Questions and Answers

What is the impact of changing the predecessor after work has started on the successor?

  • Has no impact on the project
  • Creates a potential rework situation and increases project risk (correct)
  • Reduces the amount of work to be done
  • Improves coordination and communication

What is the effect of schedule compressions on the time frame and amount of work to be done?

  • Extend the time frame without affecting the amount of work to be done
  • Affect only the time frame in which work will be done; they do not reduce the amount of work to be done (correct)
  • Have no impact on the project schedule
  • Reduce the amount of work to be done without affecting the time frame

Why is it important to focus on critical path tasks when identifying potential dependency changes?

  • Critical path tasks determine the completion date of the project (correct)
  • Critical path tasks have fewer dependencies
  • Critical path tasks are less important for project completion
  • Critical path tasks require less coordination and communication

Why is it usually not a good strategy to make dependency changes on critical path tasks that come early in a project?

<p>Introducing risk into the project when the team is not yet cohesive (B)</p> Signup and view all the answers

When should one look downstream on the critical path for compression opportunities?

<p>When looking for opportunities to introduce compression without early risk (D)</p> Signup and view all the answers

More Like This

Project Management Chapter 1 Quiz
4 questions
Project Management Fundamentals
20 questions
Project Management Flashcards
12 questions

Project Management Flashcards

IllustriousHoneysuckle avatar
IllustriousHoneysuckle
Use Quizgecko on...
Browser
Browser