Construction Contract Change Orders
10 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the main difference between a contract modification and a change order?

  • A contract modification can only be initiated by the client, while a change order can be initiated by either party. (correct)
  • A contract modification involves availability of funds, while a change order does not.
  • A contract modification requires notification of change documents, while a change order does not.
  • A contract modification is unilateral, while a change order is bilateral.
  • What triggers the need for a contract modification or change order?

  • Any change, in part or whole, occurring to a legally binding agreement (correct)
  • The expiration of the contract
  • The availability of funds
  • The completion of the project
  • Which term refers to the initiation of changes to a legally binding agreement after the contract has been signed?

  • Termination
  • Notification
  • Bilateral
  • Unilateral (correct)
  • What is the purpose of writing contract change orders?

    <p>To confirm that a change has occurred, direct the mode of further performance, and plan for its funding</p> Signup and view all the answers

    What are common causes of change orders?

    <p>Differing site conditions and design change</p> Signup and view all the answers

    Under what conditions are change orders issued?

    <p>If the method of performance is not proper</p> Signup and view all the answers

    What is the purpose of writing contract change orders?

    <p>To clarify the terms of the contract and authorize an increase in extra work</p> Signup and view all the answers

    Under what circumstances can a unilateral contract modification be issued?

    <p>When administrative changes need to be implemented</p> Signup and view all the answers

    What are the common causes of change orders?

    <p>Differing site conditions and design changes</p> Signup and view all the answers

    What are the types of contract change orders?

    <p>Normal change orders and emergency change orders</p> Signup and view all the answers

    More Like This

    Mastering Construction Contracts
    11 questions
    Types of Construction Contracts
    30 questions
    Standard Form Construction Contracts Quiz
    10 questions
    Construction Contracts Overview
    40 questions
    Use Quizgecko on...
    Browser
    Browser