11 Questions
Which of the following is NOT one of the four core knowledge areas of project management?
Project stakeholder management
Which role is primarily responsible for preparing and managing the project budget?
The project manager
What is the term used for a group of related projects managed in a coordinated way?
Program
Which of the following would NOT typically be considered a project stakeholder?
Opponents to the project
What is the term for the triangle representing the three key constraints of a project?
Triple constraint
Which knowledge area is concerned with identifying and analyzing stakeholder needs?
Project stakeholder management
According to the Standish Group study (CHAOS), what percentage of IT projects were successful in meeting scope, time, and cost goals?
16.2%
Which of the following is NOT listed as an advantage of using project management techniques?
Guaranteed project success
What is the primary characteristic that defines a project?
It has a unique purpose
Which of the following is NOT listed as an attribute of a project?
It has a strict deadline
Who typically provides the direction and funding for a project?
The project sponsor
Test your knowledge about the advantages of project management by taking this quiz. Learn about the benefits it provides, such as better control of resources and improved customer relations.