ISY109 Comprehensive Exam: Project Management
37 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the purpose of the 5 Whys technique?

  • To convert an organization's value drivers to metrics
  • To group tasks into higher level categories
  • To create a project schedule plan
  • To identify the root cause of a problem (correct)
  • What type of diagram is used to illustrate the sequence of activities?

  • Activity-on-Arrow (AOA) diagram (correct)
  • Gantt chart
  • Activity-on-Node (AON) diagram
  • Flowchart
  • What determines the start and late finish dates for each activity in a project?

  • Activity list
  • Earned value management
  • Actual cost
  • Acceptance decisions (correct)
  • What is the purpose of an activity list?

    <p>To tabulate activities to be included in a project schedule plan</p> Signup and view all the answers

    What is the total of direct and indirect costs incurred in a project?

    <p>Actual cost</p> Signup and view all the answers

    What is the purpose of converting an organization's value drivers to metrics?

    <p>To measure performance and achieve goals</p> Signup and view all the answers

    What is the primary purpose of a project life cycle?

    <p>To ensure that functionally grouped components work together</p> Signup and view all the answers

    What is the term for the amount of time an activity can be delayed without delaying a succeeding activity?

    <p>Free Slack</p> Signup and view all the answers

    What is the purpose of an Ishikawa Diagram?

    <p>To identify the root cause of quality problems</p> Signup and view all the answers

    What is the term for the degree to which a system performs its intended function?

    <p>Functionality</p> Signup and view all the answers

    What is the primary purpose of a Forward Pass in a network diagram?

    <p>To determine the early start of any immediately following activity</p> Signup and view all the answers

    What is the purpose of a Budgetary Estimate?

    <p>To allocate money into an organization's budget</p> Signup and view all the answers

    Which technique uses the actual cost of a previous similar project as a basis for estimating the cost?

    <p>Analogous Estimates</p> Signup and view all the answers

    What is a Backward Pass in a project network?

    <p>A technique used to find the critical path in a project network</p> Signup and view all the answers

    What is the purpose of a Balance Scorecard?

    <p>To track the execution of business process flows</p> Signup and view all the answers

    What is the purpose of a Cause and Effect Diagram?

    <p>To identify the root cause of a problem</p> Signup and view all the answers

    What is the purpose of Cash Flow Analysis?

    <p>To estimate the projected cost to complete a project</p> Signup and view all the answers

    What is the term for the process of subdividing project deliverables into smaller pieces?

    <p>Decomposition</p> Signup and view all the answers

    What is the ratio of earned value to actual cost?

    <p>Cost Performance Index (CPI)</p> Signup and view all the answers

    What is the term for the longest path through a project network diagram that determines the earliest project completion date?

    <p>Critical Path</p> Signup and view all the answers

    What is the term for a graphic display of data that illustrates the results of a process over time?

    <p>Control Chart</p> Signup and view all the answers

    What is the term for a cost estimate that provides an accurate estimate of project costs?

    <p>Definitive Estimate</p> Signup and view all the answers

    What is the term for the cost of conformance plus the cost of non-conformance?

    <p>Cost of Quality</p> Signup and view all the answers

    What is the term for a process that describes when and how official project documents may be changed?

    <p>Change Control System</p> Signup and view all the answers

    What is the term for a technique used to predict total project duration?

    <p>Critical Path Method (CPM)</p> Signup and view all the answers

    What is the term for a project document that outlines the cost baseline?

    <p>Cost Management Plan</p> Signup and view all the answers

    What is the term for a diagram that traces complaints about quality problems back to the responsible production operations?

    <p>Fishbone Diagram</p> Signup and view all the answers

    What is meant by Float in a project?

    <p>The amount of time a project activity may be delayed without delaying a succeeding activity</p> Signup and view all the answers

    What is the objective of Milestone in a project?

    <p>To serve as a marker to help in identifying necessary activities and setting goals</p> Signup and view all the answers

    What is the primary focus of Scope Creep?

    <p>To increase the project scope</p> Signup and view all the answers

    What is the purpose of a Stakeholder in a project?

    <p>To be affected by the project or its outcome</p> Signup and view all the answers

    What is the purpose of a Pareto Analysis?

    <p>To identify the vital few problems in a system</p> Signup and view all the answers

    What is the purpose of a Quality Circle?

    <p>To improve the effectiveness of work in a department</p> Signup and view all the answers

    What is the meaning of Slack in a project?

    <p>The amount of time a project activity can be delayed without delaying a succeeding activity</p> Signup and view all the answers

    What is the purpose of a Mind Map?

    <p>To generate and organize ideas</p> Signup and view all the answers

    What is the meaning of Resource Breakdown Structure (RBS)?

    <p>A hierarchical structure that identifies the project resources</p> Signup and view all the answers

    What is the purpose of a Performance Appraisal?

    <p>To evaluate the employee performance</p> Signup and view all the answers