Management by Objectives Quiz
10 Questions
3 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement called?

  • Management by Objectives (correct)
  • Strategic Planning
  • Contingency Planning
  • Detailed planning
  • During the full life cycle of a project, a characteristic S curve of expected expenditures indicates:

  • Problems will always occur in the execution phase.
  • The bulk of the project budget will be spent in the execution phase. (correct)
  • There are high expenditures during closeout.
  • There is a cyclic nature to all projects.
  • In which project lifecycle phase would you expect to have the greatest influence on overall project cost?

  • Concept (correct)
  • Build
  • Launch
  • Design
  • What is a characteristic feature of a project's expected expenditures during its full life cycle?

    <p>Expenditures peak during execution and decrease during closeout.</p> Signup and view all the answers

    What is a key activity in management by objectives?

    <p>Reviewing employee performance relative to objectives.</p> Signup and view all the answers

    What is the process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement called?

    <p>Management by Objectives</p> Signup and view all the answers

    During the full life cycle of a project, a characteristic S curve of expected expenditures indicates:

    <p>The bulk of the project budget will be spent in the execution phase.</p> Signup and view all the answers

    What is a key activity in management by objectives?

    <p>Discussing employee objectives and reviewing performance relative to those objectives.</p> Signup and view all the answers

    In which project lifecycle phase would you expect to have the greatest influence on overall project cost?

    <p>Concept</p> Signup and view all the answers

    What is a characteristic feature of a project's expected expenditures during its full life cycle?

    <p>Expenditures follow an S curve with peak during execution phase.</p> Signup and view all the answers

    More Like This

    SI Governance Objectives
    29 questions

    SI Governance Objectives

    ExuberantGingko1246 avatar
    ExuberantGingko1246
    Cel osiągnięcia w zarządzaniu
    38 questions

    Cel osiągnięcia w zarządzaniu

    ManeuverableHorseChestnut avatar
    ManeuverableHorseChestnut
    Objetivos en Organizaciones
    37 questions
    Use Quizgecko on...
    Browser
    Browser