Podcast
Questions and Answers
A project manager discovers that a critical path activity requires specialized equipment that is unavailable for two weeks. The delay threatens the project deadline. What should the project manager do?
A project manager discovers that a critical path activity requires specialized equipment that is unavailable for two weeks. The delay threatens the project deadline. What should the project manager do?
- Evaluate crashing options by renting similar equipment to maintain the schedule. (correct)
- Replace the activity with a less critical task to stay on track.
- Extend the project timeline to accommodate the delay.
- Adjust task dependencies to start other activities earlier.
A stakeholder requests the addition of several tasks to the project schedule. These tasks are not part of the approved scope. How should the project manager address this?
A stakeholder requests the addition of several tasks to the project schedule. These tasks are not part of the approved scope. How should the project manager address this?
- Reject the request to avoid scope creep.
- Include the tasks immediately to satisfy the stakeholder.
- Evaluate the request through the change control process and update the schedule if approved. (correct)
- Add the tasks informally and manage the additional work within the team.
While creating the project schedule, the team realizes a key resource is overallocated during the testing phase. What is the best approach to resolve this?
While creating the project schedule, the team realizes a key resource is overallocated during the testing phase. What is the best approach to resolve this?
- Delay the testing phase to avoid overloading the resource.
- Reassign tasks to other team members regardless of expertise.
- Apply fast tracking to overlap the testing phase with other activities.
- Use resource leveling to redistribute workloads without exceeding resource capacity. (correct)
A construction project includes a task that is weather-dependent. The project manager needs to account for potential weather delays in the schedule. What is the best way to handle this?
A construction project includes a task that is weather-dependent. The project manager needs to account for potential weather delays in the schedule. What is the best way to handle this?
A project team uses rolling wave planning for a long-term project. What should the project manager prioritize when creating the schedule?
A project team uses rolling wave planning for a long-term project. What should the project manager prioritize when creating the schedule?
During a schedule review, a sponsor suggests removing float from non-critical tasks to shorten the timeline. What should the project manager do?
During a schedule review, a sponsor suggests removing float from non-critical tasks to shorten the timeline. What should the project manager do?
The project sponsor requests that the schedule include early warning indicators for potential delays. What tool or technique should the project manager use?
The project sponsor requests that the schedule include early warning indicators for potential delays. What tool or technique should the project manager use?
The project team is using fast tracking to shorten the project schedule. However, this approach is increasing risks. How should the project manager address this?
The project team is using fast tracking to shorten the project schedule. However, this approach is increasing risks. How should the project manager address this?
A team is sequencing activities for a manufacturing project. They identify that one activity cannot begin until two preceding activities are complete. What dependency relationship should they use?
A team is sequencing activities for a manufacturing project. They identify that one activity cannot begin until two preceding activities are complete. What dependency relationship should they use?
During schedule compression, the project manager identifies a critical task that can be divided into smaller, parallel activities. What is the best approach?
During schedule compression, the project manager identifies a critical task that can be divided into smaller, parallel activities. What is the best approach?
The project schedule relies heavily on vendor deliverables, but the vendor has a history of delays. How should the project manager mitigate this risk?
The project schedule relies heavily on vendor deliverables, but the vendor has a history of delays. How should the project manager mitigate this risk?
A project manager notices that tasks on the critical path are frequently being delayed. What should they do to protect the project timeline?
A project manager notices that tasks on the critical path are frequently being delayed. What should they do to protect the project timeline?
A project team uses a Kanban board to manage schedules for a software project. A bottleneck appears in the testing column. What is the best course of action?
A project team uses a Kanban board to manage schedules for a software project. A bottleneck appears in the testing column. What is the best course of action?
A project must meet a fixed deadline, but resource constraints are causing delays. How should the project manager respond?
A project must meet a fixed deadline, but resource constraints are causing delays. How should the project manager respond?
The project manager is developing a schedule for a phased rollout of a new product. The sponsor requests a detailed timeline for all phases upfront. What is the best approach?
The project manager is developing a schedule for a phased rollout of a new product. The sponsor requests a detailed timeline for all phases upfront. What is the best approach?
A project team is creating a schedule for a product launch. The marketing department requests that a campaign begins before the product is fully ready. What is the best way to incorporate this into the schedule?
A project team is creating a schedule for a product launch. The marketing department requests that a campaign begins before the product is fully ready. What is the best way to incorporate this into the schedule?
While creating the project schedule, a team identifies a high degree of uncertainty in future tasks. What is the best way to handle this?
While creating the project schedule, a team identifies a high degree of uncertainty in future tasks. What is the best way to handle this?
A project schedule includes tasks with varying levels of priority. A stakeholder requests additional tasks that might delay high-priority ones. How should the project manager address this?
A project schedule includes tasks with varying levels of priority. A stakeholder requests additional tasks that might delay high-priority ones. How should the project manager address this?
A resource's availability changes midway through the project, causing a delay in a critical path task. What is the best course of action for the project manager?
A resource's availability changes midway through the project, causing a delay in a critical path task. What is the best course of action for the project manager?
The project team is using Monte Carlo simulations to analyze schedule risks. The results show a high likelihood of delays. What should the project manager prioritize?
The project team is using Monte Carlo simulations to analyze schedule risks. The results show a high likelihood of delays. What should the project manager prioritize?
A sponsor asks the project manager to compress the schedule by two weeks without changing the scope. What is the best way to achieve this?
A sponsor asks the project manager to compress the schedule by two weeks without changing the scope. What is the best way to achieve this?
A stakeholder questions why the project schedule includes lag time between two key activities. How should the project manager address this?
A stakeholder questions why the project schedule includes lag time between two key activities. How should the project manager address this?
A project involves several interdependent tasks, and the team identifies a task that can only start once another task reaches 75% completion. How should the project manager model this?
A project involves several interdependent tasks, and the team identifies a task that can only start once another task reaches 75% completion. How should the project manager model this?
The project schedule includes a task with high resource demand that conflicts with another critical task. What is the best way to resolve this?
The project schedule includes a task with high resource demand that conflicts with another critical task. What is the best way to resolve this?
A team identifies float in several non-critical tasks. How can the project manager use this float to benefit the project?
A team identifies float in several non-critical tasks. How can the project manager use this float to benefit the project?
A project team is creating a schedule for a phased product rollout. The sponsor insists on detailed timelines for all phases upfront. How should the project manager respond?
A project team is creating a schedule for a phased product rollout. The sponsor insists on detailed timelines for all phases upfront. How should the project manager respond?
A project manager identifies a high-risk task on the critical path. The team is concerned about the potential impact of delays. What should the project manager do?
A project manager identifies a high-risk task on the critical path. The team is concerned about the potential impact of delays. What should the project manager do?
A sponsor requests that the project schedule include checkpoints to ensure adherence to the timeline. What is the best way to implement this?
A sponsor requests that the project schedule include checkpoints to ensure adherence to the timeline. What is the best way to implement this?
A sponsor wants to see a visual representation of the project schedule that highlights task durations, dependencies, and milestones. What should the project manager provide?
A sponsor wants to see a visual representation of the project schedule that highlights task durations, dependencies, and milestones. What should the project manager provide?
The team realizes a task on the critical path has been underestimated by 20%. How should the project manager address this?
The team realizes a task on the critical path has been underestimated by 20%. How should the project manager address this?
A project manager is creating a schedule for a team using Agile practices. The team prefers flexible deadlines, but the sponsor demands fixed milestone dates. How should the project manager balance these needs?
A project manager is creating a schedule for a team using Agile practices. The team prefers flexible deadlines, but the sponsor demands fixed milestone dates. How should the project manager balance these needs?
A project team is working on a hybrid project with both predictive and adaptive elements. The predictive phase tasks are slipping due to dependencies on adaptive-phase deliverables that are not yet finalized. How should the project manager resolve this?
A project team is working on a hybrid project with both predictive and adaptive elements. The predictive phase tasks are slipping due to dependencies on adaptive-phase deliverables that are not yet finalized. How should the project manager resolve this?
The project's critical path contains tasks with varying risk levels. One high-risk task is forecasted to exceed its duration estimate by 40%. How should the project manager handle this?
The project's critical path contains tasks with varying risk levels. One high-risk task is forecasted to exceed its duration estimate by 40%. How should the project manager handle this?
A construction project schedule requires aligning multiple subcontractors' activities. One subcontractor consistently underperforms, creating cascading delays. What should the project manager prioritize?
A construction project schedule requires aligning multiple subcontractors' activities. One subcontractor consistently underperforms, creating cascading delays. What should the project manager prioritize?
A key stakeholder demands that their department's deliverables be prioritized, potentially delaying work critical to another stakeholder. How should the project manager resolve this conflict?
A key stakeholder demands that their department's deliverables be prioritized, potentially delaying work critical to another stakeholder. How should the project manager resolve this conflict?
A government project involves mandatory regulatory reviews at specific milestones. One regulatory body has announced a two-week delay in their review process. What is the best way to mitigate the impact?
A government project involves mandatory regulatory reviews at specific milestones. One regulatory body has announced a two-week delay in their review process. What is the best way to mitigate the impact?
A sponsor asks the project manager to add more tasks to the critical path to highlight their importance. This risks inflating the timeline unnecessarily. What should the project manager do?
A sponsor asks the project manager to add more tasks to the critical path to highlight their importance. This risks inflating the timeline unnecessarily. What should the project manager do?
During schedule creation, the project manager notices overlapping holidays across different regions where the project team operates. Some tasks require collaboration across all regions. How should the project manager handle this?
During schedule creation, the project manager notices overlapping holidays across different regions where the project team operates. Some tasks require collaboration across all regions. How should the project manager handle this?
A project manager needs to fast-track a project, but the tasks with the most opportunity for overlap introduce significant quality risks. What is the best approach?
A project manager needs to fast-track a project, but the tasks with the most opportunity for overlap introduce significant quality risks. What is the best approach?
The project team is managing a program with interdependent projects. A delay in one project's critical path affects deliverables for another project. What should the project manager prioritize?
The project team is managing a program with interdependent projects. A delay in one project's critical path affects deliverables for another project. What should the project manager prioritize?
A project team is developing a schedule for a highly innovative product with significant unknowns. Stakeholders demand a detailed, fully predictive schedule. What should the project manager do?
A project team is developing a schedule for a highly innovative product with significant unknowns. Stakeholders demand a detailed, fully predictive schedule. What should the project manager do?
A vendor-managed task on the critical path has high variability in its completion estimates. The vendor provides a wide range of optimistic, most likely, and pessimistic durations. What is the best course of action?
A vendor-managed task on the critical path has high variability in its completion estimates. The vendor provides a wide range of optimistic, most likely, and pessimistic durations. What is the best course of action?
The project team is trying to compress the schedule using crashing, but the costs are exceeding the project's budget. How should the project manager respond?
The project team is trying to compress the schedule using crashing, but the costs are exceeding the project's budget. How should the project manager respond?
A resource on a critical task has been reassigned to a higher-priority project by upper management. The reassignment delays the task and risks missing the deadline. What should the project manager prioritize?
A resource on a critical task has been reassigned to a higher-priority project by upper management. The reassignment delays the task and risks missing the deadline. What should the project manager prioritize?
A team's schedule includes tasks that must comply with external approval processes. Approvals are frequently delayed without warning. What is the best strategy?
A team's schedule includes tasks that must comply with external approval processes. Approvals are frequently delayed without warning. What is the best strategy?
A project manager is reviewing the schedule baseline and notices that non-critical tasks have unusually long durations. Stakeholders insist these durations remain unchanged. What should the project manager do?
A project manager is reviewing the schedule baseline and notices that non-critical tasks have unusually long durations. Stakeholders insist these durations remain unchanged. What should the project manager do?
Flashcards
What should a project manager do when facing a delay in a critical path activity due to unavailable equipment?
What should a project manager do when facing a delay in a critical path activity due to unavailable equipment?
When a critical path activity faces a delay due to unavailable equipment, the project manager should explore options like renting similar equipment to maintain the schedule.
How should a project manager handle a stakeholder request for tasks outside the approved scope?
How should a project manager handle a stakeholder request for tasks outside the approved scope?
When a stakeholder requests additional tasks outside of the approved project scope, the project manager should evaluate this request through the change control process and update the schedule if approved.
How to resolve resource overallocation during a project phase.
How to resolve resource overallocation during a project phase.
When a resource is overallocated during a specific project phase (like testing), the project manager should use resource leveling to redistribute workloads without exceeding resource capacity.
How to account for potential weather delays in a project schedule.
How to account for potential weather delays in a project schedule.
Signup and view all the flashcards
What is the key focus in scheduling for a project using rolling wave planning?
What is the key focus in scheduling for a project using rolling wave planning?
Signup and view all the flashcards
How should a project manager respond to a sponsor's request to remove float from non-critical tasks?
How should a project manager respond to a sponsor's request to remove float from non-critical tasks?
Signup and view all the flashcards
Which tool helps integrate early warning indicators for potential delays into the schedule?
Which tool helps integrate early warning indicators for potential delays into the schedule?
Signup and view all the flashcards
How should a project manager address increased risks while using Fast-Tracking?
How should a project manager address increased risks while using Fast-Tracking?
Signup and view all the flashcards
What dependency relationship should be used for an activity that requires two preceding activities to be finished?
What dependency relationship should be used for an activity that requires two preceding activities to be finished?
Signup and view all the flashcards
How to compress a schedule when a critical task can be divided into smaller, parallel activities?
How to compress a schedule when a critical task can be divided into smaller, parallel activities?
Signup and view all the flashcards
How to mitigate the risk of vendor delays in a project?
How to mitigate the risk of vendor delays in a project?
Signup and view all the flashcards
What should a project manager do when critical path tasks are frequently facing delays?
What should a project manager do when critical path tasks are frequently facing delays?
Signup and view all the flashcards
How to resolve a bottleneck appearing in the testing column of a Kanban board?
How to resolve a bottleneck appearing in the testing column of a Kanban board?
Signup and view all the flashcards
How to address resource constraints causing delays when a project has a fixed deadline?
How to address resource constraints causing delays when a project has a fixed deadline?
Signup and view all the flashcards
How to handle a sponsor's request for detailed schedules for all phases of a phased product rollout?
How to handle a sponsor's request for detailed schedules for all phases of a phased product rollout?
Signup and view all the flashcards
How to incorporate a marketing campaign that starts before the product is fully ready in a project schedule?
How to incorporate a marketing campaign that starts before the product is fully ready in a project schedule?
Signup and view all the flashcards
How to handle a high degree of uncertainty in future tasks during project scheduling?
How to handle a high degree of uncertainty in future tasks during project scheduling?
Signup and view all the flashcards
How to handle a stakeholder request for additional tasks that might delay high-priority ones in a project schedule?
How to handle a stakeholder request for additional tasks that might delay high-priority ones in a project schedule?
Signup and view all the flashcards
How to address a change in a key resource's availability that impacts a critical path task?
How to address a change in a key resource's availability that impacts a critical path task?
Signup and view all the flashcards
What actions should a project manager prioritize when Monte Carlo simulations indicate a high likelihood of delays?
What actions should a project manager prioritize when Monte Carlo simulations indicate a high likelihood of delays?
Signup and view all the flashcards
How to compress a project schedule by two weeks without altering the project scope?
How to compress a project schedule by two weeks without altering the project scope?
Signup and view all the flashcards
How to explain the presence of lag time between two key activities in a project schedule?
How to explain the presence of lag time between two key activities in a project schedule?
Signup and view all the flashcards
How to model a task that can only start after another task reaches 75% completion?
How to model a task that can only start after another task reaches 75% completion?
Signup and view all the flashcards
How to address resource conflicts between critical tasks in a project schedule?
How to address resource conflicts between critical tasks in a project schedule?
Signup and view all the flashcards
How to utilize float in non-critical tasks to benefit the project?
How to utilize float in non-critical tasks to benefit the project?
Signup and view all the flashcards
How to respond to a sponsor's demand for detailed timelines for all phases of a phased product rollout?
How to respond to a sponsor's demand for detailed timelines for all phases of a phased product rollout?
Signup and view all the flashcards
What should a project manager prioritize when a high-risk task appears in the critical path?
What should a project manager prioritize when a high-risk task appears in the critical path?
Signup and view all the flashcards
How to incorporate checkpoints into the project schedule to ensure adherence to the timeline?
How to incorporate checkpoints into the project schedule to ensure adherence to the timeline?
Signup and view all the flashcards
What visual tool should a project manager provide to show task durations, dependencies, and milestones in a project?
What visual tool should a project manager provide to show task durations, dependencies, and milestones in a project?
Signup and view all the flashcards
How to address an underestimated task on the critical path during project scheduling?
How to address an underestimated task on the critical path during project scheduling?
Signup and view all the flashcards
How to balance a team's preference for flexible deadlines with a sponsor's demand for fixed milestone dates in an Agile project?
How to balance a team's preference for flexible deadlines with a sponsor's demand for fixed milestone dates in an Agile project?
Signup and view all the flashcards
How to address delays in predictive phase tasks caused by dependencies on unfinalized adaptive phase deliverables in a hybrid project?
How to address delays in predictive phase tasks caused by dependencies on unfinalized adaptive phase deliverables in a hybrid project?
Signup and view all the flashcards
How to analyze the potential impact of a high-risk task with a 40% delay in its duration estimate on the overall critical path schedule?
How to analyze the potential impact of a high-risk task with a 40% delay in its duration estimate on the overall critical path schedule?
Signup and view all the flashcards
How to address an underperforming subcontractor's impact on a construction project schedule?
How to address an underperforming subcontractor's impact on a construction project schedule?
Signup and view all the flashcards
How to handle a stakeholder's demand for prioritizing their department's deliverables at the expense of another stakeholder's critical tasks?
How to handle a stakeholder's demand for prioritizing their department's deliverables at the expense of another stakeholder's critical tasks?
Signup and view all the flashcards
How to mitigate the impact of a delay in a mandatory regulatory review on a government project's schedule?
How to mitigate the impact of a delay in a mandatory regulatory review on a government project's schedule?
Signup and view all the flashcards
How to handle a sponsor's request to add more tasks to the critical path, which risks inflating the timeline?
How to handle a sponsor's request to add more tasks to the critical path, which risks inflating the timeline?
Signup and view all the flashcards
How to handle overlapping holidays across different regions when planning a schedule for a team operating globally?
How to handle overlapping holidays across different regions when planning a schedule for a team operating globally?
Signup and view all the flashcards
How to approach fast-tracking when tasks with significant quality risks are involved?
How to approach fast-tracking when tasks with significant quality risks are involved?
Signup and view all the flashcards
How to address a delay in one project's critical path that impacts deliverables for another project in a program?
How to address a delay in one project's critical path that impacts deliverables for another project in a program?
Signup and view all the flashcards
How to handle a stakeholder's demand for a fully predictive schedule for a highly innovative product with significant unknowns?
How to handle a stakeholder's demand for a fully predictive schedule for a highly innovative product with significant unknowns?
Signup and view all the flashcards
How to address high variability in a vendor-managed task's completion estimates on the critical path?
How to address high variability in a vendor-managed task's completion estimates on the critical path?
Signup and view all the flashcards
When crashing a schedule exceeds budget, how should the project manager respond?
When crashing a schedule exceeds budget, how should the project manager respond?
Signup and view all the flashcards
How to address a critical task resource being reassigned to a higher-priority project?
How to address a critical task resource being reassigned to a higher-priority project?
Signup and view all the flashcards
What is the best strategy to handle frequent delays in external approval processes that affect project tasks?
What is the best strategy to handle frequent delays in external approval processes that affect project tasks?
Signup and view all the flashcards
How to handle unusually long durations for non-critical tasks in a project schedule?
How to handle unusually long durations for non-critical tasks in a project schedule?
Signup and view all the flashcards
Study Notes
Project Management - Critical Path and Schedule Management
- Critical Path Activity Delay: A project manager should evaluate crashing options (renting similar equipment) to maintain the schedule, rather than extending the timeline, adjusting task dependencies, or replacing a critical task.
- Stakeholder Task Addition: Project managers should evaluate and approve stakeholder requests through the change control process before adding the tasks to the schedule. This prevents scope creep.
- Resource Overallocation: To resolve resource overallocation during testing, use resource leveling to redistribute workloads and avoid exceeding resource capacity.
- Weather-Dependent Task: Account for potential weather delays in construction by adding contingency buffers to the task duration in the schedule.
- Rolling Wave Planning: For long-term projects, prioritize detailed schedules for near-term tasks, and high-level plans for future phases, rather than finalizing the entire schedule upfront. Use rolling wave planning for updates.
- Removing Float From Non-Critical Tasks: Explain the purpose of float in maintaining schedule flexibility, and negotiate adjustments rather than blindly removing all float immediately, or shifting it to the critical path instead.
- Early Warning Indicators (Potential Delays): Use Earned Value Management (EVM) to track schedule performance, add milestones (checkpoints) and include Monte Carlo simulations to predict schedule risks. Adding slack to all tasks for prevention is not the best option.
- Fast Tracking Risks: Monitor risks actively while fast-tracking. Abandoning fast-tracking is not ideal when mitigating risks. Consider leveling resources to reduce risk. Focus on critical path tasks and leave non-critical ones aside.
- Activity Dependencies (Manufacturing): Use Finish-to-Start dependency when one activity cannot begin until two preceding activities are complete.
- Dividing Critical Tasks: Apply fast tracking to perform smaller, parallel activities simultaneously when a critical task can be divided.
- Vendor Delays: Add contingency buffers to tasks dependent on vendor deliverables, adjust the schedule to potentially start vendor-related tasks later. Consider replacing the vendor, but don't proceed with the current schedule and ignore delays.
- Delaying Critical Path Tasks: Focus on closely monitoring and controlling critical path tasks. Adding slack is a possible mitigation strategy to prevent future delays.
- Kanban Board Bottleneck: Reallocate resources to clear the testing phase bottleneck if appropriate rather than removing tasks, adjusting dependencies, or ignoring the bottleneck.
- Meeting Deadlines with Resource Constraints: Eliminate non-critical tasks to avoid exceeding timelines. Explore ways to balance workloads without increasing the timeline.
- Detailed Timeline for Phases: Provide high-level schedules for future phases and detailed schedules for the current phase to satisfy sponsors' requests.
- Product Launch Campaign Timing: Use fast tracking to overlap product readiness and campaign tasks, but delay the campaign if necessary, or separate the two schedules.
- Handling Schedule Uncertainty: Use rolling wave planning to detail near-term tasks while keeping future tasks at a high level and avoiding detailed task setup until more information is available.
- High-Priority Task Stakeholder Requests: Evaluate new tasks through a formal change control process. If needed, temporarily reject the new tasks to maintain high-priority tasks, or shift high-priority tasks to later in the schedule if necessary to accommodate the new request. Consider using schedule compression if acceptable.
- Delayed Task Resource Availability: Reassign the task to another resource with the necessary skills if a task is delayed. However, if extending the timeline is necessary, that could be considered to accommodate resource availability.
- Project Schedule Compression: Conduct a cost-benefit analysis to select tasks most deserving of schedule compression and prioritize those that maximize return on investment, while considering budget constraints.
- Resource Reassignment Concerns: Negotiate with upper management to reinstate the resource if possible rather than reassign the priority of the other task to the critical path.
- External Approval Delays: Integrate scheduling buffers to account for the delays of external approvals, or remove dependencies on external approvals where possible.
- Maintaining Non-Critical Task Durations: Recognize that the project's timeline should be adjusted to accommodate regional holidays and extend task durations as needed.
Project Management - Schedule and Resource Management
- Multi-Subcontractor Project Management: Engage subcontractor leadership to renegotiate performance expectations and rework dependencies to isolate the subcontractor's tasks.
- Stakeholder Conflicts: Hold a stakeholder alignment session to collaboratively reprioritize deliverables for mutual satisfaction, rather than prioritizing the stakeholder with the most authority.
- Regulatory Review Delays: Re-sequence downstream tasks that are not dependent on the review and consider adding a contingency reserve to absorbed future delays, rather than extending the project timeline or fast-tracking.
- Adding Tasks to Critical Path: Explain potential risks of inflating the timeline to stakeholders, and propose alternative prioritization strategies instead of adding them.
- Holiday Task Planning: Ensure the schedule accounts for regional holidays by adjusting the schedule and extending task durations for regional collaboration as needed.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.