Summary

This document contains practice questions on project management topics, including schedule management, crashing, and fast tracking. The questions cover various scenarios and concepts related to project management.

Full Transcript

A project manager discovers that a critical path activity requires specialized equipment that is unavailable for two weeks. The delay threatens the project deadline. What should the project manager do?\ a. Evaluate crashing options by renting similar equipment to maintain the schedule.\ b. Extend th...

A project manager discovers that a critical path activity requires specialized equipment that is unavailable for two weeks. The delay threatens the project deadline. What should the project manager do?\ a. Evaluate crashing options by renting similar equipment to maintain the schedule.\ b. Extend the project timeline to accommodate the delay.\ c. Adjust task dependencies to start other activities earlier.\ d. Replace the activity with a less critical task to stay on track.\ Correct Answer: A A stakeholder requests the addition of several tasks to the project schedule. These tasks are not part of the approved scope. How should the project manager address this?\ a. Evaluate the request through the change control process and update the schedule if approved.\ b. Include the tasks immediately to satisfy the stakeholder.\ c. Reject the request to avoid scope creep.\ d. Add the tasks informally and manage the additional work within the team.\ Correct Answer: A While creating the project schedule, the team realizes a key resource is overallocated during the testing phase. What is the best approach to resolve this?\ a. Use resource leveling to redistribute workloads without exceeding resource capacity.\ b. Apply fast tracking to overlap the testing phase with other activities.\ c. Delay the testing phase to avoid overloading the resource.\ d. Reassign tasks to other team members regardless of expertise.\ Correct Answer: A A construction project includes a task that is weather-dependent. The project manager needs to account for potential weather delays in the schedule. What is the best way to handle this?\ a. Add a contingency buffer to the task duration to account for potential delays.\ b. Ignore the weather dependency and proceed with standard task scheduling.\ c. Schedule the task during the most favorable season without contingency.\ d. Use a Finish-to-Start dependency to allow flexibility in starting subsequent tasks.\ Correct Answer: A A project team uses rolling wave planning for a long-term project. What should the project manager prioritize when creating the schedule?\ a. Develop detailed schedules for near-term tasks and high-level plans for future phases.\ b. Finalize the entire schedule upfront to prevent delays.\ c. Avoid scheduling future tasks until the current phase is complete.\ d. Use predictive planning for all phases to ensure consistency.\ Correct Answer: A During a schedule review, a sponsor suggests removing float from non-critical tasks to shorten the timeline. What should the project manager do?\ a. Explain the purpose of float in maintaining schedule flexibility and negotiate adjustments.\ b. Remove all float from non-critical tasks as requested.\ c. Shift float to the critical path to reduce its duration.\ d. Ignore the suggestion and proceed with the original schedule.\ Correct Answer: A The project sponsor requests that the schedule include early warning indicators for potential delays. What tool or technique should the project manager use?\ a. Implement Earned Value Management (EVM) to track schedule performance.\ b. Add extra milestones to act as checkpoints for potential delays.\ c. Use Monte Carlo simulations to predict schedule risks.\ d. Add slack to all tasks to prevent delays.\ Correct Answer: A The project team is using fast tracking to shorten the project schedule. However, this approach is increasing risks. How should the project manager address this?\ a. Monitor and mitigate risks actively while continuing fast tracking.\ b. Abandon fast tracking and revert to the original schedule.\ c. Use resource leveling to minimize risk exposure.\ d. Focus only on critical path tasks and ignore non-critical tasks.\ Correct Answer: A A team is sequencing activities for a manufacturing project. They identify that one activity cannot begin until two preceding activities are complete. What dependency relationship should they use?\ a. Finish-to-Start for both preceding activities.\ b. Start-to-Start with lag for the preceding activities.\ c. Finish-to-Finish for all activities.\ d. Finish-to-Start with lag for the succeeding activity.\ Correct Answer: A During schedule compression, the project manager identifies a critical task that can be divided into smaller, parallel activities. What is the best approach?\ a. Apply fast tracking to perform the smaller activities simultaneously.\ b. Crash the task by assigning additional resources.\ c. Extend the duration of the task to ensure quality.\ d. Keep the task as a single activity to maintain simplicity.\ Correct Answer: A The project schedule relies heavily on vendor deliverables, but the vendor has a history of delays. How should the project manager mitigate this risk?\ a. Add contingency buffers to tasks dependent on vendor deliverables.\ b. Adjust the schedule to start vendor-related tasks later.\ c. Replace the vendor to avoid delays.\ d. Proceed with the current schedule and address delays as they occur.\ Correct Answer: A A project manager notices that tasks on the critical path are frequently being delayed. What should they do to protect the project timeline?\ a. Focus on monitoring and controlling critical path tasks closely.\ b. Add slack to the critical path tasks to prevent future delays.\ c. Shift resources from non-critical tasks to critical tasks permanently.\ d. Use predictive planning to restructure the schedule.\ Correct Answer: A A project team uses a Kanban board to manage schedules for a software project. A bottleneck appears in the testing column. What is the best course of action?\ a. Reallocate resources to the testing phase to clear the bottleneck.\ b. Remove testing tasks from the board until resources are available.\ c. Adjust dependencies to delay testing tasks.\ d. Ignore the bottleneck and continue with other phases.\ Correct Answer: A A project must meet a fixed deadline, but resource constraints are causing delays. How should the project manager respond?\ a. Use resource smoothing to balance workloads without exceeding the deadline.\ b. Eliminate non-critical tasks from the project scope.\ c. Extend the deadline to accommodate the constraints.\ d. Focus solely on completing critical path activities.\ Correct Answer: A The project manager is developing a schedule for a phased rollout of a new product. The sponsor requests a detailed timeline for all phases upfront. What is the best approach?\ a. Provide high-level schedules for future phases and detailed schedules for the current phase.\ b. Finalize detailed schedules for all phases to ensure alignment with the sponsor\'s request.\ c. Defer creating schedules for future phases until the current phase is complete.\ d. Use rolling wave planning to provide updates as each phase progresses.\ Correct Answer: A A project team is creating a schedule for a product launch. The marketing department requests that a campaign begins before the product is fully ready. What is the best way to incorporate this into the schedule?\ a. Use fast tracking to overlap product readiness and campaign tasks.\ b. Set a Start-to-Finish dependency between the product readiness and campaign tasks.\ c. Delay the marketing campaign until the product is fully ready.\ d. Assign a separate schedule for the marketing team and manage it independently.\ **Correct Answer**: A While creating the project schedule, a team identifies a high degree of uncertainty in future tasks. What is the best way to handle this?\ a. Use rolling wave planning to detail near-term tasks while keeping future tasks at a high level.\ b. Develop a fully detailed schedule for all tasks to reduce uncertainty.\ c. Apply contingency buffers to all uncertain tasks.\ d. Avoid scheduling uncertain tasks until more information is available.\ **Correct Answer**: A A project schedule includes tasks with varying levels of priority. A stakeholder requests additional tasks that might delay high-priority ones. How should the project manager address this?\ a. Evaluate the new tasks through a formal change control process before adding them to the schedule.\ b. Include the tasks immediately and adjust the high-priority tasks as needed.\ c. Reject the new tasks to ensure that high-priority tasks remain unaffected.\ d. Shift the high-priority tasks to later in the schedule to accommodate the request.\ **Correct Answer**: A A resource\'s availability changes midway through the project, causing a delay in a critical path task. What is the best course of action for the project manager?\ a. Reassign the task to another resource with the necessary skills.\ b. Add float to the task to account for the delay.\ c. Extend the project schedule to accommodate the resource\'s availability.\ d. Focus on non-critical tasks while waiting for the resource.\ **Correct Answer**: A The project team is using Monte Carlo simulations to analyze schedule risks. The results show a high likelihood of delays. What should the project manager prioritize?\ a. Develop mitigation strategies for high-risk activities and communicate findings to stakeholders.\ b. Add contingency time to all tasks in the project schedule.\ c. Reevaluate the entire project plan and start over.\ d. Focus only on activities on the critical path.\ **Correct Answer**: A A sponsor asks the project manager to compress the schedule by two weeks without changing the scope. What is the best way to achieve this?\ a. Evaluate options for crashing or fast tracking critical path tasks.\ b. Eliminate low-priority tasks from the schedule.\ c. Use resource smoothing to shorten task durations.\ d. Extend work hours for the project team.\ **Correct Answer**: A A stakeholder questions why the project schedule includes lag time between two key activities. How should the project manager address this?\ a. Explain that the lag is necessary to account for dependencies or external factors.\ b. Remove the lag to appease the stakeholder and accelerate the timeline.\ c. Replace the lag with additional tasks to fill the gap.\ d. Ignore the stakeholder's concern and proceed with the schedule.\ **Correct Answer**: A A project involves several interdependent tasks, and the team identifies a task that can only start once another task reaches 75% completion. How should the project manager model this?\ a. Use a lead time to start the task once the predecessor is partially complete.\ b. Create a Finish-to-Start dependency between the tasks.\ c. Split the dependent task into smaller segments.\ d. Use lag time to delay the start of the task.\ **Correct Answer**: A The project schedule includes a task with high resource demand that conflicts with another critical task. What is the best way to resolve this?\ a. Apply resource leveling to balance the workload without changing the schedule significantly.\ b. Focus all resources on the critical task and delay the other task.\ c. Extend the project timeline to accommodate both tasks.\ d. Reassign tasks without considering team expertise.\ **Correct Answer**: A A team identifies float in several non-critical tasks. How can the project manager use this float to benefit the project?\ a. Reallocate resources from non-critical tasks with float to critical tasks.\ b. Remove float to shorten the project schedule.\ c. Use float to extend the duration of non-critical tasks.\ d. Ignore float, as it does not affect the critical path.\ **Correct Answer**: A A project team is creating a schedule for a phased product rollout. The sponsor insists on detailed timelines for all phases upfront. How should the project manager respond?\ a. Use high-level timelines for future phases and detailed schedules for the current phase, following rolling wave planning principles.\ b. Create detailed schedules for all phases to meet the sponsor's expectations.\ c. Ignore the request and focus on completing the first phase.\ d. Delay the rollout until all schedules are finalized.\ **Correct Answer**: A A project manager identifies a high-risk task on the critical path. The team is concerned about the potential impact of delays. What should the project manager do?\ a. Develop contingency plans for the task and closely monitor its progress.\ b. Reassign the task to a non-critical path activity.\ c. Extend the project timeline to mitigate the risk.\ d. Ignore the risk and proceed with the original schedule.\ **Correct Answer**: A A sponsor requests that the project schedule include checkpoints to ensure adherence to the timeline. What is the best way to implement this?\ a. Add milestones at key points in the schedule to act as progress checkpoints.\ b. Create detailed daily task lists for the team to follow.\ c. Focus on reporting at the end of each project phase.\ d. Use the critical path to define checkpoints automatically.\ **Correct Answer**: A A sponsor wants to see a visual representation of the project schedule that highlights task durations, dependencies, and milestones. What should the project manager provide?\ a. A Gantt chart that visually depicts the schedule and milestones.\ b. A network diagram showing only dependencies.\ c. A list of milestones in a tabular format.\ d. A textual description of the project plan.\ **Correct Answer**: A The team realizes a task on the critical path has been underestimated by 20%. How should the project manager address this?\ a. Reevaluate the task's duration and adjust the schedule baseline if needed.\ b. Reassign resources from non-critical tasks to complete the task on time.\ c. Extend the project timeline to accommodate the new estimate.\ d. Remove other tasks to compensate for the underestimated task.\ **Correct Answer**: A A project manager is creating a schedule for a team using Agile practices. The team prefers flexible deadlines, but the sponsor demands fixed milestone dates. How should the project manager balance these needs?\ a. Set fixed milestones while allowing flexibility within iterations.\ b. Align all deadlines with the sponsor's expectations.\ c. Allow the team to set deadlines without milestones.\ d. Use Kanban to eliminate fixed dates entirely.\ **Correct Answer**: A A project team is working on a hybrid project with both predictive and adaptive elements. The predictive phase tasks are slipping due to dependencies on adaptive-phase deliverables that are not yet finalized. How should the project manager resolve this?\ a. Introduce rolling wave planning to refine adaptive-phase deliverables in time for predictive dependencies.\ b. Extend the predictive phase to allow more time for adaptive deliverables.\ c. Compress the adaptive schedule using crashing techniques.\ d. Remove adaptive-phase deliverables from predictive dependencies.\ **Correct Answer**: A The project's critical path contains tasks with varying risk levels. One high-risk task is forecasted to exceed its duration estimate by 40%. How should the project manager handle this?\ a. Conduct a Monte Carlo simulation to determine the probability of meeting the overall schedule.\ b. Add a contingency buffer to the critical path to absorb the delay.\ c. Focus on monitoring low-risk critical tasks to offset the delay.\ d. Reallocate resources from non-critical tasks to mitigate the delay.\ **Correct Answer**: A A construction project schedule requires aligning multiple subcontractors' activities. One subcontractor consistently underperforms, creating cascading delays. What should the project manager prioritize?\ a. Use resource smoothing to redistribute work among available subcontractors.\ b. Engage the subcontractor's leadership to renegotiate performance expectations.\ c. Rework the dependencies to isolate the subcontractor's tasks from others.\ d. Add float to tasks managed by the underperforming subcontractor.\ **Correct Answer**: B A key stakeholder demands that their department's deliverables be prioritized, potentially delaying work critical to another stakeholder. How should the project manager resolve this conflict?\ a. Conduct a stakeholder alignment session to reprioritize deliverables collaboratively.\ b. Prioritize the stakeholder with the highest authority in the organization.\ c. Add the stakeholder's tasks to the critical path and extend the timeline.\ d. Use earned value metrics to justify the prioritization of critical path tasks.\ **Correct Answer**: A A government project involves mandatory regulatory reviews at specific milestones. One regulatory body has announced a two-week delay in their review process. What is the best way to mitigate the impact?\ a. Re-sequence downstream tasks that are not dependent on the review.\ b. Add a contingency reserve to all milestones to absorb future delays.\ c. Fast-track all tasks preceding the review to make up for lost time.\ d. Escalate the delay to the project sponsor and request additional resources.\ **Correct Answer**: A A sponsor asks the project manager to add more tasks to the critical path to highlight their importance. This risks inflating the timeline unnecessarily. What should the project manager do?\ a. Explain the impact of critical path inflation and suggest alternative prioritization strategies.\ b. Add the tasks to the critical path to align with the sponsor's request.\ c. Remove float from non-critical tasks to balance the schedule.\ d. Highlight tasks using a priority code without modifying the critical path.\ **Correct Answer**: A During schedule creation, the project manager notices overlapping holidays across different regions where the project team operates. Some tasks require collaboration across all regions. How should the project manager handle this?\ a. Adjust the schedule to account for regional holidays and extend task durations.\ b. Use resource leveling to assign non-collaborative tasks during holidays.\ c. Assign a buffer to each collaborative task to account for potential delays.\ d. Mandate that team members work through holidays to meet deadlines.\ **Correct Answer**: A A project manager needs to fast-track a project, but the tasks with the most opportunity for overlap introduce significant quality risks. What is the best approach?\ a. Fast-track only low-risk tasks and accept a partially compressed timeline.\ b. Fast-track high-risk tasks and develop contingency plans for potential quality issues.\ c. Avoid fast-tracking entirely and focus on maintaining quality.\ d. Use crashing to add resources to high-risk tasks instead of fast-tracking.\ **Correct Answer**: A The project team is managing a program with interdependent projects. A delay in one project's critical path affects deliverables for another project. What should the project manager prioritize?\ a. Implement program-level schedule integration and coordinate critical path adjustments.\ b. Shift resources from unaffected projects to address the delay.\ c. Delay all downstream projects until the impacted deliverables are ready.\ d. Isolate the affected project's schedule to prevent cascading impacts.\ **Correct Answer**: A A project team is developing a schedule for a highly innovative product with significant unknowns. Stakeholders demand a detailed, fully predictive schedule. What should the project manager do?\ a. Propose a hybrid approach with rolling wave planning for uncertain areas.\ b. Create a fully predictive schedule with buffers for unknowns.\ c. Develop a high-level milestone schedule and avoid task-level details.\ d. Shift to an agile approach and refuse to provide a predictive schedule.\ **Correct Answer**: A A vendor-managed task on the critical path has high variability in its completion estimates. The vendor provides a wide range of optimistic, most likely, and pessimistic durations. What is the best course of action?\ a. Use the three-point estimating method to calculate an expected duration for scheduling.\ b. Add the pessimistic duration to the schedule to avoid underestimating.\ c. Use the optimistic duration and request regular updates from the vendor.\ d. Avoid scheduling the task until the vendor provides a narrower estimate.\ **Correct Answer**: A The project team is trying to compress the schedule using crashing, but the costs are exceeding the project's budget. How should the project manager respond?\ a. Conduct a cost-benefit analysis to determine which tasks provide the highest ROI when crashed.\ b. Reduce the scope of the project to accommodate the increased costs.\ c. Abandon crashing and accept the original timeline.\ d. Use fast tracking instead of crashing, even for high-risk tasks.\ **Correct Answer**: A A resource on a critical task has been reassigned to a higher-priority project by upper management. The reassignment delays the task and risks missing the deadline. What should the project manager prioritize?\ a. Request an equivalent replacement resource with similar expertise.\ b. Extend the project timeline to accommodate the delay.\ c. Negotiate with upper management to reinstate the resource.\ d. Reassign the task to a non-critical path activity.\ **Correct Answer**: A A team's schedule includes tasks that must comply with external approval processes. Approvals are frequently delayed without warning. What is the best strategy?\ a. Incorporate buffers for all tasks requiring external approvals.\ b. Use a just-in-time approach to request approvals closer to task deadlines.\ c. Remove dependencies on external approvals where possible.\ d. Proceed with non-critical tasks while awaiting approvals.\ **Correct Answer**: A A project manager is reviewing the schedule baseline and notices that non-critical tasks have unusually long durations. Stakeholders insist these durations remain unchanged. What should the project manager do?\ a. Use schedule compression techniques to ensure non-critical tasks do not impact the critical path.\ b. Reduce task durations without consulting stakeholders.\ c. Move non-critical tasks to the critical path to increase their visibility.\ d. Retain the durations and extend the overall timeline to maintain stakeholder satisfaction.\ **Correct Answer**: A

Use Quizgecko on...
Browser
Browser