Podcast
Questions and Answers
What does the Cost Performance Index (CPI) indicate if it is less than 1?
What does the Cost Performance Index (CPI) indicate if it is less than 1?
What is the formula to calculate the Schedule Performance Index (SPI)?
What is the formula to calculate the Schedule Performance Index (SPI)?
What is the purpose of Earned Value Analysis (EVA)?
What is the purpose of Earned Value Analysis (EVA)?
What is the formula to calculate the Cost Performance Index (CPI)?
What is the formula to calculate the Cost Performance Index (CPI)?
Signup and view all the answers
What does Estimation at Completion (EAC) predict?
What does Estimation at Completion (EAC) predict?
Signup and view all the answers
What is the purpose of forecasting techniques in project management?
What is the purpose of forecasting techniques in project management?
Signup and view all the answers
What is the formula for Case #3 of Estimation at Completion (EAC)?
What is the formula for Case #3 of Estimation at Completion (EAC)?
Signup and view all the answers
What is the purpose of the Schedule Performance Index (SPI)?
What is the purpose of the Schedule Performance Index (SPI)?
Signup and view all the answers
What is the Earned Value (EV) of the project?
What is the Earned Value (EV) of the project?
Signup and view all the answers
What does a Cost Variance (CV) of -20,000 indicate?
What does a Cost Variance (CV) of -20,000 indicate?
Signup and view all the answers
What is the formula to calculate Schedule Variance (SV)?
What is the formula to calculate Schedule Variance (SV)?
Signup and view all the answers
What does a Schedule Variance (SV) of -10,000 indicate?
What does a Schedule Variance (SV) of -10,000 indicate?
Signup and view all the answers
What is the purpose of Cost Performance Index (CPI)?
What is the purpose of Cost Performance Index (CPI)?
Signup and view all the answers
How is the Earned Value (EV) calculated?
How is the Earned Value (EV) calculated?
Signup and view all the answers
What is the purpose of Variance Analysis?
What is the purpose of Variance Analysis?
Signup and view all the answers
What is the Planned Value (PV) of the project at the 6th month?
What is the Planned Value (PV) of the project at the 6th month?
Signup and view all the answers
What is the purpose of Earned Value Analysis in project management?
What is the purpose of Earned Value Analysis in project management?
Signup and view all the answers
What is the formula to calculate Planned Value (PV)?
What is the formula to calculate Planned Value (PV)?
Signup and view all the answers
What is the Actual Cost (AC) of the project in the given scenario?
What is the Actual Cost (AC) of the project in the given scenario?
Signup and view all the answers
What is the Earned Value (EV) of the project if 40% of the work has been completed and the project's budget is 100,000.00?
What is the Earned Value (EV) of the project if 40% of the work has been completed and the project's budget is 100,000.00?
Signup and view all the answers
What is the purpose of the Schedule Performance Index (SPI) in Earned Value Analysis?
What is the purpose of the Schedule Performance Index (SPI) in Earned Value Analysis?
Signup and view all the answers
What is the purpose of the Cost Performance Index (CPI) in Earned Value Analysis?
What is the purpose of the Cost Performance Index (CPI) in Earned Value Analysis?
Signup and view all the answers
What is the result of a variance analysis if the project's Earned Value (EV) is greater than its Planned Value (PV)?
What is the result of a variance analysis if the project's Earned Value (EV) is greater than its Planned Value (PV)?
Signup and view all the answers
What is the project's Planned Value (PV) after 9 months if the project's budget is 100,000.00 and the project is 75% complete?
What is the project's Planned Value (PV) after 9 months if the project's budget is 100,000.00 and the project is 75% complete?
Signup and view all the answers
Study Notes
Earned Value (EV) Management
- EV allows project managers to assess the value achieved relative to the planned value, helping to determine if the project is ahead or behind schedule.
Planned Value (PV)
- PV is the budgeted cost of work scheduled (BCWS).
- PV = BAC × % complete (planned).
- Example: Project duration: 12 months, Project budget (BAC): 100,000.00, Elapsed time: 9 months, % complete (planned): 75%, PV = 100,000.00 × 75% = 75,000.00.
Actual Cost (AC)
- AC is the total cost incurred by the project.
- Example: Elapsed time: 6 months, Actual cost: 60,000.00, AC = 60,000.00.
Earned Value (EV)
- EV is the value of the work completed.
- EV = % complete × BAC.
- Example: Elapsed time: 6 months, % complete: 40%, EV = 40% × 100,000.00 = 40,000.00.
Variance Analysis
- Cost Variance (CV): measures the difference between the earned value and actual cost.
- CV = EV - AC.
- Example: CV = 40,000.00 - 60,000.00 = -20,000.00, CV < 0 indicates over budget.
Performance Indexes
-
Cost Performance Index (CPI): measures the cost efficiency of the project.
-
CPI = EV / AC.
-
Example: CPI = 40,000.00 / 60,000.00 = 0.667, CPI < 1 indicates over budget.
-
Schedule Performance Index (SPI): measures the schedule efficiency of the project.
-
SPI = EV / PV.
-
Example: SPI = 40,000.00 / 50,000.00 = 0.8, SPI < 1 indicates behind schedule.
Forecasting Techniques
- Estimation at Completion (EAC): predicts the total cost of a project once it's finished.
- Case #1: EAC = BAC / CPI.
- Case #2: EAC = AC + (BAC – EV).
- Case #3: EAC = AC + [(BAC – EV) / (CPI * SPI)].
Note: These notes are a summary of the key concepts and formulas related to Earned Value Management, Variance Analysis, Performance Indexes, and Forecasting Techniques.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Assess project progress with Earned Value Management. Learn to calculate Planned Value (PV) and determine if the project is on track. Useful for project managers and planners.