Methods for Determining Percent Complete in Project Management
30 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the purpose of taking corrective action in project control?

  • To select performance measures
  • To determine the baseline schedule and budget
  • To analyze deviations and their causes (correct)
  • To update schedules
  • What kind of information is needed for updating schedules according to the text?

  • Activities that have been deleted (correct)
  • Activities that have not started
  • The estimated value of each performance measure
  • The baseline schedule
  • In project control, what should be analyzed to detect current and future deviations?

  • Actual completion date of each activity
  • Raw data collection frequency
  • Collected data from various sources (correct)
  • Activities that are complete
  • What does the project control system aim to address?

    <p>Determining the causes of deviations</p> Signup and view all the answers

    Which type of activities are crucial for updating schedules?

    <p>Completed activities with actual completion dates</p> Signup and view all the answers

    What does the project control system help project managers do?

    <p>Identify and correct deviations</p> Signup and view all the answers

    Which method is more suitable for large and complex or multistage activities?

    <p>Incremental milestone method</p> Signup and view all the answers

    What does the Weighted Milestone Method allow project managers to do?

    <p>Divide work packages into small segments</p> Signup and view all the answers

    When does the Start-Finish percentage method work best?

    <p>For small activities or those with no or short duration</p> Signup and view all the answers

    In what scenarios would the Supervisor's opinion method be used?

    <p>When no other applicable method is suitable</p> Signup and view all the answers

    What type of data does the Progress Table capture?

    <p>Dates of when the milestones were achieved</p> Signup and view all the answers

    How does the Weighted Milestone Method differ from the Incremental Milestone Method?

    <p>By dividing work packages into small segments</p> Signup and view all the answers

    What does a positive VAC indicate?

    <p>The project is under budget</p> Signup and view all the answers

    What does a negative VAC suggest?

    <p>The project is over budget</p> Signup and view all the answers

    What does TCPI < 1 mean for a project?

    <p>More funds and less work are needed</p> Signup and view all the answers

    What does TCPI = 1 indicate for a project?

    <p>Just enough funds to complete the work</p> Signup and view all the answers

    What does it mean if the VAC value approaches zero?

    <p>Budget is accurate</p> Signup and view all the answers

    What is the purpose of TCPI in a project?

    <p>To assess cost performance needed to achieve project goals</p> Signup and view all the answers

    What types of changes can trigger updates to project schedules?

    <p>Changes in duration, logic, budget, resources, constraints, and others</p> Signup and view all the answers

    What is considered a schedule-related, but not activity-specific change?

    <p>A change in resource availability</p> Signup and view all the answers

    Which frequency of updating project schedules is likely the most common?

    <p>Biweekly</p> Signup and view all the answers

    What negative consequences can arise from infrequent updates to project schedules?

    <p>Overwhelming the scheduler with work progress reports</p> Signup and view all the answers

    Why is achieving the right balance in the frequency of updates crucial for project managers?

    <p>To ensure work progress is properly analyzed</p> Signup and view all the answers

    In what scenario might a subcontractor be involved in a schedule-related change?

    <p>Taking over another subcontractor's work</p> Signup and view all the answers

    What does TCPI stand for in project management?

    <p>Total Cost Performance Index</p> Signup and view all the answers

    How is the monetary value of remaining work calculated in the TCPI formula?

    <p>(Total Project Budget - Actual Expenditure)</p> Signup and view all the answers

    Which formula should be used to calculate TCPI if the project must be completed within the original budget?

    <p>TCPI = (Budget at Completion - Earned Value) / (Budget at Completion - Actual Cost)</p> Signup and view all the answers

    What does the TCPI represent in project management when it is greater than 1?

    <p>Project under budget</p> Signup and view all the answers

    How can the TCPI be calculated if the project has to be completed within the revised budget (EAC)?

    <p>(Budget at Completion - Earned Value) / (Estimated at Completion - Actual Cost)</p> Signup and view all the answers

    What is the purpose of using different TCPI formulas based on whether the original or revised budget needs to be maintained?

    <p>To adapt to changing project conditions and budgets</p> Signup and view all the answers

    More Like This

    Project Management Chapter 1 Quiz
    4 questions
    Project Management Process Groups
    14 questions

    Project Management Process Groups

    WellConnectedComputerArt avatar
    WellConnectedComputerArt
    PMI Project Management Terms Flashcards
    26 questions
    Use Quizgecko on...
    Browser
    Browser