What is the primary responsibility of the official-in-charge regarding the block section?

  • To ensure the Station Master is informed of the entry time only.
  • To clear the block section completely by the specified time. (correct)
  • To remain in the block section and assist with train operations.
  • To enter the block section and notify train officials
  • What information must be recorded by both Station Masters in the Train Signal Register when a motor trolley is entering a block section?

  • The motor trolley number and other particulars as for a train. (correct)
  • The weather conditions which may impact the ride.
  • The names of the officials traveling on the trolley.
  • The time of entry and exit of the motor trolley.
  • How should a Station Master acknowledge the line clear for a motor trolley proceeding outside station limits?

  • By sending a radio message of acknowledgement to the receiving station.
  • By handing over the authority to proceed, along with a duplicate memo to the messenger after obtaining a signature. (correct)
  • By simply providing a verbal approval to the official-in-charge.
  • By providing a written confirmation to the official in charge through the railway's internal messaging system.
  • What action should an officer in charge of a motor trolley take at a reception signal if it is 'on' during the day with good visibility?

    <p>Wait for a minimum of 10 minutes, then cautiously proceed past, being prepared to stop short of obstructions. (A)</p> Signup and view all the answers

    What potential danger exists when motor trolleys pass over spring loaded points?

    <p>They are prone to derailment because they are too light to correctly trail through the spring-loaded points. (A)</p> Signup and view all the answers

    Prior to placing the motor trolley on the track outside station limits, what must the official-in-charge receive?

    <p>The authority to proceed and a duplicate copy of the memo sent to the Station Master. (C)</p> Signup and view all the answers

    What should an officer do at the outermost facing points when passing a signal at 'on'?

    <p>Stop until hand-signaled into the station by the Station Master. (B)</p> Signup and view all the answers

    What is the initial action the official-in-charge must take when planning to enter a block section with a motor trolley?

    <p>Inform the Station Master about the block section and expected clearance time. (D)</p> Signup and view all the answers

    When a motor trolley approaches spring-loaded points against its direction of travel, what action must the driver take?

    <p>Stop before the points, lift the trolley off the track, and place it on the correct line. (C)</p> Signup and view all the answers

    What is the primary responsibility of the Station Master when a motor trolley is dispatched from a station with spring-loaded points against its direction of travel?

    <p>To issue a Caution Order to the motor trolley driver, detailing the location of the points. (D)</p> Signup and view all the answers

    During a crossing of trains, where can a motor trolley be berthed?

    <p>On a non-running line, or on a running line already occupied by a train. (A)</p> Signup and view all the answers

    If a motor trolley breaks down, what is the immediate action required by the official-in-charge?

    <p>Remove the trolley from the line immediately, if it can't be propelled by hand. (D)</p> Signup and view all the answers

    When a disabled motor trolley is to be placed back on the line, what should be followed?

    <p>The same procedure as for the initial placement of a motor trolley on the line must be followed. (A)</p> Signup and view all the answers

    In the context of being used as a crossing train, how is a berthed motor trolley considered?

    <p>It is not counted as a crossing train for the purpose of the number of trains permitted to cross at a station. (D)</p> Signup and view all the answers

    Where can information about motor trolley operations in a single line token section be found?

    <p>Para No. 4.19 of BWM - Part I. (D)</p> Signup and view all the answers

    According to the provided content, where can guidelines for motor trolley operation on a double line section be found?

    <p>Para No. 6.16 of BWM - Part I. (C)</p> Signup and view all the answers

    Flashcards

    Motor Trolley Block Section Notification

    The person in charge of a motor trolley informs the station master when they will enter and clear a block section.

    Motor Trolley Authorization Process

    The station master receives the notification, confirms the line is clear with the other station master, and then gives the 'official-in-charge' the authority to proceed, recording everything in the Train Signal Register.

    Motor Trolley Block Section Responsibility

    The person in charge of a motor trolley is responsible for clearing the block section within the specified time.

    Out-of-Station Motor Trolley Procedure

    A written memo is sent to the station master to request line clearance outside of station limits, indicating time needed for clearing the block section.

    Signup and view all the flashcards

    Out-of-Station Motor Trolley Placement

    A Motor Trolley must be placed on the line only after receiving authority to proceed and a duplicate copy of the memo.

    Signup and view all the flashcards

    Motor Trolley Signal Compliance

    Motor Trolley operators must follow all fixed signals.

    Signup and view all the flashcards

    Officer's Discretion with Motor Trolley Signals

    Officers in charge of a motor trolley can pass a reception signal in the daytime with good visibility after waiting at least 10 minutes, but must proceed cautiously and stop at outer facing points until signaled into the station.

    Signup and view all the flashcards

    Motor Trolley Derailment Risk

    Because of their lightness, motor trolleys can easily derail when passing over spring-loaded points.

    Signup and view all the flashcards

    Caution Order for Spring-Loaded Points

    When spring-loaded points are positioned against the path of a motor trolley, the Station Master must inform the Station Master at the other end to issue a Caution Order to the motor trolley driver, specifying the location of the points.

    Signup and view all the flashcards

    Station Master's Responsibility for Spring-Loaded Points

    It is the responsibility of the Station Master to warn the motor trolley driver of the presence of spring-loaded points before dispatching the trolley.

    Signup and view all the flashcards

    Driver's Response to Caution Order

    When a Caution Order is issued, the motor trolley driver must stop short of the spring-loaded points, manually lift the trolley off the track, and place it on the correct line before proceeding.

    Signup and view all the flashcards

    Official's Responsibility for Spring-Loaded Point Locations

    The official in charge of a motor trolley must familiarize themselves with the location of spring-loaded points on the section before placing the trolley on the line.

    Signup and view all the flashcards

    Berthing of Motor Trolleys During Train Crossings

    A motor trolley can be temporarily parked on a non-running or running line to facilitate the crossing of trains. It does not count as a crossing train for the purpose of allowable crossings.

    Signup and view all the flashcards

    Procedure for Disabled Motor Trolleys

    If a motor trolley breaks down and cannot be moved by hand, the official in charge must remove it from the line immediately.

    Signup and view all the flashcards

    Motor Trolley Operations in Single-Line Token Sections

    In single-line token sections, the procedures for operating a motor trolley as a train or following another train or motor trolley are outlined in Para 4.19 of the Board's Working Manual (BWM) - Part I.

    Signup and view all the flashcards

    Motor Trolley Operations in Single-Line Tokenless Sections

    In single-line tokenless sections, the procedures for operating a motor trolley as a train or following another train or motor trolley are outlined in Para 5.29 of the Board's Working Manual (BWM) - Part I.

    Signup and view all the flashcards

    Study Notes

    Motor Trolley Operation Procedures

    • Block Section Procedures: The official-in-charge must notify the Station Master of the block section and time the motor trolley will enter. The Station Master then confirms line clearance with the other end Station Master, granting authority to proceed. Both Station Masters record the motor trolley's details (number as train number) in the Train Signal Register using red ink. The official-in-charge is responsible for clearing the block by the set time.

    • Placing Motor Trolley Outside Station Limits: A memo (duplicate) requesting line clearance is sent to the nearest Station Master, specifying the required clearing time. The receiving Station Master obtains clearance from the other end and provides the authority to proceed, along with the memo duplicate. The official in charge only places the motor trolley on the line after receiving authority and the duplicate memo.

    Motor Trolley Signal Operation

    • Fixed Signals: The motor trolley's in-charge must obey all fixed signals. A railway officer may, under daylight and good visibility conditions, pass reception signals set to "on" after waiting 10 minutes. However, proceeding with special caution remains crucial, as short stops are necessary for potential roadblocks, wrong points or placement at the outer facing points. The motor trolley must await further signal confirmation from the station master before entering the station.

    • Spring-Loaded Points: Motor trolleys cannot traverse spring-loaded points due to their light weight, potentially derailing if they pass through these points. To avoid this: The Station Master, before granting line-clearance, advises the other end Station Master about the existence of spring-loaded points (location). Station Masters issuing motor trolley's caution notices about spring loaded points at their respective ends (location). The motor trolley driver must lift the trolley off the track and place it on the correct line after stopping short of the points.

    • Crossing Trains: Motor trolleys can be moved to a non-running line or an occupied running line in order to facilitate crossing trains. It does not count as a crossing train for station capacity calculations.

    Motor Trolley Breakdown and Special Cases

    • Breakdown: If a motor trolley breaks down and cannot be hand-propelled, the official-in-charge must remove it from the track immediately. To replace a disabled motor trolley, the procedures outlined in the document must be followed.

    • Single and Double Line Sections, Token Section, Tokenless Section: For specific procedures on how motor trolley operates as a train, including following other trains in single-line token or tokenless and, double-line sections, refer to relevant paragraphs. These procedures (and related document numbers) are specified for each operational condition (e.g., single line token, tokenless section, double line).

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz covers the essential procedures for operating a motor trolley within block sections and outside station limits. Participants will learn about the roles of Station Masters, notification protocols, and signal operations necessary for safe and efficient motor trolley management.

    More Like This

    Motor and Cognitive Skills Overview
    11 questions
    Motor Learning Chapter 2 Flashcards
    13 questions
    Motor Vehicle Unit 172 Flashcards
    47 questions
    Classification of Motor Skills Quiz
    10 questions
    Use Quizgecko on...
    Browser
    Browser