Questions and Answers
Which task has the highest effort requirement?
Which task has the highest effort requirement?
Which tasks are dependent on T2?
Which tasks are dependent on T2?
What is the total duration for T10?
What is the total duration for T10?
Which task is completed last based on the task schedule?
Which task is completed last based on the task schedule?
Signup and view all the answers
Which staff member is not allocated to any tasks during Week 0?
Which staff member is not allocated to any tasks during Week 0?
Signup and view all the answers
How many tasks depend on T4?
How many tasks depend on T4?
Signup and view all the answers
Which estimation technique is most crucial for organizations managing software projects?
Which estimation technique is most crucial for organizations managing software projects?
Signup and view all the answers
What is the dependency for task T9?
What is the dependency for task T9?
Signup and view all the answers
What is the primary focus of risk management in software development?
What is the primary focus of risk management in software development?
Signup and view all the answers
Which of the following factors contributes to uncertainties in software development?
Which of the following factors contributes to uncertainties in software development?
Signup and view all the answers
What is an example of a business risk in software development?
What is an example of a business risk in software development?
Signup and view all the answers
In the context of cost estimation, which technique relies on the manager's judgment and past experiences?
In the context of cost estimation, which technique relies on the manager's judgment and past experiences?
Signup and view all the answers
Which of the following is a type of risk that specifically affects the quality or performance of the developed software?
Which of the following is a type of risk that specifically affects the quality or performance of the developed software?
Signup and view all the answers
What does project risk primarily affect?
What does project risk primarily affect?
Signup and view all the answers
What is a common example of a project risk related to staffing?
What is a common example of a project risk related to staffing?
Signup and view all the answers
Which approach uses a formulaic method to estimate project effort based on product attributes?
Which approach uses a formulaic method to estimate project effort based on product attributes?
Signup and view all the answers
What should be done with the project plan as development progresses?
What should be done with the project plan as development progresses?
Signup and view all the answers
Which aspect is NOT essential in project scheduling?
Which aspect is NOT essential in project scheduling?
Signup and view all the answers
What is a recommended action to minimize delays in task execution?
What is a recommended action to minimize delays in task execution?
Signup and view all the answers
Which of the following is a key component of risk management in project planning?
Which of the following is a key component of risk management in project planning?
Signup and view all the answers
In the context of project scheduling, what should be estimated for each task?
In the context of project scheduling, what should be estimated for each task?
Signup and view all the answers
What is one primary purpose of regularly revising project estimates?
What is one primary purpose of regularly revising project estimates?
Signup and view all the answers
Which of the following describes the first step in the project planning process?
Which of the following describes the first step in the project planning process?
Signup and view all the answers
Which statement is true regarding task scheduling techniques?
Which statement is true regarding task scheduling techniques?
Signup and view all the answers
Study Notes
Tasks, Durations, and Dependencies
- Tasks have effort (person-days) and duration (days)
- Dependencies are represented with (M#) where M1-M8 are specific dependencies
- T1 has a duration of 10 days with 15 person-days required
- T2 has a duration of 15 days with 8 person-days required
- T3 depends on T1 and has a duration of 15 days with 20 person-days required
- T5 depends on T2 and T4 and has a duration of 10 days with 5 person-days required
- T6 depends on T1 and T2 and has a duration of 5 days with 10 person-days required
- T7 depends on T1 and has a duration of 20 days with 25 person-days required
- T8 depends on T4 and has a duration of 25 days with 75 person-days required
- T9 depends on T3 and T6 and has a duration of 15 days with 10 person-days required
- T10 depends on T7 and T8 and has a duration of 15 days with 20 person-days required
- T11 depends on T9 and has a duration of 10 days with 10 person-days required
- T12 depends on T10 and T11 and has a duration of 10 days with 20 person-days required
Activity Bar Chart
- The activity bar chart shows the start and finish times for each task
- Tasks T1 and T2 start immediately
- Tasks T3 and T7 depend on T1 starting at week 1
- Task T8 depends on T4 starting at week 3
- Tasks T5 and T6 have multiple dependencies
- The project finishes in week 11
Staff Allocation Chart
- Jane is assigned to tasks T1, T3, T9, T10, and T12
- Ali is assigned to tasks T1 and T8
- Geetha is assigned to tasks T2, T6, T7, and T3
- Maya is assigned to task T8
- Fred is assigned to tasks T4, T8, T11, and T12
- Mary is assigned task T 5
- Hong is assigned to tasks T7 and T6
Estimation Techniques
- Organizations need to make estimates for software effort and costs
- Experience-based techniques rely on the manager's expertise from previous projects
- Algorithmic cost modeling utilizes formulas to calculate project effort based on product attributes and process characteristics
Estimate Uncertainty
- Estimates can vary significantly throughout the project's life cycle
- There is typically high uncertainty in the feasibility and requirement phases
- The code and delivery phases have lower uncertainty
Risk Management
- Risk management is concerned with recognizing risks and planning to minimize their impact
- Software risk management is important because of inherent uncertainty in software development
- Risks can arise from loosely defined requirements, changing customer needs, difficulties in estimating resources and time, and differing skill levels
- Risks must be anticipated, their impact understood, and steps taken to avoid them
Risk Classification
- Risks are classified based on their type (technical, organizational, etc.) and what they affect
- Project risks affect the schedule or resources
- Product risks affect the quality or performance of the software
- Business risks affect the organization developing or procuring the software
Risk Examples
- Staff turnover is a risk affecting the project
- Management change is a risk affecting the project
- Hardware unavailability is a risk affecting the project
- Requirements change is a risk affecting the project and the product
Development Planning
- The project plan should be regularly adjusted as the project progresses
- The schedule, cost estimate, and identified risks must be revised regularly
- The process involves identifying constraints, risks, and milestones
The Project Planning Process
- The process includes identifying constraints and risks, defining the project schedule, defining milestones and deliverables, monitoring progress, and taking action to mitigate risk
Project Scheduling
- Project scheduling is about organizing the work into tasks and planning their execution
- Tasks are assigned effort and time estimates
- Resources required for each task are determined
Project Scheduling Activities
- Splitting the project into tasks and estimating time and resources
- Organizing tasks concurrently to optimize workforce utilization
- Minimizing task dependencies to prevent delays caused by waiting for other tasks to complete
- This process relies on the project manager's intuition and experience
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz focuses on understanding the concepts of tasks, durations, and dependencies in project management. It includes various scenarios involving task dependencies and the associated person-days required for completion. Test your knowledge on how to manage and analyze project timelines effectively.