>To ensure unnecessary changes are avoided and all changes are documented</p> Signup and view all the answers

    In project team organization, why is it important to divide activities and create groups?

    <p>To facilitate better coordination and collaboration</p> Signup and view all the answers

    How can you distinguish a project as either objective or product-based?

    <p>By identifying the aim of the project, whether to produce a product or meet an objective</p> Signup and view all the answers

    When analyzing project characteristics, what is the significance of distinguishing between information system and embedded system projects?

    <p>Different characteristics and critical issues apply to each type</p> Signup and view all the answers