FPM WEEK 6 - Scenario

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

A project manager discovers that a critical path activity requires specialized equipment that is unavailable for two weeks. The delay threatens the project deadline. What should the project manager do?

  • Evaluate crashing options by renting similar equipment to maintain the schedule. (correct)
  • Replace the activity with a less critical task to stay on track.
  • Extend the project timeline to accommodate the delay.
  • Adjust task dependencies to start other activities earlier.

A stakeholder requests the addition of several tasks to the project schedule. These tasks are not part of the approved scope. How should the project manager address this?

  • Reject the request to avoid scope creep.
  • Include the tasks immediately to satisfy the stakeholder.
  • Evaluate the request through the change control process and update the schedule if approved. (correct)
  • Add the tasks informally and manage the additional work within the team.

While creating the project schedule, the team realizes a key resource is overallocated during the testing phase. What is the best approach to resolve this?

  • Delay the testing phase to avoid overloading the resource.
  • Reassign tasks to other team members regardless of expertise.
  • Apply fast tracking to overlap the testing phase with other activities.
  • Use resource leveling to redistribute workloads without exceeding resource capacity. (correct)

A construction project includes a task that is weather-dependent. The project manager needs to account for potential weather delays in the schedule. What is the best way to handle this?

<p>Add a contingency buffer to the task duration to account for potential delays. (C)</p> Signup and view all the answers

A project team uses rolling wave planning for a long-term project. What should the project manager prioritize when creating the schedule?

<p>Develop detailed schedules for near-term tasks and high-level plans for future phases. (C)</p> Signup and view all the answers

During a schedule review, a sponsor suggests removing float from non-critical tasks to shorten the timeline. What should the project manager do?

<p>Explain the purpose of float in maintaining schedule flexibility and negotiate adjustments. (D)</p> Signup and view all the answers

The project sponsor requests that the schedule include early warning indicators for potential delays. What tool or technique should the project manager use?

<p>Implement Earned Value Management (EVM) to track schedule performance. (D)</p> Signup and view all the answers

The project team is using fast tracking to shorten the project schedule. However, this approach is increasing risks. How should the project manager address this?

<p>Monitor and mitigate risks actively while continuing fast tracking. (B)</p> Signup and view all the answers

A team is sequencing activities for a manufacturing project. They identify that one activity cannot begin until two preceding activities are complete. What dependency relationship should they use?

<p>Finish-to-Start for both preceding activities. (C)</p> Signup and view all the answers

During schedule compression, the project manager identifies a critical task that can be divided into smaller, parallel activities. What is the best approach?

<p>Apply fast tracking to perform the smaller activities simultaneously. (A)</p> Signup and view all the answers

The project schedule relies heavily on vendor deliverables, but the vendor has a history of delays. How should the project manager mitigate this risk?

<p>Add contingency buffers to tasks dependent on vendor deliverables. (A)</p> Signup and view all the answers

A project manager notices that tasks on the critical path are frequently being delayed. What should they do to protect the project timeline?

<p>Focus on monitoring and controlling critical path tasks closely. (D)</p> Signup and view all the answers

A project team uses a Kanban board to manage schedules for a software project. A bottleneck appears in the testing column. What is the best course of action?

<p>Reallocate resources to the testing phase to clear the bottleneck. (C)</p> Signup and view all the answers

A project must meet a fixed deadline, but resource constraints are causing delays. How should the project manager respond?

<p>Use resource smoothing to balance workloads without exceeding the deadline. (C)</p> Signup and view all the answers

The project manager is developing a schedule for a phased rollout of a new product. The sponsor requests a detailed timeline for all phases upfront. What is the best approach?

<p>Provide high-level schedules for future phases and detailed schedules for the current phase. (B)</p> Signup and view all the answers

A project team is creating a schedule for a product launch. The marketing department requests that a campaign begins before the product is fully ready. What is the best way to incorporate this into the schedule?

<p>Delay the marketing campaign until the product is fully ready. (A)</p> Signup and view all the answers

While creating the project schedule, a team identifies a high degree of uncertainty in future tasks. What is the best way to handle this?

<p>Use rolling wave planning to detail near-term tasks while keeping future tasks at a high level. (D)</p> Signup and view all the answers

A project schedule includes tasks with varying levels of priority. A stakeholder requests additional tasks that might delay high-priority ones. How should the project manager address this?

<p>Evaluate the new tasks through a formal change control process before adding them to the schedule. (D)</p> Signup and view all the answers

A resource's availability changes midway through the project, causing a delay in a critical path task. What is the best course of action for the project manager?

<p>Reassign the task to another resource with the necessary skills. (D)</p> Signup and view all the answers

The project team is using Monte Carlo simulations to analyze schedule risks. The results show a high likelihood of delays. What should the project manager prioritize?

<p>Develop mitigation strategies for high-risk activities and communicate findings to stakeholders. (C)</p> Signup and view all the answers

A sponsor asks the project manager to compress the schedule by two weeks without changing the scope. What is the best way to achieve this?

<p>Evaluate options for crashing or fast tracking critical path tasks. (B)</p> Signup and view all the answers

A stakeholder questions why the project schedule includes lag time between two key activities. How should the project manager address this?

<p>Explain that the lag is necessary to account for dependencies or external factors. (C)</p> Signup and view all the answers

A project involves several interdependent tasks, and the team identifies a task that can only start once another task reaches 75% completion. How should the project manager model this?

<p>Use a lead time to start the task once the predecessor is partially complete. (A)</p> Signup and view all the answers

The project schedule includes a task with high resource demand that conflicts with another critical task. What is the best way to resolve this?

<p>Apply resource leveling to balance the workload without changing the schedule significantly. (A)</p> Signup and view all the answers

A team identifies float in several non-critical tasks. How can the project manager use this float to benefit the project?

<p>Reallocate resources from non-critical tasks with float to critical tasks. (B)</p> Signup and view all the answers

A project team is creating a schedule for a phased product rollout. The sponsor insists on detailed timelines for all phases upfront. How should the project manager respond?

<p>Use high-level timelines for future phases and detailed schedules for the current phase, following rolling wave planning principles. (C)</p> Signup and view all the answers

A project manager identifies a high-risk task on the critical path. The team is concerned about the potential impact of delays. What should the project manager do?

<p>Develop contingency plans for the task and closely monitor its progress. (C)</p> Signup and view all the answers

A sponsor requests that the project schedule include checkpoints to ensure adherence to the timeline. What is the best way to implement this?

<p>Add milestones at key points in the schedule to act as progress checkpoints. (D)</p> Signup and view all the answers

A sponsor wants to see a visual representation of the project schedule that highlights task durations, dependencies, and milestones. What should the project manager provide?

<p>A Gantt chart that visually depicts the schedule and milestones. (C)</p> Signup and view all the answers

The team realizes a task on the critical path has been underestimated by 20%. How should the project manager address this?

<p>Reevaluate the task's duration and adjust the schedule baseline if needed. (D)</p> Signup and view all the answers

A project manager is creating a schedule for a team using Agile practices. The team prefers flexible deadlines, but the sponsor demands fixed milestone dates. How should the project manager balance these needs?

<p>Set fixed milestones while allowing flexibility within iterations. (D)</p> Signup and view all the answers

A project team is working on a hybrid project with both predictive and adaptive elements. The predictive phase tasks are slipping due to dependencies on adaptive-phase deliverables that are not yet finalized. How should the project manager resolve this?

<p>Introduce rolling wave planning to refine adaptive-phase deliverables in time for predictive dependencies. (C)</p> Signup and view all the answers

The project's critical path contains tasks with varying risk levels. One high-risk task is forecasted to exceed its duration estimate by 40%. How should the project manager handle this?

<p>Conduct a Monte Carlo simulation to determine the probability of meeting the overall schedule. (A)</p> Signup and view all the answers

A construction project schedule requires aligning multiple subcontractors' activities. One subcontractor consistently underperforms, creating cascading delays. What should the project manager prioritize?

<p>Engage the subcontractor's leadership to renegotiate performance expectations. (B)</p> Signup and view all the answers

A key stakeholder demands that their department's deliverables be prioritized, potentially delaying work critical to another stakeholder. How should the project manager resolve this conflict?

<p>Conduct a stakeholder alignment session to reprioritize deliverables collaboratively. (D)</p> Signup and view all the answers

A government project involves mandatory regulatory reviews at specific milestones. One regulatory body has announced a two-week delay in their review process. What is the best way to mitigate the impact?

<p>Re-sequence downstream tasks that are not dependent on the review. (D)</p> Signup and view all the answers

A sponsor asks the project manager to add more tasks to the critical path to highlight their importance. This risks inflating the timeline unnecessarily. What should the project manager do?

<p>Explain the impact of critical path inflation and suggest alternative prioritization strategies. (C)</p> Signup and view all the answers

During schedule creation, the project manager notices overlapping holidays across different regions where the project team operates. Some tasks require collaboration across all regions. How should the project manager handle this?

<p>Adjust the schedule to account for regional holidays and extend task durations. (D)</p> Signup and view all the answers

A project manager needs to fast-track a project, but the tasks with the most opportunity for overlap introduce significant quality risks. What is the best approach?

<p>Fast-track only low-risk tasks and accept a partially compressed timeline. (A)</p> Signup and view all the answers

The project team is managing a program with interdependent projects. A delay in one project's critical path affects deliverables for another project. What should the project manager prioritize?

<p>Implement program-level schedule integration and coordinate critical path adjustments. (A)</p> Signup and view all the answers

A project team is developing a schedule for a highly innovative product with significant unknowns. Stakeholders demand a detailed, fully predictive schedule. What should the project manager do?

<p>Propose a hybrid approach with rolling wave planning for uncertain areas. (B)</p> Signup and view all the answers

A vendor-managed task on the critical path has high variability in its completion estimates. The vendor provides a wide range of optimistic, most likely, and pessimistic durations. What is the best course of action?

<p>Use the three-point estimating method to calculate an expected duration for scheduling. (A)</p> Signup and view all the answers

The project team is trying to compress the schedule using crashing, but the costs are exceeding the project's budget. How should the project manager respond?

<p>Conduct a cost-benefit analysis to determine which tasks provide the highest ROI when crashed. (B)</p> Signup and view all the answers

A resource on a critical task has been reassigned to a higher-priority project by upper management. The reassignment delays the task and risks missing the deadline. What should the project manager prioritize?

<p>Request an equivalent replacement resource with similar expertise. (C)</p> Signup and view all the answers

A team's schedule includes tasks that must comply with external approval processes. Approvals are frequently delayed without warning. What is the best strategy?

<p>Incorporate buffers for all tasks requiring external approvals. (D)</p> Signup and view all the answers

A project manager is reviewing the schedule baseline and notices that non-critical tasks have unusually long durations. Stakeholders insist these durations remain unchanged. What should the project manager do?

<p>Use schedule compression techniques to ensure non-critical tasks do not impact the critical path. (A)</p> Signup and view all the answers

Flashcards

What should a project manager do when facing a delay in a critical path activity due to unavailable equipment?

When a critical path activity faces a delay due to unavailable equipment, the project manager should explore options like renting similar equipment to maintain the schedule.

How should a project manager handle a stakeholder request for tasks outside the approved scope?

When a stakeholder requests additional tasks outside of the approved project scope, the project manager should evaluate this request through the change control process and update the schedule if approved.

How to resolve resource overallocation during a project phase.

When a resource is overallocated during a specific project phase (like testing), the project manager should use resource leveling to redistribute workloads without exceeding resource capacity.

How to account for potential weather delays in a project schedule.

To account for potential weather delays in a schedule-dependent task, the project manager should add a contingency buffer to the task duration.

Signup and view all the flashcards

What is the key focus in scheduling for a project using rolling wave planning?

Rolling wave planning involves creating detailed plans for near-term tasks and high-level plans for future phases.

Signup and view all the flashcards

How should a project manager respond to a sponsor's request to remove float from non-critical tasks?

When a sponsor suggests removing float from non-critical tasks to shorten the timeline, the project manager should explain the purpose of float in maintaining schedule flexibility and negotiate adjustments.

Signup and view all the flashcards

Which tool helps integrate early warning indicators for potential delays into the schedule?

To include early warning indicators for potential delays in the project schedule, the project manager should implement Earned Value Management (EVM) to track schedule performance.

Signup and view all the flashcards

How should a project manager address increased risks while using Fast-Tracking?

When fast-tracking introduces risks, the project manager should actively monitor and mitigate risks while continuing the approach.

Signup and view all the flashcards

What dependency relationship should be used for an activity that requires two preceding activities to be finished?

When one activity cannot begin until two preceding activities are complete, a Finish-to-Start dependency relationship should be used for both preceding activities.

Signup and view all the flashcards

How to compress a schedule when a critical task can be divided into smaller, parallel activities?

To compress a schedule by dividing a critical task into smaller parallel activities, apply fast tracking to perform the smaller activities simultaneously.

Signup and view all the flashcards

How to mitigate the risk of vendor delays in a project?

To mitigate the risk of vendor delays, the project manager should add contingency buffers to tasks dependent on vendor deliverables.

Signup and view all the flashcards

What should a project manager do when critical path tasks are frequently facing delays?

When critical path tasks are frequently delayed, the project manager should focus on monitoring and controlling those tasks closely.

Signup and view all the flashcards

How to resolve a bottleneck appearing in the testing column of a Kanban board?

To clear a bottleneck in the testing column of a Kanban board, reallocate resources to the testing phase to clear the bottleneck.

Signup and view all the flashcards

How to address resource constraints causing delays when a project has a fixed deadline?

When a fixed project deadline is imposed with resource constraints causing delays, the project manager should use resource smoothing to balance workloads without exceeding the deadline.

Signup and view all the flashcards

How to handle a sponsor's request for detailed schedules for all phases of a phased product rollout?

When developing a schedule for a phased product rollout with a sponsor requesting a detailed timeline for all phases upfront, the project manager should provide high-level schedules for future phases and detailed schedules for the current phase, following rolling wave planning principles.

Signup and view all the flashcards

How to incorporate a marketing campaign that starts before the product is fully ready in a project schedule?

To incorporate a marketing campaign that begins before a product is fully ready, use fast tracking to overlap product readiness and campaign tasks.

Signup and view all the flashcards

How to handle a high degree of uncertainty in future tasks during project scheduling?

When a project team identifies a high degree of uncertainty in future tasks, the best approach is to use rolling wave planning, detailing near-term tasks while keeping future tasks at a high level.

Signup and view all the flashcards

How to handle a stakeholder request for additional tasks that might delay high-priority ones in a project schedule?

When a stakeholder requests additional tasks that might delay high-priority ones, the project manager should evaluate the new tasks through a formal change control process before adding them to the schedule.

Signup and view all the flashcards

How to address a change in a key resource's availability that impacts a critical path task?

When a resource's availability changes midway through a project, causing a delay in a critical path task, the project manager should reassign the task to another resource with necessary skills.

Signup and view all the flashcards

What actions should a project manager prioritize when Monte Carlo simulations indicate a high likelihood of delays?

When Monte Carlo simulations show a high likelihood of delays, the project manager should prioritize developing mitigation strategies for high-risk activities and communicating findings to stakeholders.

Signup and view all the flashcards

How to compress a project schedule by two weeks without altering the project scope?

To compress the schedule by two weeks without changing the scope, the project manager should evaluate options for crashing or fast tracking critical path tasks.

Signup and view all the flashcards

How to explain the presence of lag time between two key activities in a project schedule?

When a stakeholder questions lag time between two key activities, the project manager should explain that lag is necessary to account for dependencies or external factors.

Signup and view all the flashcards

How to model a task that can only start after another task reaches 75% completion?

When a task can only start once another reaches 75% completion, use a lead time to start the task once the predecessor is partially complete.

Signup and view all the flashcards

How to address resource conflicts between critical tasks in a project schedule?

To resolve conflicts with high resource demands between critical tasks, apply resource leveling to balance the workload without significantly changing the schedule.

Signup and view all the flashcards

How to utilize float in non-critical tasks to benefit the project?

The project manager can use float in non-critical tasks by reallocating resources from them to critical tasks, ultimately benefiting the project.

Signup and view all the flashcards

How to respond to a sponsor's demand for detailed timelines for all phases of a phased product rollout?

When a sponsor insists on detailed timelines for all phases of a phased product rollout, the project manager should use high-level timelines for future phases and detailed schedules for the current phase, following rolling wave planning principles.

Signup and view all the flashcards

What should a project manager prioritize when a high-risk task appears in the critical path?

When a high-risk task poses a threat to the schedule, the project manager should develop contingency plans and monitor its progress closely.

Signup and view all the flashcards

How to incorporate checkpoints into the project schedule to ensure adherence to the timeline?

To ensure adherence to the timeline, the project manager should add milestones at key points in the schedule to act as progress checkpoints.

Signup and view all the flashcards

What visual tool should a project manager provide to show task durations, dependencies, and milestones in a project?

To visually represent the project schedule, highlighting task durations, dependencies, and milestones, the project manager should provide a Gantt chart.

Signup and view all the flashcards

How to address an underestimated task on the critical path during project scheduling?

When a task on the critical path is underestimated by 20%, the project manager should reevaluate the task's duration and adjust the schedule baseline if needed.

Signup and view all the flashcards

How to balance a team's preference for flexible deadlines with a sponsor's demand for fixed milestone dates in an Agile project?

When a team uses Agile practices and prefers flexible deadlines, the project manager should balance those needs by setting fixed milestones while allowing flexibility within iterations.

Signup and view all the flashcards

How to address delays in predictive phase tasks caused by dependencies on unfinalized adaptive phase deliverables in a hybrid project?

When predictive phase tasks are slipping due to dependencies on adaptive-phase deliverables that are not yet finalized, the project manager should introduce rolling wave planning to refine adaptive-phase deliverables in time for those dependencies.

Signup and view all the flashcards

How to analyze the potential impact of a high-risk task with a 40% delay in its duration estimate on the overall critical path schedule?

When a high-risk task on the critical path is forecasted to exceed its duration estimate by 40%, the project manager should conduct a Monte Carlo simulation to determine the probability of meeting the overall schedule.

Signup and view all the flashcards

How to address an underperforming subcontractor's impact on a construction project schedule?

When a subcontractor consistently underperforms, causing cascading delays in a construction project, the project manager should engage the subcontractor's leadership to renegotiate performance expectations.

Signup and view all the flashcards

How to handle a stakeholder's demand for prioritizing their department's deliverables at the expense of another stakeholder's critical tasks?

When a key stakeholder demands prioritization of their department's deliverables, potentially delaying work critical to another stakeholder, the project manager should conduct a stakeholder alignment session to reprioritize deliverables collaboratively.

Signup and view all the flashcards

How to mitigate the impact of a delay in a mandatory regulatory review on a government project's schedule?

When a government project faces a two-week delay due to regulatory review, the project manager should re-sequence downstream tasks that are not dependent on the review.

Signup and view all the flashcards

How to handle a sponsor's request to add more tasks to the critical path, which risks inflating the timeline?

When a sponsor asks to add more tasks to the critical path, the project manager should explain the impact of critical path inflation and suggest alternative prioritization strategies.

Signup and view all the flashcards

How to handle overlapping holidays across different regions when planning a schedule for a team operating globally?

When planning a schedule for a team operating across regions with overlapping holidays, adjust the schedule to account for regional holidays and extend task durations where necessary.

Signup and view all the flashcards

How to approach fast-tracking when tasks with significant quality risks are involved?

When fast-tracking introduces significant quality risks, the project manager should prioritize fast-tracking only low-risk tasks and accept a partially compressed timeline.

Signup and view all the flashcards

How to address a delay in one project's critical path that impacts deliverables for another project in a program?

When a delay in one project's critical path affects deliverables for another project in a program, the project manager should implement program-level schedule integration and coordinate critical path adjustments.

Signup and view all the flashcards

How to handle a stakeholder's demand for a fully predictive schedule for a highly innovative product with significant unknowns?

When stakeholders demand a detailed, fully predictive schedule for a highly innovative product with significant unknowns, the project manager should propose a hybrid approach with rolling wave planning for uncertain areas.

Signup and view all the flashcards

How to address high variability in a vendor-managed task's completion estimates on the critical path?

When a vendor-managed task on the critical path has a high variability in its completion estimates, the project manager should use the three-point estimating method to calculate an expected duration for scheduling.

Signup and view all the flashcards

When crashing a schedule exceeds budget, how should the project manager respond?

When crashing costs exceed budget, the project manager should conduct a cost-benefit analysis to determine which tasks provide the highest ROI when crashed.

Signup and view all the flashcards

How to address a critical task resource being reassigned to a higher-priority project?

When a resource on a critical task is reassigned, the project manager should request an equivalent replacement resource with similar expertise.

Signup and view all the flashcards

What is the best strategy to handle frequent delays in external approval processes that affect project tasks?

To address frequent delays in approval processes, the project manager should incorporate buffers for all tasks requiring external approvals.

Signup and view all the flashcards

How to handle unusually long durations for non-critical tasks in a project schedule?

When non-critical tasks have unusually long durations, the project manager should use schedule compression techniques to ensure they do not impact the critical path.

Signup and view all the flashcards

Study Notes

Project Management - Critical Path and Schedule Management

  • Critical Path Activity Delay: A project manager should evaluate crashing options (renting similar equipment) to maintain the schedule, rather than extending the timeline, adjusting task dependencies, or replacing a critical task.
  • Stakeholder Task Addition: Project managers should evaluate and approve stakeholder requests through the change control process before adding the tasks to the schedule. This prevents scope creep.
  • Resource Overallocation: To resolve resource overallocation during testing, use resource leveling to redistribute workloads and avoid exceeding resource capacity.
  • Weather-Dependent Task: Account for potential weather delays in construction by adding contingency buffers to the task duration in the schedule.
  • Rolling Wave Planning: For long-term projects, prioritize detailed schedules for near-term tasks, and high-level plans for future phases, rather than finalizing the entire schedule upfront. Use rolling wave planning for updates.
  • Removing Float From Non-Critical Tasks: Explain the purpose of float in maintaining schedule flexibility, and negotiate adjustments rather than blindly removing all float immediately, or shifting it to the critical path instead.
  • Early Warning Indicators (Potential Delays): Use Earned Value Management (EVM) to track schedule performance, add milestones (checkpoints) and include Monte Carlo simulations to predict schedule risks. Adding slack to all tasks for prevention is not the best option.
  • Fast Tracking Risks: Monitor risks actively while fast-tracking. Abandoning fast-tracking is not ideal when mitigating risks. Consider leveling resources to reduce risk. Focus on critical path tasks and leave non-critical ones aside.
  • Activity Dependencies (Manufacturing): Use Finish-to-Start dependency when one activity cannot begin until two preceding activities are complete.
  • Dividing Critical Tasks: Apply fast tracking to perform smaller, parallel activities simultaneously when a critical task can be divided.
  • Vendor Delays: Add contingency buffers to tasks dependent on vendor deliverables, adjust the schedule to potentially start vendor-related tasks later. Consider replacing the vendor, but don't proceed with the current schedule and ignore delays.
  • Delaying Critical Path Tasks: Focus on closely monitoring and controlling critical path tasks. Adding slack is a possible mitigation strategy to prevent future delays.
  • Kanban Board Bottleneck: Reallocate resources to clear the testing phase bottleneck if appropriate rather than removing tasks, adjusting dependencies, or ignoring the bottleneck.
  • Meeting Deadlines with Resource Constraints: Eliminate non-critical tasks to avoid exceeding timelines. Explore ways to balance workloads without increasing the timeline.
  • Detailed Timeline for Phases: Provide high-level schedules for future phases and detailed schedules for the current phase to satisfy sponsors' requests.
  • Product Launch Campaign Timing: Use fast tracking to overlap product readiness and campaign tasks, but delay the campaign if necessary, or separate the two schedules.
  • Handling Schedule Uncertainty: Use rolling wave planning to detail near-term tasks while keeping future tasks at a high level and avoiding detailed task setup until more information is available.
  • High-Priority Task Stakeholder Requests: Evaluate new tasks through a formal change control process. If needed, temporarily reject the new tasks to maintain high-priority tasks, or shift high-priority tasks to later in the schedule if necessary to accommodate the new request. Consider using schedule compression if acceptable.
  • Delayed Task Resource Availability: Reassign the task to another resource with the necessary skills if a task is delayed. However, if extending the timeline is necessary, that could be considered to accommodate resource availability.
  • Project Schedule Compression: Conduct a cost-benefit analysis to select tasks most deserving of schedule compression and prioritize those that maximize return on investment, while considering budget constraints.
  • Resource Reassignment Concerns: Negotiate with upper management to reinstate the resource if possible rather than reassign the priority of the other task to the critical path.
  • External Approval Delays: Integrate scheduling buffers to account for the delays of external approvals, or remove dependencies on external approvals where possible.
  • Maintaining Non-Critical Task Durations: Recognize that the project's timeline should be adjusted to accommodate regional holidays and extend task durations as needed.

Project Management - Schedule and Resource Management

  • Multi-Subcontractor Project Management: Engage subcontractor leadership to renegotiate performance expectations and rework dependencies to isolate the subcontractor's tasks.
  • Stakeholder Conflicts: Hold a stakeholder alignment session to collaboratively reprioritize deliverables for mutual satisfaction, rather than prioritizing the stakeholder with the most authority.
  • Regulatory Review Delays: Re-sequence downstream tasks that are not dependent on the review and consider adding a contingency reserve to absorbed future delays, rather than extending the project timeline or fast-tracking.
  • Adding Tasks to Critical Path: Explain potential risks of inflating the timeline to stakeholders, and propose alternative prioritization strategies instead of adding them.
  • Holiday Task Planning: Ensure the schedule accounts for regional holidays by adjusting the schedule and extending task durations for regional collaboration as needed.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Module 6 - ChatGBT PDF

More Like This

Use Quizgecko on...
Browser
Browser