What happens if the Employer’s Representative does not give the Notice of agreement or determination within the relevant time limit?

  • The matter shall be deemed to be an Agreement
  • The matter shall be deemed to be a Dispute (correct)
  • The matter shall be deemed resolved
  • The matter shall be referred to the Contractor
  • What is the effect of each agreement or determination?

  • It shall be binding only on the Contractor
  • It shall not be binding until further notice
  • It shall be binding only on the Employer
  • It shall be binding on both Parties (correct)
  • When must the Contractor include the payment amount in the next Statement?

  • When a dispute arises
  • When an agreement or determination concerns the payment of an amount from one Party to the other Party (correct)
  • When the Employer’s Representative gives a Notice of agreement
  • When an agreement is reached
  • What happens if the determination is revised under Clause 21?

    <p>It is no longer binding</p> Signup and view all the answers

    What is the time frame within which the Contractor can object to a nominated Subcontractor?

    <p>14 days</p> Signup and view all the answers

    When is the submission of the health and safety manual required?

    <p>Within 21 days of Commencement Date</p> Signup and view all the answers

    Who is responsible for setting out works and rectifying errors in positioning?

    <p>Contractor</p> Signup and view all the answers

    What triggers the application of Sub-Clause 7.5 [Defects and Rejection]?

    <p>Non-compliance with the Contract</p> Signup and view all the answers

    Who is required to provide fencing, lighting, safe access, and temporary works for public and adjacent land/property protection?

    <p>Contractor</p> Signup and view all the answers

    What is the definition of 'Nominated Subcontractor'?

    <p>Subcontractor named in Employer's Requirements or instructed by the Employer under Provisional Sums</p> Signup and view all the answers

    When must the JV members comply with health and safety regulations and laws?

    <p>At all times</p> Signup and view all the answers

    What is the time frame for the Contractor to prepare and implement a Compliance Verification System?

    <p>Within 21 days of Commencement Date</p> Signup and view all the answers

    What is the Contractor responsible for verifying?

    <p>Accuracy of reference items</p> Signup and view all the answers

    Who is responsible for the care of all persons on the Site?

    <p>Contractor</p> Signup and view all the answers

    What does the Compliance Verification System need to include?

    <p>Reporting method for inspection and test results</p> Signup and view all the answers

    What is the consequence of non-compliance with the Contract?

    <p>Application of Sub-Clause 7.5 [Defects and Rejection]</p> Signup and view all the answers

    Under Clause 4.10, what does compliance with the QM System and/or Compliance Verification System NOT relieve the Contractor from?

    <p>Any duty, obligation or responsibility under or in connection with the Contract</p> Signup and view all the answers

    According to Clause 4.11, what is the Contractor responsible for verifying and interpreting?

    <p>All data made available by the Employer under Sub-Clause 2.5</p> Signup and view all the answers

    Under Clause 4.12, what does the Contractor accept total responsibility for by signing the Contract Agreement?

    <p>Having foreseen all difficulties and costs of successfully completing the Works</p> Signup and view all the answers

    According to Clause 4.13, who is responsible for bearing all costs and charges for special and/or temporary rights-of-way?

    <p>The Contractor</p> Signup and view all the answers

    What does the Contractor need to obtain at their risk and cost according to Clause 4.13?

    <p>Any additional facilities outside the Site required for the Works</p> Signup and view all the answers

    What is the Contractor deemed to have satisfied themselves as to under Clause 4.11?

    <p>The correctness and sufficiency of the Contract Price stated in the Contract Agreement</p> Signup and view all the answers

    Under Clause 4.12, what is the Contract Price deemed to cover unless otherwise stated in the Contract?

    <p>All the Contractor’s obligations under the Contract and all things necessary for the proper execution of the Works</p> Signup and view all the answers

    According to Clause 4.13, who must bear the costs and charges for special and/or temporary rights-of-way required for the purposes of the Works?

    <p>The Contractor</p> Signup and view all the answers

    What is the time frame within which a Party may give a Notice of Dissatisfaction (NOD) if dissatisfied with the Employer's Representative's determination?

    <p>28 days</p> Signup and view all the answers

    If only part of the determination is disputed, what must be done in the Notice of Dissatisfaction (NOD)?

    <p>It must be clearly identified</p> Signup and view all the answers

    What may lead to arbitration under Sub-Clause 21.6 without prejudice to other rights?

    <p>Failure to comply with the agreement or determination</p> Signup and view all the answers

    What must the Contractor do not less than 28 days before exercising certain powers as specified in the Contract Data?

    <p>Give the Employer a Notice</p> Signup and view all the answers

    What is the Contractor responsible for managing, coordinating, and ensuring?

    <p>The work of all Subcontractors</p> Signup and view all the answers

    What are the involved parties required to be fluent in for communications as defined in the Contract?

    <p>The language</p> Signup and view all the answers

    What may the Contractor not subcontract works with a total accumulated value greater than?

    <p>The percentage stated in the Contract Data</p> Signup and view all the answers

    What must the Employer's Representative advise the Parties of within 14 days after giving or receiving the notice of agreement or determination?

    <p>Typographical, clerical, or arithmetical errors</p> Signup and view all the answers

    What happens if the determination is revised under Clause 21?

    <p>The revised determination becomes final and binding</p> Signup and view all the answers

    What must be done if either Party requires the other to attend a management meeting?

    <p>Records of the meeting must be kept and distributed to attendees</p> Signup and view all the answers

    What must the Contractor ensure about the Works?

    <p>They are fit for their intended purpose</p> Signup and view all the answers

    What is the consequence of non-compliance with the agreement or determination?

    <p>Arbitration under Sub-Clause 21.6</p> Signup and view all the answers

    Study Notes

    FIDIC 2017 Conditions of Contract for EPC/Turnkey Projects

    • Subcontractor's appointment requires detailed particulars including relevant experience, work commencement, and site commencement
    • "Nominated Subcontractor" defined as one named in Employer's Requirements or instructed by Employer under Provisional Sums
    • Contractor can object to nominated Subcontractor within 14 days with detailed reasons
    • Contractor entitled to EOT and/or payment for delay/cost due to Employer's instruction causing unforeseeable cooperation issues
    • Contractor responsible for setting out works, verifying accuracy of reference items, and rectifying errors in positioning
    • Contractor obligated to comply with health and safety regulations and laws, directives, and care for all persons on the Site
    • Contractor to provide fencing, lighting, safe access, and temporary works for public and adjacent land/property protection
    • Submission of health and safety manual required within 21 days of Commencement Date
    • JV members also obligated to comply with health and safety regulations and laws
    • Contractor to prepare and implement a Compliance Verification System to demonstrate compliance with the Contract
    • Compliance Verification System to include reporting method for inspection and test results
    • Non-compliance with the Contract triggers application of Sub-Clause 7.5 [Defects and Rejection]

    FIDIC EPC/Turnkey Projects Contract - Key Provisions

    • The Employer's Representative must immediately advise the Parties of any typographical, clerical, or arithmetical errors found within 14 days after giving or receiving the notice of agreement or determination.
    • If dissatisfied with the Employer's Representative's determination, a Party may give a Notice of Dissatisfaction (NOD) within 28 days, and if no NOD is given, the determination is deemed final and binding.
    • If only part of the determination is disputed, that part must be clearly identified in the NOD, and the remainder becomes final and binding.
    • Failure to comply with the agreement or determination may lead to arbitration under Sub-Clause 21.6 without prejudice to other rights.
    • Either Party may require the other to attend a management meeting to discuss future work and other matters, and records of these meetings must be kept and distributed to attendees.
    • The Contractor is obligated to execute the Works in accordance with the Contract and ensure they are fit for their intended purpose.
    • All involved parties must be fluent in the language for communications as defined in the Contract.
    • The Contractor may not subcontract works with a total accumulated value greater than the percentage stated in the Contract Data or any part of the Works for which subcontracting is not permitted.
    • The Contractor is responsible for managing, coordinating, and ensuring the work of all Subcontractors complies with the Contract.
    • The Contractor must give the Employer a Notice not less than 28 days before exercising certain powers as specified in the Contract Data.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your knowledge of the key provisions and obligations outlined in the FIDIC 2017 Conditions of Contract for EPC/Turnkey Projects, including subcontractor appointment, compliance verification system, dispute resolution, and management meetings.

    More Like This

    R 2017 - 1
    46 questions

    R 2017 - 1

    AstoundedHamster avatar
    AstoundedHamster
    R 2017 - 8
    37 questions

    R 2017 - 8

    AstoundedHamster avatar
    AstoundedHamster
    R 2017 - 17
    37 questions

    R 2017 - 17

    AstoundedHamster avatar
    AstoundedHamster
    S 2017 - 6
    40 questions

    S 2017 - 6

    AstoundedHamster avatar
    AstoundedHamster
    Use Quizgecko on...
    Browser
    Browser