Podcast
Questions and Answers
For any proposed bridge site, the topographic and river surveys should be extended from the centerline of the bridge at least:
For any proposed bridge site, the topographic and river surveys should be extended from the centerline of the bridge at least:
What is the simplest type of superstructure of a concrete bridge with a limited span of 8 meters?
What is the simplest type of superstructure of a concrete bridge with a limited span of 8 meters?
Which of these is not classified as a type of caisson foundation?
Which of these is not classified as a type of caisson foundation?
Which of the following documents is not necessary at the project site?
Which of the following documents is not necessary at the project site?
Signup and view all the answers
An asphalt cement can be a good bituminous binder material for item:
An asphalt cement can be a good bituminous binder material for item:
Signup and view all the answers
The following reasons may cause the granting of contract time extension with the exception of one:
The following reasons may cause the granting of contract time extension with the exception of one:
Signup and view all the answers
What is the allowable variance from the original unit price, so that a contract will be entitled to contract price escalation?
What is the allowable variance from the original unit price, so that a contract will be entitled to contract price escalation?
Signup and view all the answers
The government may rescind the contract work if there is:
The government may rescind the contract work if there is:
Signup and view all the answers
From the time of project was bid to the issuance of notice to proceed, how many calendar days is required for a project to be entitled to contract price adjustment?
From the time of project was bid to the issuance of notice to proceed, how many calendar days is required for a project to be entitled to contract price adjustment?
Signup and view all the answers
Under which of the following conditions must a change order not to be issued?
Under which of the following conditions must a change order not to be issued?
Signup and view all the answers
Study Notes
DPWH Accreditation Overview
- The accreditation focuses on contractors' and consultants' project engineers in the context of DPWH (Department of Public Works and Highways) within the Philippines.
- The material is rooted in the 2020 edition, which includes updated policies and practices relevant to project engineering.
Suggested Reference E-Books for PE Exam
- DGCS Vol. I to VI: Comprehensive guidelines on construction practices.
- Accessibility Law (BP 344): Regulations ensuring accessibility in construction.
- Simplified Construction Handbook: A practical guide for streamlined construction processes.
- Blue Book Vol. II (2013) and Vol. III (1995): Reference volumes detailing construction methodologies.
- Methodology Books: Include specific guides for building, road, and bridge construction.
Key Questions for Project Engineers
- Bridge Site Surveys: Topographic and river surveys should extend 100 to 200 meters both upstream and downstream from the bridge centerline for proper assessment.
- Concrete Bridge Superstructure: The simplest superstructure for a bridge with a limited span of 8 meters is a Reinforced Concrete Slab.
- Caisson Foundations: Pneumatic foundation is not classified as a type of caisson; recognized types include box, open, and hydraulic caissons.
Essential Project Documents
- Project sites must have critical documents such as bills of quantities, plans, and general specifications; feasibility studies are not strictly necessary on-site.
Asphalt Cement Use
- Asphalt cement serves as an effective bituminous binder material, typically referenced in project items, such as items 306, 308, 310, and 311.
Contract Time Extensions
- Factors such as adverse climate conditions and causes beyond a contractor’s control can justify extensions, while contractor failures to supply manpower do not.
Contract Price Escalation
- Contracts are eligible for price escalation if variances from the original price exceed 5%.
Contract Rescission Conditions
- Contracts may be rescinded due to undue delays solely caused by the contractor, alongside issues like right-of-way problems.
Contract Price Adjustment Timeline
- A 60-day period from bid acceptance to notice of proceeding is required for projects to qualify for price adjustments.
Change Order Issuance
- Change orders should not be issued for work deletions that don't increase overall costs or where the cost controlling increase remains under 25%.
Online Resources
- Additional study materials and quizzes can be accessed through social media pages associated with Engr. Jeston G. Elano for further preparation.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your knowledge with our DPWH Accreditation Quiz for Contractors and Consultants. This quiz is specially curated for Project Engineers and aims to enhance your understanding of key topics necessary for accreditation. Engage with challenging questions and prepare yourself for success in your professional journey.