Questions and Answers

What is the purpose of a work breakdown structure (WBS)?

  • Detailing all the tasks that must be performed (correct)
  • Listing the major contributors to a project
  • Identifying stakeholders in a project
  • Creating schedules for project tasks
  • Why is it recommended to keep a project plan in a loose-leaf notebook with electronic backup?

  • To decrease the chances of stakeholders scrutinizing the plan
  • To ensure the plan is always available in both physical and digital formats (correct)
  • To complicate the plan review process
  • To prevent stakeholders from accessing it easily
  • Who should sign off on a project plan?

  • Only managers
  • Only financial people
  • Anyone who contributed to the plan (correct)
  • A cranky bunch of stakeholders
  • What does a signature on a project plan imply?

    <p>The signer agrees with scope of work and accepts valid specifications</p> Signup and view all the answers

    When should changes be made to a project plan?

    <p>Only if a significant deviation occurs</p> Signup and view all the answers

    What should be done to avoid scope creep in a project?

    <p>Avoid changes that result in additional work for the project</p> Signup and view all the answers

    What is a key barrier to good planning according to the text?

    <p>Prevailing paradigm</p> Signup and view all the answers

    What does control in the planning sense involve?

    <p>Comparing actual progress to planned progress</p> Signup and view all the answers

    Which of the following is considered an ingredient to make a good plan?

    <p>Project mission statement</p> Signup and view all the answers

    What is the importance of having exit criteria with milestones in project planning?

    <p>To ensure project progress is on track</p> Signup and view all the answers

    In project planning, what does the term 'logistics' refer to?

    <p>Arranging for people to have necessary resources</p> Signup and view all the answers

    What role does strategy play in planning a project properly?

    <p>It dictates how tactics are executed</p> Signup and view all the answers

    What is the first step in the basis project planning steps outlined in the text?

    <p>Define the problem</p> Signup and view all the answers

    What is a key aspect of effective planning to anticipate unexpected obstacles?

    <p>Conducting a risk analysis</p> Signup and view all the answers

    What is one way to avoid over analyzing risks during the planning process?

    <p>Identify every possible risk</p> Signup and view all the answers

    Why is it important to involve the people who will implement the plan in its preparation?

    <p>To ensure buy-in and commitment to the plan</p> Signup and view all the answers

    What should be done after preparing a master schedule and budget in project planning, according to the text?

    <p>Get the plan signed off by all project stakeholders</p> Signup and view all the answers

    Why should the planning session itself be time-limited according to the text?

    <p>To keep people on track</p> Signup and view all the answers