Project Management Tasks and Dependencies
24 Questions
3 Views

Project Management Tasks and Dependencies

Created by
@FoolproofBinary7030

Podcast Beta

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which task has the highest effort requirement?

  • T6
  • T8 (correct)
  • T7
  • T3
  • Which tasks are dependent on T2?

  • T4 and T5
  • T5 and T6 (correct)
  • T6 and T3
  • T3 and T9
  • What is the total duration for T10?

  • 20 days
  • 15 days (correct)
  • 10 days
  • 25 days
  • Which task is completed last based on the task schedule?

    <p>T12</p> Signup and view all the answers

    Which staff member is not allocated to any tasks during Week 0?

    <p>Mary</p> Signup and view all the answers

    How many tasks depend on T4?

    <p>Two</p> Signup and view all the answers

    Which estimation technique is most crucial for organizations managing software projects?

    <p>Effort estimation</p> Signup and view all the answers

    What is the dependency for task T9?

    <p>T3 and T6</p> Signup and view all the answers

    What is the primary focus of risk management in software development?

    <p>Minimizing the effect of risks on a project</p> Signup and view all the answers

    Which of the following factors contributes to uncertainties in software development?

    <p>Loosely defined requirements</p> Signup and view all the answers

    What is an example of a business risk in software development?

    <p>Management change</p> Signup and view all the answers

    In the context of cost estimation, which technique relies on the manager's judgment and past experiences?

    <p>Experience-based techniques</p> Signup and view all the answers

    Which of the following is a type of risk that specifically affects the quality or performance of the developed software?

    <p>Product risk</p> Signup and view all the answers

    What does project risk primarily affect?

    <p>The timeline and resources of the project</p> Signup and view all the answers

    What is a common example of a project risk related to staffing?

    <p>Staff turnover</p> Signup and view all the answers

    Which approach uses a formulaic method to estimate project effort based on product attributes?

    <p>Algorithmic cost modeling</p> Signup and view all the answers

    What should be done with the project plan as development progresses?

    <p>It should be regularly amended.</p> Signup and view all the answers

    Which aspect is NOT essential in project scheduling?

    <p>Organizing tasks into a rigid sequence.</p> Signup and view all the answers

    What is a recommended action to minimize delays in task execution?

    <p>Organizing tasks concurrently.</p> Signup and view all the answers

    Which of the following is a key component of risk management in project planning?

    <p>Initiating risk mitigation actions.</p> Signup and view all the answers

    In the context of project scheduling, what should be estimated for each task?

    <p>The time and resources needed.</p> Signup and view all the answers

    What is one primary purpose of regularly revising project estimates?

    <p>To adjust to changes in software development.</p> Signup and view all the answers

    Which of the following describes the first step in the project planning process?

    <p>Identifying constraints.</p> Signup and view all the answers

    Which statement is true regarding task scheduling techniques?

    <p>Concurrent organization of tasks is recommended.</p> Signup and view all the answers

    Study Notes

    Tasks, Durations, and Dependencies

    • Tasks have effort (person-days) and duration (days)
    • Dependencies are represented with (M#) where M1-M8 are specific dependencies
    • T1 has a duration of 10 days with 15 person-days required
    • T2 has a duration of 15 days with 8 person-days required
    • T3 depends on T1 and has a duration of 15 days with 20 person-days required
    • T5 depends on T2 and T4 and has a duration of 10 days with 5 person-days required
    • T6 depends on T1 and T2 and has a duration of 5 days with 10 person-days required
    • T7 depends on T1 and has a duration of 20 days with 25 person-days required
    • T8 depends on T4 and has a duration of 25 days with 75 person-days required
    • T9 depends on T3 and T6 and has a duration of 15 days with 10 person-days required
    • T10 depends on T7 and T8 and has a duration of 15 days with 20 person-days required
    • T11 depends on T9 and has a duration of 10 days with 10 person-days required
    • T12 depends on T10 and T11 and has a duration of 10 days with 20 person-days required

    Activity Bar Chart

    • The activity bar chart shows the start and finish times for each task
    • Tasks T1 and T2 start immediately
    • Tasks T3 and T7 depend on T1 starting at week 1
    • Task T8 depends on T4 starting at week 3
    • Tasks T5 and T6 have multiple dependencies
    • The project finishes in week 11

    Staff Allocation Chart

    • Jane is assigned to tasks T1, T3, T9, T10, and T12
    • Ali is assigned to tasks T1 and T8
    • Geetha is assigned to tasks T2, T6, T7, and T3
    • Maya is assigned to task T8
    • Fred is assigned to tasks T4, T8, T11, and T12
    • Mary is assigned task T 5
    • Hong is assigned to tasks T7 and T6

    Estimation Techniques

    • Organizations need to make estimates for software effort and costs
    • Experience-based techniques rely on the manager's expertise from previous projects
    • Algorithmic cost modeling utilizes formulas to calculate project effort based on product attributes and process characteristics

    Estimate Uncertainty

    • Estimates can vary significantly throughout the project's life cycle
    • There is typically high uncertainty in the feasibility and requirement phases
    • The code and delivery phases have lower uncertainty

    Risk Management

    • Risk management is concerned with recognizing risks and planning to minimize their impact
    • Software risk management is important because of inherent uncertainty in software development
    • Risks can arise from loosely defined requirements, changing customer needs, difficulties in estimating resources and time, and differing skill levels
    • Risks must be anticipated, their impact understood, and steps taken to avoid them

    Risk Classification

    • Risks are classified based on their type (technical, organizational, etc.) and what they affect
    • Project risks affect the schedule or resources
    • Product risks affect the quality or performance of the software
    • Business risks affect the organization developing or procuring the software

    Risk Examples

    • Staff turnover is a risk affecting the project
    • Management change is a risk affecting the project
    • Hardware unavailability is a risk affecting the project
    • Requirements change is a risk affecting the project and the product

    Development Planning

    • The project plan should be regularly adjusted as the project progresses
    • The schedule, cost estimate, and identified risks must be revised regularly
    • The process involves identifying constraints, risks, and milestones

    The Project Planning Process

    • The process includes identifying constraints and risks, defining the project schedule, defining milestones and deliverables, monitoring progress, and taking action to mitigate risk

    Project Scheduling

    • Project scheduling is about organizing the work into tasks and planning their execution
    • Tasks are assigned effort and time estimates
    • Resources required for each task are determined

    Project Scheduling Activities

    • Splitting the project into tasks and estimating time and resources
    • Organizing tasks concurrently to optimize workforce utilization
    • Minimizing task dependencies to prevent delays caused by waiting for other tasks to complete
    • This process relies on the project manager's intuition and experience

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    03-Project management.pdf

    Description

    This quiz focuses on understanding the concepts of tasks, durations, and dependencies in project management. It includes various scenarios involving task dependencies and the associated person-days required for completion. Test your knowledge on how to manage and analyze project timelines effectively.

    More Like This

    Use Quizgecko on...
    Browser
    Browser