Questions and Answers
What is the primary purpose of the Postqualification of Contractor process?
What is the primary purpose of the Postqualification of Contractor process?
- To evaluate the contractor's eligibility and qualifications (correct)
- To prepare and submit bids and bid bonds
- To determine the lowest calculated responsive bid
- To award the contract to the winning bidder
What is the next step after the opening of bids/tenders?
What is the next step after the opening of bids/tenders?
- Submission of bids
- Abstracting of bids
- Determination of the lowest calculated responsive bid (correct)
- Awarding of the contract
What is the purpose of the Submission, Opening and Abstracting of Bids/Tenders stage?
What is the purpose of the Submission, Opening and Abstracting of Bids/Tenders stage?
- To prepare and submit bids and bid bonds
- To negotiate the contract terms
- To evaluate the bids and select the winner
- To receive and record bids from contractors (correct)
What is the focus of the Detailed Evaluation of Bids stage?
What is the focus of the Detailed Evaluation of Bids stage?
What is the By Negotiated Contract method used for?
What is the By Negotiated Contract method used for?
What is the purpose of the Supporting Documents stage?
What is the purpose of the Supporting Documents stage?
What is the focus of the Contract Implementation stage?
What is the focus of the Contract Implementation stage?
What is the purpose of the Variation Orders/Change Order/Extra Work Order/Supplemental Agreement?
What is the purpose of the Variation Orders/Change Order/Extra Work Order/Supplemental Agreement?
Where should the advertisement for bidding be posted?
Where should the advertisement for bidding be posted?
What is the minimum number of contractors required to participate in the bidding?
What is the minimum number of contractors required to participate in the bidding?
When can the advertisement be made in a newspaper of general nationwide circulation?
When can the advertisement be made in a newspaper of general nationwide circulation?
How are contractors invited for foreign-financed/assisted contracts?
How are contractors invited for foreign-financed/assisted contracts?
What information should the notice for prequalification/eligibility screening contain?
What information should the notice for prequalification/eligibility screening contain?
What is the purpose of the notice for prequalification/eligibility screening?
What is the purpose of the notice for prequalification/eligibility screening?
Who provides the notice for prequalification/eligibility screening?
Who provides the notice for prequalification/eligibility screening?
What is the primary responsibility of the Bid and Award Committee (BAC) in an office/agency/corporation?
What is the primary responsibility of the Bid and Award Committee (BAC) in an office/agency/corporation?
Who is the administrative officer of the agency concerned in relation to the BAC?
Who is the administrative officer of the agency concerned in relation to the BAC?
What type of contracts may require direct invitation of contractors?
What type of contracts may require direct invitation of contractors?
What is the minimum ranking of the Chairman of the BAC in the office/agency/corporation?
What is the minimum ranking of the Chairman of the BAC in the office/agency/corporation?
How many provisional members are designated by the head of office/agency/corporation for the BAC?
How many provisional members are designated by the head of office/agency/corporation for the BAC?
Who designates the technical member of the BAC?
Who designates the technical member of the BAC?
What is the requirement for the provisional members of the BAC?
What is the requirement for the provisional members of the BAC?
What is the purpose of the checklist of required documents in the bidding process?
What is the purpose of the checklist of required documents in the bidding process?
What is the minimum amount of the cash deposit certificate or credit line that the contractor's bank must extend to the contractor?
What is the minimum amount of the cash deposit certificate or credit line that the contractor's bank must extend to the contractor?
What document is required to be submitted by the contractor to ensure compliance with the Occupational Safety and Health Standards?
What document is required to be submitted by the contractor to ensure compliance with the Occupational Safety and Health Standards?
What happens if a contractor's first envelope is missing one or more of the required documents?
What happens if a contractor's first envelope is missing one or more of the required documents?
What is the purpose of the first envelope in the bidding process?
What is the purpose of the first envelope in the bidding process?
What is the minimum amount of time that the contractor's bank must extend a credit line to the contractor?
What is the minimum amount of time that the contractor's bank must extend a credit line to the contractor?
What is the purpose of the second envelope in the bidding process?
What is the purpose of the second envelope in the bidding process?
What is the consequence of a contractor's failure to comply with the Occupational Safety and Health Standards?
What is the consequence of a contractor's failure to comply with the Occupational Safety and Health Standards?
What is the minimum percentage of the approved budget for the contract under bidding that the contractor's single largest managed/supervised contract similar to the contract under bidding must be equal to?
What is the minimum percentage of the approved budget for the contract under bidding that the contractor's single largest managed/supervised contract similar to the contract under bidding must be equal to?
Who verifies the experience of the contractor's key personnel?
Who verifies the experience of the contractor's key personnel?
What is the purpose of the BAC or designated procurement unit's inquiry with the contractor's previous employers and clients?
What is the purpose of the BAC or designated procurement unit's inquiry with the contractor's previous employers and clients?
What is the requirement for the equipment units listed by the contractor?
What is the requirement for the equipment units listed by the contractor?
What authority does the BAC or designated procurement unit have regarding the equipment units?
What authority does the BAC or designated procurement unit have regarding the equipment units?
Why does the BAC or designated procurement unit check the contractor's performance in ongoing government and private contracts?
Why does the BAC or designated procurement unit check the contractor's performance in ongoing government and private contracts?
What is the purpose of the documented proofs of ownership and/or lease and/or purchase agreements?
What is the purpose of the documented proofs of ownership and/or lease and/or purchase agreements?
What is the requirement for the number and capacities of the equipment units?
What is the requirement for the number and capacities of the equipment units?
Flashcards are hidden until you start studying
Study Notes
Bid and Award Committee (BAC)
- The BAC or designated procurement unit is responsible for the conduct of prequalification, bidding, evaluation of bids, postqualification, and recommending award of contracts.
- The committee is composed of:
- A chairman (at least third-ranking official of the office/agency/corporation)
- An executive officer and secretary (legal officer of the office/agency/corporation or administrative officer)
- A regular technical member designated by the head of office/agency/corporation
- At least two provisional members with experience in the type of contract to be bid and in project management, designated by the head of office/agency/corporation on a project-to-project basis
Advertisement and Invitation
- The advertisement shall be posted in the newspaper, website, and premises of the office/agency/corporation concerned.
- The invitation may also be advertised through other forms of media such as radio and television.
- In cases of contracts requiring special technology, direct invitation of contractors known for their capacity to undertake such type of contracts may be made.
- For foreign-financed/assisted contracts, contractors are invited under the same procedures and/or in accordance with procedures established by, and agreed upon with, the lending/financing institution.
Issuance of Qualification Statements/Forms
- The BAC or designated procurement unit shall provide prospective bidders with the notice for prequalification/eligibility screening, which includes:
- Name and location of project
- Equipment utilization schedule
- Certificate of site inspection
- Bid security
- Certification that the Detailed Estimates, Cash Flow by Quarter, and Payments Schedule are in the second envelope
- Commitment from the contractor's bank to extend a credit line if awarded the contract to be bid
- Construction Safety and Health Program
- Other non-discretionary criteria as stated in the instructions to bidders
Contents of First Envelope
- The first envelope shall contain:
- Notice for prequalification/eligibility screening
- Equipment utilization schedule
- Certificate of site inspection
- Bid security
- Certification that the Detailed Estimates, Cash Flow by Quarter, and Payments Schedule are in the second envelope
- Commitment from the contractor's bank to extend a credit line if awarded the contract to be bid
- Construction Safety and Health Program
- Other non-discretionary criteria as stated in the instructions to bidders
Contents of Second Envelope
- The second envelope shall contain:
- Bid prices in the bill of quantities
- Experience of the contractor's key personnel
- Equipment units listed by the contractor
Verification and Evaluation
- The BAC or designated procurement unit shall verify the experience of the contractor's key personnel and equipment units listed.
- The BAC or designated procurement unit shall make appropriate inquiries with the personnel's previous employers and clients and conduct checks on their past contracts.
- The BAC or designated procurement unit shall have the authority to undertake an actual physical inspection of the equipment units and make appropriate inquiries and checks with the equipment lessors and suppliers concerned.