In a lump-sum contract, who bears the most risk for cost overruns?
In a lump-sum contract, who bears the most risk for cost overruns?
- The architect
- The subcontractor
- The owner
- The contractor (correct)
Which delivery method offers the greatest flexibility to incorporate design changes during construction?
Which delivery method offers the greatest flexibility to incorporate design changes during construction?
- Design-Build
- Lump Sum
- Cost Plus (correct)
- Construction Management at Risk
What is a key advantage of using a Construction Management (CM) at Risk delivery method?
What is a key advantage of using a Construction Management (CM) at Risk delivery method?
- Reduced risk for the owner
- Predictable project costs
- Improved project schedule (correct)
- Cost-plus feature
- Simplified contract structure
- Construction Manager acts as a consultant during construction
What is the primary characteristic of a cost-plus contract?
What is the primary characteristic of a cost-plus contract?
Which delivery method requires complete design before the contract is awarded?
Which delivery method requires complete design before the contract is awarded?
A homeowner hires a contractor to build a custom home with an agreed-upon 15% profit margin. If the construction costs $600,000, how much will the contractor receive as their fee?
A homeowner hires a contractor to build a custom home with an agreed-upon 15% profit margin. If the construction costs $600,000, how much will the contractor receive as their fee?
What is a key disadvantage of a lump-sum contract for an owner?
What is a key disadvantage of a lump-sum contract for an owner?
In a Construction Management (CM) at Risk delivery method, who is responsible for guaranteeing a maximum price (GMP)?
In a Construction Management (CM) at Risk delivery method, who is responsible for guaranteeing a maximum price (GMP)?
What is a key advantage of guaranteed maximum price contracts?
What is a key advantage of guaranteed maximum price contracts?
In the construction management no risk model, who retains the financial risks?
In the construction management no risk model, who retains the financial risks?
What is a disadvantage of using unit price or time and materials contracts?
What is a disadvantage of using unit price or time and materials contracts?
What is a characteristic of the construction manager's role in the construction management no risk model?
What is a characteristic of the construction manager's role in the construction management no risk model?
What kind of projects are unit price or time and materials contracts best suited for?
What kind of projects are unit price or time and materials contracts best suited for?
Which project delivery method typically offers the highest cost certainty?
Which project delivery method typically offers the highest cost certainty?
Which delivery method is characterized by high flexibility?
Which delivery method is characterized by high flexibility?
What is a common issue related to disputes in Lump Sum contracts?
What is a common issue related to disputes in Lump Sum contracts?
How can scheduling and cost tracking be effectively managed in CM and Cost Plus contracts?
How can scheduling and cost tracking be effectively managed in CM and Cost Plus contracts?
What is typically the speed of execution in a Cost Plus delivery method?
What is typically the speed of execution in a Cost Plus delivery method?
What is the primary benefit of a Cost Plus with GMP contract model?
What is the primary benefit of a Cost Plus with GMP contract model?
Which contractor selection method focuses primarily on cost efficiency?
Which contractor selection method focuses primarily on cost efficiency?
In which scenario is prequalification of contractors most important?
In which scenario is prequalification of contractors most important?
What is a key component of change order management in Cost Plus contracts?
What is a key component of change order management in Cost Plus contracts?
What risk mitigation strategy do contractors typically employ in Lump Sum contracts?
What risk mitigation strategy do contractors typically employ in Lump Sum contracts?
What type of clause is common in Lump Sum and CM contracts to penalize delays?
What type of clause is common in Lump Sum and CM contracts to penalize delays?
How does Building Information Modeling (BIM) enhance project delivery?
How does Building Information Modeling (BIM) enhance project delivery?
What is the focus of negotiated contracts compared to other types?
What is the focus of negotiated contracts compared to other types?
What pricing approach is best suited for projects with a well-defined scope?
What pricing approach is best suited for projects with a well-defined scope?
Which method has the highest risk to the contractor?
Which method has the highest risk to the contractor?
For which type of projects is the Unit Price method most suitable?
For which type of projects is the Unit Price method most suitable?
What is the owner’s risk percentage associated with the CM (No Risk) method?
What is the owner’s risk percentage associated with the CM (No Risk) method?
When is it advisable to use a Cost Plus method?
When is it advisable to use a Cost Plus method?
Which delivery method balances risk equally between the contractor and the owner?
Which delivery method balances risk equally between the contractor and the owner?
In hybrid delivery methods, what gives lump sum pricing some flexibility?
In hybrid delivery methods, what gives lump sum pricing some flexibility?
What is a drawback of the Cost Plus pricing method?
What is a drawback of the Cost Plus pricing method?
Flashcards
Guaranteed Maximum Price (GMP)
Guaranteed Maximum Price (GMP)
A pricing method where total costs are capped, providing cost certainty for the owner.
Construction Management (CM) No Risk
Construction Management (CM) No Risk
A model where the CM advises on construction without financial risk for overruns, leaving the owner liable.
Unit Price Contract
Unit Price Contract
A payment method where contractors are paid based on agreed-upon unit rates or actual time and materials used.
Time and Materials (T&M)
Time and Materials (T&M)
Signup and view all the flashcards
Financial Risks in Construction
Financial Risks in Construction
Signup and view all the flashcards
Lump Sum Contract
Lump Sum Contract
Signup and view all the flashcards
Advantages of Lump Sum
Advantages of Lump Sum
Signup and view all the flashcards
Disadvantages of Lump Sum
Disadvantages of Lump Sum
Signup and view all the flashcards
Cost Plus Contract
Cost Plus Contract
Signup and view all the flashcards
Advantages of Cost Plus
Advantages of Cost Plus
Signup and view all the flashcards
Disadvantages of Cost Plus
Disadvantages of Cost Plus
Signup and view all the flashcards
Construction Management at Risk
Construction Management at Risk
Signup and view all the flashcards
Collaboration in CM at Risk
Collaboration in CM at Risk
Signup and view all the flashcards
Lump Sum Pricing
Lump Sum Pricing
Signup and view all the flashcards
Cost Plus Pricing
Cost Plus Pricing
Signup and view all the flashcards
CM (At Risk)
CM (At Risk)
Signup and view all the flashcards
CM (No Risk)
CM (No Risk)
Signup and view all the flashcards
Unit Price Method
Unit Price Method
Signup and view all the flashcards
Hybrid Delivery Methods
Hybrid Delivery Methods
Signup and view all the flashcards
Risk Distribution: Lump Sum
Risk Distribution: Lump Sum
Signup and view all the flashcards
Owner's Risk vs. Contractor's Risk
Owner's Risk vs. Contractor's Risk
Signup and view all the flashcards
Cost Plus with GMP
Cost Plus with GMP
Signup and view all the flashcards
Competitive Bidding
Competitive Bidding
Signup and view all the flashcards
Negotiated Contracts
Negotiated Contracts
Signup and view all the flashcards
Prequalification
Prequalification
Signup and view all the flashcards
Scope of Work Clauses
Scope of Work Clauses
Signup and view all the flashcards
Change Order Management
Change Order Management
Signup and view all the flashcards
Liquidated Damages
Liquidated Damages
Signup and view all the flashcards
Building Information Modeling (BIM)
Building Information Modeling (BIM)
Signup and view all the flashcards
Project Management Software
Project Management Software
Signup and view all the flashcards
Delivery Method Factors
Delivery Method Factors
Signup and view all the flashcards
Study Notes
Lump Sum (Traditional Method)
- Description: A lump-sum contract commits the contractor to completing the entire project for a fixed price, regardless of costs.
- Key Features:
- Fixed total price
- High risk for the contractor due to potential cost overruns
- Requires complete design before tendering
- Advantages:
- Predictable costs for the owner
- Simple and straightforward contract
- Minimal owner involvement during construction
- Disadvantages:
- Less flexibility for design changes
- Higher contingency costs included by contractors
- Example: A government building contract of $10 million would require the contractor to absorb any extra costs exceeding this amount, due to unforeseen delays.
Cost Plus
- Description: The owner pays the contractor actual costs plus a predetermined fee (fixed or percentage).
- Key Features:
- Flexible pricing mechanism
- Greater transparency of costs
- Owner assumes most financial risks
- Advantages:
- Allows projects to start before final design
- More control over material selection and changes
- Disadvantages:
- Risk of escalating costs for the owner
- Requires close monitoring of expenses
- Example: A homeowner hires a contractor to renovate their house for $500,000, with a 10% profit margin for the contractor.
Construction Management (CM) at Risk
- Description: The construction manager acts as consultant in the design phase and becomes the general contractor during construction, guaranteeing a maximum price (GMP).
- Key Features:
- Combines lump sum and cost-plus elements
- CM assumes risk for cost overruns
- Promotes collaboration between design and construction teams
- Advantages:
- Improved project schedule due to overlapping design and construction phases
- Guaranteed maximum price provides cost certainty
- Disadvantages:
- Higher fees for the CM
- Requires higher level of trust and coordination
- Example: A shopping mall project hires a CM, guaranteeing costs won't exceed $20 million, covering expertise through the design phase.
Construction Management (CM) No Risk
- Description: Construction manager acts solely as an advisor, managing the construction process without financial risk for overruns.
- Key Features:
- CM provides professional advice and oversight
- Owner retains all financial risks
- Best suited for complex projects with multiple stakeholders
- Advantages:
- Transparency and flexibility for the owner
- CM focuses on project quality, rather than managing risks
- Disadvantages:
- Owner must closely monitor costs and progress
- No cost guarantees
- Example: A university hires a CM to oversee a new campus building. The CM coordinates contractors, ensuring quality but without a guaranteed maximum price.
Unit Price or Time and Materials (T&M)
- Description: Contractor payment is based on the unit rate or actual time and material used.
- Key Features:
- Flexible pricing for undefined scopes of work
- Ideal for renovation or maintenance projects
- Owner bears the financial risk
- Advantages:
- Easy adjustments for changes in scope
- Useful for uncertain scope projects
- Disadvantages:
- Potentially higher costs for the owner
- Requires detailed cost tracking and verification
- Example: A road repair project charges $100 per square foot for resurfacing, with final costs depending on the total area repaired.
Selection Process
- Well-Defined Scope: For well-defined scope projects, Lump Sum or CM (At Risk) are likely suitable.
- Cost Certainty: If the owner wants cost certainty, consider Lump Sum or CM (At Risk).
- Alternative: Otherwise, other options like Cost Plus or CM (No Risk), are viable.
Risk Considerations
- Each contract type involves risks that must be considered (Owner and Contractor). The risk ownership/distribution vary based on the method chosen.
Legal and Contractual aspects
- Delivery methods are legally bound.
- Legal frameworks cover enforceability and resolution of disputes.
- Scope-of-work clauses are essential for a Lump sum.
- Change order processes are common in Cost Plus/Time-and-Materials contracts.
- Liquidated damages are a clause found in Lump sum and CM contracts, where penalties for delayed completion apply.
Additional Insights
- Hybrid approaches combining elements of different methods are common for better results and benefit utilization.
- Modern technology such as BIM aids collaboration during design and construction phases, helping minimize errors.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz explores the key characteristics of lump-sum and cost-plus construction contracts. Understand the advantages and disadvantages of each type, and how they impact project management and owner involvement. Test your knowledge on real-world applications of these contracts.