Untitled
57 Questions
53 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which phase of the design and construction process involves determining the materials to be used for the structure?

  • Pre-construction phase
  • Pre-design phase
  • Design phase (correct)
  • Construction phase

What is a primary objective of the pre-design phase in the construction process?

  • Selection of the general contractor
  • Physical realization of the building
  • Setting objectives and criteria for planning (correct)
  • Determining the specific building materials to be used

Which activity is typically performed during the pre-construction phase?

  • Installing utility infrastructure (correct)
  • Determining the geometry of the structure
  • Initiating the title search
  • Completing the physical construction of the building

What aspect of a construction project is addressed during the pre-construction phase?

<p>Securing building permits (B)</p> Signup and view all the answers

Why is it important to designate space for construction waste materials during the pre-construction phase?

<p>To comply with environmental regulations (A)</p> Signup and view all the answers

Which of the following parties is responsible for initiating a construction project?

<p>Owner (A)</p> Signup and view all the answers

Which role primarily involves providing professional services to the main construction team, such as specialized expertise or advice?

<p>Consultant (C)</p> Signup and view all the answers

What is the primary task of a general contractor in a construction project?

<p>Completing the actual construction (A)</p> Signup and view all the answers

What is the purpose of testing labs and inspection agencies in a construction project?

<p>To provide quality control services (C)</p> Signup and view all the answers

What type of drawing represents a building as if a horizontal cut has been made through it, and the top portion removed?

<p>Floor plan (D)</p> Signup and view all the answers

In excavation, what is the primary function of steel tiebacks that are installed through the wall and into the soil?

<p>To provide structural support and stabilize the sides of the excavation. (B)</p> Signup and view all the answers

When is a cofferdam most appropriately used in construction projects?

<p>When needing a temporary, watertight enclosure in water-bearing soil or directly in water. (D)</p> Signup and view all the answers

What distinguishes a pneumatic caisson from an open caisson?

<p>Pneumatic caissons use pressurized air to keep water out, while open caissons are exposed to normal atmospheric pressure. (C)</p> Signup and view all the answers

Which of the following best describes the 'needle' method in underpinning?

<p>Inserting heavy timbers or steel beams horizontally through a building's wall to provide support. (C)</p> Signup and view all the answers

A construction project requires working below the water table in unstable soil. Which of the following methods would be most suitable for creating a dry working environment?

<p>A cofferdam (D)</p> Signup and view all the answers

Under what circumstances would it be most appropriate to employ underpinning techniques?

<p>When constructing a new building very close to an existing structure. (A)</p> Signup and view all the answers

What is the primary purpose of grouting in the context of soil anchors?

<p>To create a strong bond between the metal shaft and the surrounding soil. (C)</p> Signup and view all the answers

A project involves constructing a bridge pier in a river. The riverbed consists of a layer of permeable soil, followed by a layer of impervious rock with low bearing capacity, and finally solid bedrock. Which foundation method would be most suitable?

<p>Cofferdam extending to solid bedrock (A)</p> Signup and view all the answers

During a deep excavation project in an urban area, engineers opt for steel sheet piling with cross-lot bracings. What is the primary reason for choosing this method over tiebacks?

<p>Cross-lot bracings eliminate obstructions outside the immediate excavation zone, unlike tiebacks which extend into adjacent properties. (D)</p> Signup and view all the answers

A construction team is preparing to use tiebacks to secure sheet piling in a wide excavation. The soil report indicates the presence of loose sandy soil. Which tieback installation method is most suitable for this condition?

<p>Installing a screw anchor with rotary drilling equipment. (A)</p> Signup and view all the answers

In the slurry wall construction process, what is the primary purpose of using a bentonite clay and water slurry during the excavation phase?

<p>To stabilize the walls of the excavation, preventing collapse before the concrete is poured. (A)</p> Signup and view all the answers

During the installation of tiebacks in firm soil, hydraulic jacks are used. What is the main function of these jacks in the tieback process?

<p>To tighten the cable and apply tension, securing the sheeting. (A)</p> Signup and view all the answers

A construction project requires a deep excavation where the support system will eventually become part of the permanent foundation. Which of the following methods is most suitable?

<p>Slurry wall using cast-in-place concrete (B)</p> Signup and view all the answers

When is it most appropriate to use 'steel sheet piling with interlocking steel sheets' as a soil support method?

<p>When needing to support soils from caving in. (C)</p> Signup and view all the answers

What advantage do screw anchors offer over traditional grouted tiebacks in loose soil conditions?

<p>Installation is quicker and they can be withdrawn and reused. (A)</p> Signup and view all the answers

In a slurry wall construction, after the welded cage of steel reinforcing is lowered into the cavity and concrete is poured, what happens to the slurry?

<p>The slurry is displaced by the concrete and pumped out. (A)</p> Signup and view all the answers

An engineer is designing a concrete pavement and needs to optimize load distribution. Which layer primarily contributes to distributing the load in a flexible pavement system?

<p>Sub-base course (C)</p> Signup and view all the answers

A construction project requires choosing between flexible and rigid pavement. Which characteristic is most indicative of a rigid pavement's performance?

<p>Thick, reinforced concrete paving (D)</p> Signup and view all the answers

When designing a building's foundation, which element represents the portion of the structure primarily responsible for directly supporting service loads above ground?

<p>Superstructure (C)</p> Signup and view all the answers

An engineer is tasked with selecting a suitable foundation for a high-rise building on a site with weak surface soils. Which foundation type would be most appropriate?

<p>Deep pile foundation (D)</p> Signup and view all the answers

A bridge pier needs to be designed to transfer its heavy load directly onto the bedrock below. Which type of foundation is best suited for this?

<p>Drilled pile foundation (A)</p> Signup and view all the answers

When choosing a foundation system, which factor related to the surrounding environment is most critical to consider to prevent structural damage?

<p>Frost line depth (A)</p> Signup and view all the answers

An engineer is weighing design options for a foundation in an area with expansive clay soils. Which foundation design consideration is most crucial to minimize potential damage from soil movement?

<p>Extending the foundation below the active zone of the expansive soil (B)</p> Signup and view all the answers

A geotechnical report indicates a high water table and the presence of organic matter in the subsurface soil. Which foundation system is least suitable under these conditions without extensive ground improvement?

<p>Shallow spread footing (B)</p> Signup and view all the answers

Which drawing provides specific instructions for fabricating structural steelwork for a building project?

<p>Shop drawing (B)</p> Signup and view all the answers

What is a primary purpose of conducting a site assessment before construction begins?

<p>To ensure an efficient design and construction process. (D)</p> Signup and view all the answers

A site plan typically includes which of the following details?

<p>Locations of underground utilities and fire hydrants. (D)</p> Signup and view all the answers

Which of the following site work activities is most directly related to preparing a waterfront property for building construction?

<p>Dredging. (A)</p> Signup and view all the answers

During site work, what is the best practice for managing topsoil?

<p>Stockpiling and protecting it for reuse. (D)</p> Signup and view all the answers

A civil engineer is tasked with minimizing erosion on a construction site. Which strategy aligns with this goal?

<p>Implementing temporary seeding and mulch barriers. (C)</p> Signup and view all the answers

Why is storm-water drainage considered essential during and after construction?

<p>To prevent water from entering basements or pooling on surfaces. (C)</p> Signup and view all the answers

Which activity is included in site clearing?

<p>Removing trees and other vegetation. (A)</p> Signup and view all the answers

What does site remediation primarily aim to achieve?

<p>Removing toxic substances and restoring natural habitats. (B)</p> Signup and view all the answers

Which of the following is the MOST accurate description of earthwork?

<p>Soil excavation, transportation, and relocation. (B)</p> Signup and view all the answers

Which of the following actions is considered grading?

<p>Changing the landform of a site using heavy equipment. (C)</p> Signup and view all the answers

What is the purpose of 'cut and fill' in construction?

<p>To balance the amount of soil removed and added to a site. (C)</p> Signup and view all the answers

During excavation, when is a sloped excavation side typically used?

<p>For shallow excavations on a large site. (C)</p> Signup and view all the answers

What is the primary function of a subsurface drainage system?

<p>To remove water from a development area using drainpipes. (B)</p> Signup and view all the answers

What is the main goal of establishing erosion control measures on a construction site?

<p>To control erosion and sedimentation problems. (B)</p> Signup and view all the answers

Which of the following foundation types is most suitable when the soil has a low bearing capacity or varies significantly across the building's footprint?

<p>Mat/Raft Foundation (C)</p> Signup and view all the answers

A building's design requires a foundation that supports two columns positioned close to each other. Which type of footing is most appropriate?

<p>Combined Footing (C)</p> Signup and view all the answers

In the construction of a slab on grade, what is the purpose of laying a bed of compacted fill gravel?

<p>To act as a capillary break and provide a solid, well-drained base. (A)</p> Signup and view all the answers

A column is situated very close to a property line. Which type of footing would be most appropriate to prevent the footing from extending onto the neighboring property?

<p>Combined Footing (C)</p> Signup and view all the answers

During the construction of a slab on grade, what is the typical order of placement for the following elements after the ground is compacted? i) Reinforcing bars or steel mesh ii) Moisture barrier iii) Compacted fill gravel iv) Formwork

<p>iv, iii, ii, i (B)</p> Signup and view all the answers

When should a mat or raft foundation be considered over individual spread footings for a building?

<p>When the spread footings would cover more than 50% of the building footprint area. (C)</p> Signup and view all the answers

What is the primary reason for pouring a mat foundation monolithically and continuously?

<p>To avoid construction joints that could weaken the slab. (C)</p> Signup and view all the answers

What is the minimum recommended thickness for a slab on grade in typical construction applications?

<p>4 inches (B)</p> Signup and view all the answers

Flashcards

Pre-Design Phase

Setting objectives & criteria for planning.

Design Phase

Determining geometry, materials, and performance of structure.

Pre-Construction Phase

Selection of project participants & outlining contractual agreements.

Construction Phase

Physical realization of a finished building.

Signup and view all the flashcards

Pre-Design Phase Start

Finding the design firm and feasibility studies.

Signup and view all the flashcards

Pre-Construction Activities

Activities like securing permits and site prep.

Signup and view all the flashcards

More Pre-Construction

Activities like dewatering and shoring.

Signup and view all the flashcards

Final Pre-Construction steps

Arranging deliveries, storage, and pre-con meetings.

Signup and view all the flashcards

Owner

Initiates project

Signup and view all the flashcards

Architects and engineers

Design the building

Signup and view all the flashcards

What is Pavement?

A surfacing type for vehicular or pedestrian traffic.

Signup and view all the flashcards

Flexible Pavement Layers

Compacted subgrade, sub-base course, base course, and wearing surface.

Signup and view all the flashcards

Rigid Pavement Layers

Compacted subgrade, base course, concrete paving, and wearing surface.

Signup and view all the flashcards

Major Building Elements

Superstructure, substructure, and foundation.

Signup and view all the flashcards

What is a Superstructure?

The portion of a building above the ground that directly supports service loads.

Signup and view all the flashcards

What is a Substructure?

The enclosed portion of a building below grade that supports the superstructure.

Signup and view all the flashcards

Foundation Load Transfer

Spread foundations, driven pile foundations, and drilled pile foundations.

Signup and view all the flashcards

Foundation Depth Factors

Placed below the frost line to prevent heaving due to freeze-thaw cycles.

Signup and view all the flashcards

Tiebacks

Steel rods inserted through a wall into the soil to stabilize excavations.

Signup and view all the flashcards

Soil Anchor

Metal shafts grouted into soil to stabilize excavation sides.

Signup and view all the flashcards

Cofferdam

Temporary watertight enclosure to keep water out of construction area.

Signup and view all the flashcards

Caisson

Watertight shell for construction below water level.

Signup and view all the flashcards

Open Caisson

Caisson open to the atmosphere. Work occurs under normal air pressure.

Signup and view all the flashcards

Pneumatic Caisson

Air and watertight caisson, pressurized to keep water out during excavation.

Signup and view all the flashcards

Underpinning

Supporting an existing building's foundation during nearby construction.

Signup and view all the flashcards

Needles (Underpinning)

Heavy timbers or steel beams supporting a wall horizontally.

Signup and view all the flashcards

Sheeting

Supports soil from caving in using sheet piling, lagging, and slurry walls.

Signup and view all the flashcards

Steel Sheet Piling

Steel sheets interlocked and driven into the earth before excavation.

Signup and view all the flashcards

Cross-Lot Bracings

Horizontal supports in wide excavations; transfer forces to footings.

Signup and view all the flashcards

Rakers

Angled supports that transfer forces to a footing set in the excavation's bottom.

Signup and view all the flashcards

Tieback (Firm Soil/Rock)

Steel cable inserted into a drilled hole, grouted, and tightened to secure sheeting.

Signup and view all the flashcards

Tieback (Loose Soil)

Screw anchor installed with drilling; good for loose sandy & clay soils.

Signup and view all the flashcards

Slurry Wall

Protects the excavated area; becomes part of the permanent foundation using cast-in-place concrete.

Signup and view all the flashcards

Spread Footing

Enlarged base of a stem (column) that transmits building loads to the soil.

Signup and view all the flashcards

Strip Footing

Enlarged base of a stem wall continuous around the perimeter of a structure.

Signup and view all the flashcards

Combined Footing

A spread footing that supports two or more columns close to each other.

Signup and view all the flashcards

Slab on Grade

Reinforced concrete slab placed directly on the ground for structural support.

Signup and view all the flashcards

Slab on Grade Construction Steps

Compacted ground, formwork, gravel bed, moisture barrier, insulation (optional), rebar/mesh, utilities, concrete pour.

Signup and view all the flashcards

Mat/Raft Foundation

Thick RC slabs covering the entire building footprint, evenly spreading weight.

Signup and view all the flashcards

When to Use Mat Foundation

Used when soil has low bearing capacity or varies across the area.

Signup and view all the flashcards

Combined Footing Purpose

Footings that support walls/columns near the property line.

Signup and view all the flashcards

Building Section

A view of a building after a vertical plane has been cut through it, removing the front portion.

Signup and view all the flashcards

Elevation

View of the exterior façade of a building, showing geometries and materials.

Signup and view all the flashcards

Shop Drawings

Detailed instructions for fabricating specific components (e.g., steelwork).

Signup and view all the flashcards

Site Assessment

Assessment performed before construction to ensure efficient design and construction.

Signup and view all the flashcards

Site Plan

A detailed drawing of the proposed site development project.

Signup and view all the flashcards

Site Work Activities

Activities including erosion control, demolition, earthwork, and foundations.

Signup and view all the flashcards

Sedimentation and Erosion Control

Methods to control dirt and contaminants leaving a construction site via storm water.

Signup and view all the flashcards

Storm-Water Drainage

Removal of water from a development area during and after construction.

Signup and view all the flashcards

Demolition

Breakdown and removal of existing structures and hazardous materials.

Signup and view all the flashcards

Site Remediation

Activities that benefit the building site in the long term, e.g. removing toxic substances.

Signup and view all the flashcards

Earthwork

Soil excavation, transportation, and relocation.

Signup and view all the flashcards

Grading

Changing the landform of a site using heavy equipment.

Signup and view all the flashcards

Cutting

Removing soil from a slope to increase the area for building construction.

Signup and view all the flashcards

Filling

Soil is imported to fill lower levels to increase area available

Signup and view all the flashcards

Grubbing

Removal of subsurface obstructions (roots, stumps, etc).

Signup and view all the flashcards

Study Notes

  • Design and construction have four phases: pre-design, design, pre-construction, and construction.

Pre-Design Phase

  • Setting objectives and planning criteria is key
  • Begins after the owner identifies the design firm or consultants
  • A feasibility study might be completed
  • The owner & consultant decide the goals & objectives
  • Identifying needs and constraints is part of the process
  • Includes title search and zoning analysis, site search & selection, financial planning, scheduling, and programming

Design Phase

  • Geometry, materials, and performance of structure are determined

Pre-Construction Phase

  • Involves selecting project participants and outlining contractual agreements
  • Activities involve getting building permits, selecting project participants, and signing agreements
  • GC establishes a field office, does subsurface investigation, also site preparation
  • Dewatering, shoring, underpinning and earthwork is part of the process
  • Installing utility infrastructure; site improvements like access roads and walks are included
  • Arrange access for deliveries and equipment
  • Designate space to storage and staging of materials
  • Designate space to sorting and storage of construction waste materials
  • A pre-construction conference should be arranged that includes the owner, general contractor (GC), construction manager, and subcontractors

Construction Phase

  • A finished building is physically constructed

Construction Industry Divisions

  • Building construction includes residential, commercial, civic, educational, religious, and agricultural projects
  • Heavy construction includes highways, bridges, canals, dams, subways, tunnels, utility piping, water control, and communication projects
  • Industrial construction involves buildings for large scale manufacturing & processing plants or utility generation installation

Main Players

  • Owner- Initiates project
  • Architect and engineers- Design the building
  • General contractor- Completes actual construction

Support Players

  • Consultants: offer professional services to the main team
  • Subcontractors perform portions of work under GC
  • Product representative assists with submittals and furnishes field services
  • Manufacturers produce materials or products
  • Testing labs & inspection agencies offer quality control services

Orthographic Drawings

  • Floor plan: Image of a building, looked down upon after an imaginary horizontal cut, footprint
  • Building section: View of a building after a vertical plane has been cut through it
  • Elevation: View of the exterior facade, delineating geometries and material

Shop Drawings

  • Give precise directions for certain components, suich as steelwork and concrete

Site Assessment

  • Site assessment performed before the start of construction
  • Ensures efficient design and construction
  • Involves land and topographic surveys, subsurface soil testing, and environmental studies

Site Plan

  • A detailed drawing of a planned site development
  • Prepared by licensed architect, engineer, or surveyor
  • Illustrates locations, dimensions, floor elevations of structures
  • Site entrance & exits, drives, fire & service lanes are listed
  • Shows parking & loading areas and pedestrian walkways
  • Displays existing & proposed underground & overhead utilities, grades
  • Marks locations of public or private site lighting and fire hydrant
  • Displays existing contours & proposed changes to help verify drainage

Site Work Activities

  • Includes many activities such as: erosion control, demolition, earthwork, and site remediation
  • Addresses foundations with spread footings, piles, and caissons
  • Can address wet enviroments that require dredging, underwater work, & constructing seawalls, jetties, docks
  • Requires setting uo Utility trenches for water, sewer, gas, oil, steam distribution
  • Involves construction of ponds, drainage reservoirs and sewage lagoons
  • Requires putting in of Walks, fences, irrigation systems, & landscaping

Site Work Considerations

  • Conservation of natural features
  • Preventing the escape of pollutants
  • Restoration of damaged areas
  • Containing site disturbances
  • Protecting & restoring existing vegetation
  • Properly stockpiling and protecting stripped topsoil for reuse
  • Prohibit the discharge of toxic waste materials
  • Acknowledge of flood zones

Sedimentation and Erosion Control

  • Storm water transports dirt & contaminants from construction site
  • Erosion & sedimentation problems should be controlled
  • Civil engineer identifies areas prone to erosion & suggests strategies for soil stabilization
  • Utilize temporary erosion and sedimentation control measures like temporary seeding, mulch barriers, earth berms, silt fencing and sediment traps
  • Permanent plantings, fast-growing grasses
  • Placement of earthen swales (depression) to divert runoff water into temporary sediment basins

Stormwater Drainage

  • Remov water from a development
  • Important to do both during and after construction
  • Prevents water damage to basements and surfaces
  • A topographic map should be used
  • Surface drainage systems can include ditches, swales, detention basins
  • Subsurface drainage can use drainpipes (concrete, PVC) leading to storm-water system

Demolition

  • Breakdown & removal of existing structures
  • Includes buildings, roadways, parking areas, and submerged tanks, utility lines
  • Involves removal of hazardous materials (asbestos)
  • Site clearing is removal of trees and other vegetations
  • Grubbing is removal of subsurface obstructions (roots, stumps, etc.)

Site Remediation

  • Involves activities that benefit the building site in the long-term
  • Generating productive soils
  • Restoring natural habitats
  • Removing toxic substances
  • Preventing erosion

Earthwork

  • Relates to soil excavation, transportation, and relocation
  • Activities include: grading & excavating, backfilling & compacting, laying base courses
  • Stabilizing the soil, setting up slope protection, and establishing erosion control

Grading

  • Changing the landform of a site using heavy equipment
  • Leveling the area for building/structures
  • Creating movement paths
  • Establishing drainage and landscape features
  • Rough grading levels the ground for excavation and building
  • Some equipment to use is grader, front-end loader and backhoe
  • Topsoil should be preserved
  • A level plane can be accomplished by cutting (removing soil), filling (importing), or cut and fill (balances)

Excavation

  • Excavation depth depends on the type of soil
  • A sloped side can be used for shallow work
  • Bench system can be used for a deep excavation

Sheeting

  • A method of supporting soils from caving in
  • Done in the form of sheet piling, lagging, and slurry walls
  • Sheet pile may be wood, aluminum, steel, vinyl, or precast concrete placed vertically into the ground
  • Vertical steel columns (soldier piles) driven into the soil and horizontal wood lagging, it contains excavations.
  • Steel sheet piling uses interlocking steel sheets are driven or vibrated into the earth before excavation
  • Uses cross-lot bracings which are supported steel posts

Tiebacks

  • Secures sheet pile on a wide construction site to avoid obstructions
  • Option 1 - on a firm soil/rock: a steel cable is inserted, the hole is filled, the cable is tightened
  • Option 2 - on a loose soil: usea a screw anchor

Slurry Wall

  • A cast-in-place concrete method protects, becomes foundation
  • Excavation is dug with a clamshell bucket, filled with slurry of bentonite clay & water
  • Welded steel is lowered into the cavity, concrete is poured and excavation can begin

Soil Anchor

  • Metal grouted shafts stabilize excavation sides
  • Drill holes, fill the hole with grout
  • Push reinforced steel bar

Cofferdam

  • Temporary watertight enclosures for use in water or water-bearing soil
  • Prevents water from construction
  • Using sheet piling or a double-wall structure extend down to bedrock

Caisson

  • A watertight shell for carrying out construction below water level
  • May be open or pneumatic
  • Open caisson is exposed to the weather, work is performed under pressure
  • Pneumatic caisson is air and watertight
  • To keep excavation clear and free of water, the process requires pressurized air

Underpinning

  • Supports existing building when construction happens nearby
  • The use of trenches occurs at intervals and filled to support
  • Needles are heavy wooden timbers or steel beams, spacing is a factor

Paving

  • Surfacing for vehicular or pedestrian traffic use
  • Common materials: Portland, asphalt concrete, stabilized soil and gravel
  • Flexible Layers uses Compacted subgrade, provides additional support
  • Includes high quality materials with bitumen for base and wearing surface
  • Rigid layers are compated and have reinforced concrete

Building Elements

  • Superstructure above the ground
  • Substructure below grade
  • Foundation supports

Foundation Classification

  • Shallow is pad or strip footing
  • Deep uses piles and shafts
  • Load transfer happens via spreading
  • Loads bearing can be transfered via driven or drilled pile foundation

Foundation Choice

  • Dependent on Type and size of the building
  • Also includes soil and subsurface water conditions
  • Based on Building code requirements
  • Placed below frost line to prevent freeze-thaw
  • Spread footing transmits loads to the soil
  • Strip footing is around the perimeter
  • A Combined footing shares columns for support

Slab Grade

  • Reinforced concrete slab placed directly on the ground for support with thick edes
  • Minimum of 4 inches
  • Constructed as an extension of a stem wall
  • Construction involves compacting the ground and applying a gravel bed
  • Reinforce with steel or mesh

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Untitled
44 questions

Untitled

ExaltingAndradite avatar
ExaltingAndradite
Untitled
6 questions

Untitled

StrikingParadise avatar
StrikingParadise
Untitled Quiz
18 questions

Untitled Quiz

RighteousIguana avatar
RighteousIguana
Untitled Quiz
50 questions

Untitled Quiz

JoyousSulfur avatar
JoyousSulfur
Use Quizgecko on...
Browser
Browser