Procurement Regulations Quiz
44 Questions
0 Views

Procurement Regulations Quiz

Created by
@IntegralMaracas

Questions and Answers

Who is considered the head of the procurement in local government units (LGUs)?

  • The head of the national agency
  • The local chief executive (correct)
  • The governing board member
  • The authorized procurement officer
  • What are some of the infrastructure projects included under the provided definitions?

  • Developing private sector office buildings
  • Construction of residential housing
  • Renovating commercial retail spaces
  • Building restoration and maintenance of hospitals (correct)
  • Which entity is responsible for procurement in government-owned or controlled corporations (GOCCs)?

  • The budgetary committee
  • The head of the state department
  • The governing board or its authorized official (correct)
  • The regional administrator
  • When procurement responsibility is decentralized, who is considered the head of procurement (HoPE)?

    <p>The head of each decentralized unit</p> Signup and view all the answers

    Which of the following is NOT included in the definition of infrastructure projects?

    <p>Construction of private residential properties</p> Signup and view all the answers

    What does Common-Use Supplies and Equipment (CSE) refer to?

    <p>Items essential for day-to-day operations of Procuring Entities</p> Signup and view all the answers

    Which process is NOT part of Competitive Bidding?

    <p>Post-contract evaluation</p> Signup and view all the answers

    Consulting Services primarily require expertise that is what?

    <p>Adequate external technical and professional expertise</p> Signup and view all the answers

    Which of the following best describes a Domestic Bidder?

    <p>A person or entity offering goods produced in the Philippines</p> Signup and view all the answers

    What is the significance of the Electronic Catalogue in relation to CSE?

    <p>It includes the goods and equipment categorized as CSE</p> Signup and view all the answers

    Which of the following activities is considered a Consulting Service?

    <p>Conducting a feasibility study</p> Signup and view all the answers

    What do the terms 'Competitive Bidding' and 'Public Bidding' refer to?

    <p>Identical processes with interchangeable meanings</p> Signup and view all the answers

    To which type of procurement does Rule V of this IRR relate?

    <p>Competitive Bidding processes</p> Signup and view all the answers

    What is included in the invitation to bid?

    <p>The type of work</p> Signup and view all the answers

    What does prequalification of contractors involve?

    <p>Assessing contractor ability before bidding</p> Signup and view all the answers

    When are the qualifications of the low bidder typically evaluated?

    <p>After the bids are opened</p> Signup and view all the answers

    Which factor is NOT typically assessed when checking contractor ability?

    <p>Political affiliations</p> Signup and view all the answers

    What type of documents are construction documents considered to be?

    <p>Written and graphic documents</p> Signup and view all the answers

    How can the invitation to bid be disseminated to contractors?

    <p>By mailing and public advertisements</p> Signup and view all the answers

    What is the purpose of the notice to proceed in the bidding process?

    <p>To indicate the start of construction</p> Signup and view all the answers

    Which of the following is NOT a qualification criterion for contractors?

    <p>Location of the contractor</p> Signup and view all the answers

    Which procurement does not require a pre-procurement conference?

    <p>Procurement of Consulting Services costing ₱1,000,000.00 and below</p> Signup and view all the answers

    What information must be included in the Invitation to Bid for Goods?

    <p>Name of the contract and a brief description of the goods</p> Signup and view all the answers

    Which element is NOT a required inclusion in the Invitation to Bid?

    <p>The approval from local government</p> Signup and view all the answers

    What should the Invitation to Bid specify regarding electronic bid submission?

    <p>Whether submissions through electronic means are allowed</p> Signup and view all the answers

    Which of the following is NOT a requirement for goods procurement in the Invitation to Bid?

    <p>Detailed list of past contracts</p> Signup and view all the answers

    What is an important criterion for Consulting Services as stated in the Invitation to Bid?

    <p>Shortlisting of prospective bidders</p> Signup and view all the answers

    What information does NOT need to be included about the procurement of Infrastructure Projects?

    <p>Total budget for the project</p> Signup and view all the answers

    Which of the following is a requirement for the submission and receipt of bids detailed in the Invitation to Bid?

    <p>Date, time, and place of bids' opening</p> Signup and view all the answers

    What constitutes a small procurement of Consulting Services?

    <p>Costing ₱1,000,000.00 or less</p> Signup and view all the answers

    What is the purpose of a pre-bid conference?

    <p>To discuss technical and financial components of the bid</p> Signup and view all the answers

    What must happen for a statement made at a pre-bid conference to modify the bidding documents?

    <p>It must be identified in writing as an amendment</p> Signup and view all the answers

    Who is responsible for opening the bids?

    <p>The BAC in the presence of bidders or their representatives</p> Signup and view all the answers

    What is included in the responsibilities during the bid evaluation phase?

    <p>Ranking the total bid prices</p> Signup and view all the answers

    How long is the bid evaluation process expected to take?

    <p>3 days</p> Signup and view all the answers

    What document must be prepared to formally award a bid?

    <p>Resolution to Award</p> Signup and view all the answers

    What is the timeframe for posting the Notice to Award?

    <p>1 day</p> Signup and view all the answers

    What happens during the delivery, inspection, and acceptance phase?

    <p>Final inspection and acceptance of goods or services</p> Signup and view all the answers

    How is the lowest calculated responsive bid determined?

    <p>Through clarification of bids and examination of documents</p> Signup and view all the answers

    What is the role of the BAC during the bid opening?

    <p>To initial every page of original copies of all eligible documents</p> Signup and view all the answers

    In what situation would a bid submission be deemed unacceptable?

    <p>If the bid does not meet the eligibility requirements</p> Signup and view all the answers

    What is the purpose of a bid bulletin?

    <p>To amend the bidding process and documents</p> Signup and view all the answers

    What documentation is required for the award notice?

    <p>Resolution of the BAC to Award</p> Signup and view all the answers

    How long is the typical timeframe for the implementation of a contract after the award?

    <p>1 day</p> Signup and view all the answers

    Study Notes

    Pre-Bid Conference

    • Conducted at a specified time to discuss technical and financial aspects of the bid and eligibility requirements.
    • Any statements made during this conference can modify bidding documents only if documented as formal amendments.

    Receipt and Opening of Bids

    • Bids are opened by the Bids and Awards Committee (BAC) in the presence of bidders or their representatives.
    • All BAC members present must initial each page of the original copies of each eligible bid.

    Bid Evaluation

    • Involves a preliminary examination of bids to assess eligibility, documentation, and pricing.
    • An Abstract of Bids is prepared, ranking total bid prices from lowest to highest.
    • Evaluation report is generated based on the review.

    Awarding of Contract

    • Resolution to Award and Notice to Award prepared and approved by the BAC and its Secretariat.
    • Notice to Award is issued to the bidder, followed by posting the Performance Security.

    Implementation of Contract

    • Contract signing occurs after the Notice to Proceed is issued to the winning bidder.
    • Delivery of goods/services is mandated as specified in the contract, followed by final inspection and acceptance.

    Advertising Process

    • Begins with an invitation to bid, detailing the type of work, location, and timeline for the bid opening.
    • Invitations may be distributed via mail or public media such as newspapers or PhilGEPS website.

    Qualification of Contractors

    • Contractors' capabilities assessed based on experience, financial resources, integrity, personnel, and equipment.
    • Prequalification restricts bidding to only capable contractors, while post-qualification verifies the low bidder's qualifications before contract award.

    Bidding Documents

    • Construction documents include written and graphic materials for project design and contract administration.
    • Common-use supplies are categorized based on daily operational requirements of procurement entities.

    Competitive Bidding Process

    • Open to any interested party and includes advertisement, pre-bid conference, eligibility screening, bid receipt and opening, evaluation, post-qualification, and contract award.

    Notice to Proceed

    • The procurements for small goods, infrastructure projects, and consulting services may not require a pre-procurement conference if they fall below specified cost thresholds.

    Contents of Invitation to Bid

    • Should outline project descriptions, evaluation criteria, deadlines, ABC (Approved Budget for the Contract), funding sources, contract durations, and contact information for bidding entities.

    Electronic Bid Submission

    • Bidding documents must clarify if electronic submission and receipt of bids are permitted by the procuring entity.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Test your knowledge on the regulations regarding small procurements, including thresholds for goods, infrastructure projects, and consulting services. This quiz covers key concepts and requirements in the bidding process.