Construction Project Schedule PDF

Summary

This document is a construction project schedule for a building project. It details various tasks, durations, and dependencies. The schedule covers different phases of the project, from demolition and site clearance to ground floor, first floor, second floor, and third floor construction.

Full Transcript

Task Mode Task Name Duration Start Finish Predecessors Auto General Work 6 days 06-11-23 13-11-23 Scheduled Auto Demolition, Site Clearance 4 days 06-11-23 09-11-23 Scheduled Auto...

Task Mode Task Name Duration Start Finish Predecessors Auto General Work 6 days 06-11-23 13-11-23 Scheduled Auto Demolition, Site Clearance 4 days 06-11-23 09-11-23 Scheduled Auto Compound Wall Preparation/Fencing 2 days 10-11-23 13-11-23 2 Scheduled Auto Lineout 2 days 09-11-23 10-11-23 3SS-1 day Scheduled Auto Substructure 13 days 13-11-23 29-11-23 Scheduled Auto Foundation 13 days 13-11-23 29-11-23 Scheduled Auto Excavate Foundation 3 days 13-11-23 15-11-23 4 Scheduled Auto P.C.C. for all footings 1 day 16-11-23 16-11-23 7 Scheduled Auto Reinforcement works for footings and 6 days 17-11-23 24-11-23 8 Scheduled columns Auto Soiling (Backfilling) 2 days 22-11-23 23-11-23 9FS-3 days Scheduled Auto Prepare and pour concrete for floor 3 days 24-11-23 28-11-23 10 Scheduled Auto Anti-termite & Waterproofing layer 1 day 29-11-23 29-11-23 11 Scheduled Auto Superstructure 52 days 30-11-23 13-02-24 Scheduled Auto Ground Floor 52 days 30-11-23 13-02-24 Scheduled Auto Casting of Columns 6 days 30-11-23 07-12-23 12 Scheduled Auto Casting of Lift Walls 1 day 07-12-23 07-12-23 15FS-3 days Scheduled Auto 15,18FF-4 Casting of Staircase 1 day 13-02-24 13-02-24 Scheduled days Auto Shuttering work for slab 6 days 08-12-23 15-12-23 15,16 Scheduled Auto Slab Casting 1 day 18-12-23 18-12-23 18 Scheduled Auto First Floor 39 days 19-12-23 13-02-24 Scheduled Auto Casting of Columns 6 days 19-12-23 26-12-23 19 Scheduled Auto Casting of Lift Walls 1 day 26-12-23 26-12-23 21FS-3 days Scheduled Auto 24FF-4 Casting of Staircase 1 day 13-02-24 13-02-24 Scheduled days,21 Auto Shuttering work for slab 6 days 27-12-23 04-01-24 21,22 Scheduled Auto Slab Casting 1 day 05-01-24 05-01-24 24 Scheduled Auto Second Floor 26 days 08-01-24 13-02-24 Scheduled Auto Casting of Columns 6 days 08-01-24 15-01-24 25 Scheduled Auto Casting of Lift Walls 1 day 15-01-24 15-01-24 27FS-3 days Scheduled Auto 27,30FF-4 Casting of Staircase 1 day 13-02-24 13-02-24 Scheduled days Auto Shuttering work for slab 6 days 16-01-24 23-01-24 27,28 Scheduled Auto Slab Casting 1 day 24-01-24 24-01-24 30 Scheduled Auto Third Floor 13 days 25-01-24 13-02-24 Scheduled Auto Casting of Columns 6 days 25-01-24 02-02-24 31 Scheduled Auto Casting of Lift Walls 1 day 02-02-24 02-02-24 33FS-3 days Scheduled Auto 33,36FF-4 Casting of Staircase 1 day 13-02-24 13-02-24 Scheduled days Auto Shuttering work for slab 6 days 05-02-24 12-02-24 33,34 Scheduled Auto Slab Casting 1 day 13-02-24 13-02-24 36 Scheduled

Use Quizgecko on...
Browser
Browser