Project Management and Refurbishment Works Quiz
15 Questions
0 Views

Project Management and Refurbishment Works Quiz

Created by
@ResourcefulGreenTourmaline

Podcast Beta

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which party instructed Avison Young to project manage the refurbishment works?

  • The Tenants
  • The Security
  • The Landlord (correct)
  • The Estate
  • What was the main purpose of the refurbishment works?

  • To improve site security
  • To improve the general condition of the estate
  • To secure new tenants (correct)
  • To repair external elements
  • What type of lease agreement are the units on?

  • External repairing and insuring basis
  • Internal repairing and insuring basis (correct)
  • Partial repairing and insuring basis
  • Full repairing and insuring basis
  • Why is site security a concern for the landlord and tenants?

    <p>Due to the 24/7 operations of the current tenants</p> Signup and view all the answers

    What did the client want to improve by installing additional security lights?

    <p>Security</p> Signup and view all the answers

    Which of the following was NOT included in the original package of works?

    <p>Installation of additional security lighting across the estate</p> Signup and view all the answers

    What was the purpose of upgrading the lighting supplies?

    <p>To improve the EPC ratings of the units</p> Signup and view all the answers

    What was the reason for installing a new 3 phase power supply to one unit?

    <p>To accommodate the increased power needs of the unit</p> Signup and view all the answers

    What was the purpose of redecorating the structural frame, internal walls, and existing floor slab?

    <p>To repair damages to the units' structure</p> Signup and view all the answers

    What type of doors were installed as part of the original package of works?

    <p>Roller shutter and personnel doors</p> Signup and view all the answers

    Which of the following was NOT part of the original package of works?

    <p>Installation of additional security lighting across the estate</p> Signup and view all the answers

    What was the purpose of the new amenity blocks installed within the units?

    <p>To enhance the facilities for the tenants</p> Signup and view all the answers

    What was the reason for repairing/replacing the flat roofs?

    <p>To prevent water leakage</p> Signup and view all the answers

    What was the purpose of redecorating the roof lining panels?

    <p>To improve the EPC ratings of the units</p> Signup and view all the answers

    What was the main purpose of upgrading the lighting supplies?

    <p>To improve the EPC ratings of the units</p> Signup and view all the answers

    More Quizzes Like This

    Project Management Chapter 1 Quiz
    4 questions
    Project Management Fundamentals
    20 questions
    Project Management Chapter 1 Review
    20 questions
    Use Quizgecko on...
    Browser
    Browser