Which type of tender call is frequently used when the project involves public funds?

  • Open Competitive Bids (correct)
  • Invited Competitive Bids
  • Direct Selection
  • All of the above
  • What information should be included in the Notice of Tender?

  • Name and location of project
  • Name of the client and the architect
  • Size and type of project
  • All of the above (correct)
  • What is the purpose of pre-qualification in invited bids?

  • To ensure contractors have the necessary financial capacity
  • To assess the capacity and previous record of contractors
  • To eliminate candidates who do not demonstrate relevant experience
  • All of the above (correct)
  • What type of construction contract is based on mutual trust and full disclosure of all estimates and quotations?

    <p>Cost Plus Contract</p> Signup and view all the answers

    What is the purpose of a bond in the construction industry?

    <p>To ensure financial security for the owner</p> Signup and view all the answers

    According to the text, what is the purpose of a 'privilege clause' in a bid package?

    <p>To justify a decision to award a contract to someone other than the lowest bidder</p> Signup and view all the answers

    What does the Supreme Court of Canada ruling state about accepting a non-compliant bid?

    <p>It is considered a breach of the duty of fairness to all other bidders</p> Signup and view all the answers

    What should architects indicate in the Instructions to Bidders when preparing tender documents?

    <p>The requirements for a compliant bid</p> Signup and view all the answers

    Why is it important to issue complete sets of bid documents?

    <p>To ensure easy access to the drawings and specifications</p> Signup and view all the answers

    What is the purpose of obtaining a deposit when obtaining bid documents?

    <p>To ensure the safe return of the bid documents</p> Signup and view all the answers

    Which of the following is NOT a method of selecting contractors and awarding construction contracts?

    <p>Negotiated proposals</p> Signup and view all the answers

    What is the name of the guide that provides a complete guide to the bid process?

    <p>CCDC 23</p> Signup and view all the answers

    According to the text, what is one of the architect's responsibilities under the Canadian Standard Form of Contract Between Client and Architect: RAIC Document Six?

    <p>Assisting the client in awarding contracts</p> Signup and view all the answers

    What must the architect and the client determine at the outset of the project?

    <p>All of the above</p> Signup and view all the answers

    Which type of contract is described as simpler to manage in the text?

    <p>Stipulated price contract with a single bid call</p> Signup and view all the answers

    Which of the following statements about bid depositories is true?

    <p>Bid depositories are facilities operated by construction associations to collect and register bids from sub-contractors and suppliers.</p> Signup and view all the answers

    Which of the following is NOT a purpose of addenda in bid documents?

    <p>To issue new information only in writing to all bidders and others.</p> Signup and view all the answers

    What is the recommended timeframe for issuing the last addendum before bid closing?

    <p>4 working days</p> Signup and view all the answers

    How does the length of the bid period vary?

    <p>Based on the project complexity.</p> Signup and view all the answers

    What is the recommended approach for receiving bids in multiple locations?

    <p>It is recommended to receive bids in a single location.</p> Signup and view all the answers

    Which type of bond guarantees that claimants will be paid for labor and materials provided to the contractor for use on the project?

    <p>Labour and material payment bond</p> Signup and view all the answers

    What is the purpose of a performance bond?

    <p>To indemnify the owner in the event of default on the part of the contractor</p> Signup and view all the answers

    What is the recommended form for a bid bond?

    <p>CCDC Form 220</p> Signup and view all the answers

    What is the typical range for the amount of a bid bond?

    <p>5-10% of the estimated construction cost</p> Signup and view all the answers

    Which document should the architect refer to in order to prepare the bid package?

    <p>CCDC 23</p> Signup and view all the answers

    According to CCDC 23, it is not recommended that bids close on a Friday or a Monday, nor immediately following or preceding a statutory holiday. Usually, the time for closing bids is mid- to late-afternoon. It is important to specify the time as 'before' the hour, not 'on' or 'at' the hour.

    <p>Mid-afternoon</p> Signup and view all the answers

    Which of the following days is NOT recommended for bid closure?

    <p>Saturday</p> Signup and view all the answers

    How should the time for bid closure be specified?

    <p>Before the hour</p> Signup and view all the answers

    When is it recommended to close bids following a statutory holiday?

    <p>Two days after</p> Signup and view all the answers

    Which of the following is an example of a well-worded bid closure instruction?

    <p>Bids must be received before 3:00 P.M. on Thursday, February 9, 2009</p> Signup and view all the answers

    True or false: It is recommended to close bids on a Friday or a Monday, as per CCDC 23.

    <p>False</p> Signup and view all the answers

    True or false: Bids should be received 'at' the specified hour, according to CCDC 23.

    <p>False</p> Signup and view all the answers

    True or false: A well-worded bid closure instruction should include the date and time.

    <p>True</p> Signup and view all the answers

    True or false: Bids should be received before mid-afternoon, as per CCDC 23.

    <p>True</p> Signup and view all the answers

    True or false: It is not necessary to issue complete sets of bid documents.

    <p>False</p> Signup and view all the answers