Commissioning of Electric Traction
82 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the initial step required before introducing electrification on the zonal railway?

  • Position additional maintenance staff immediately
  • Create a nucleus setup at headquarters (correct)
  • Recruit drivers from other transport modes
  • Complete all OHE facilities
  • How far in advance should a Training School be organized for staff training?

  • 3 months in advance
  • 6 months in advance
  • 2 years in advance
  • 1 year in advance (correct)
  • What is required for the selection of running staff from steam and diesel cadre?

  • New hiring practices
  • Conversion training courses (correct)
  • Immediate staffing changes
  • No additional training necessary
  • When should the Inspectorial cadre be positioned to ensure compliance?

    <p>3 months before commissioning</p> Signup and view all the answers

    What should be expedited to support the maintenance and operation of OHE?

    <p>Completion of OHE and PSI depots</p> Signup and view all the answers

    How long before the arrival of locomotives should staff be posted to a loco-shed?

    <p>6 months</p> Signup and view all the answers

    What advantage does establishing a nucleus setup of key officers provide?

    <p>Enhanced rapport with construction organization</p> Signup and view all the answers

    What is the role of the Contractor or Supplier after the issue of the final acceptance Certificates?

    <p>They can provide advice if necessary.</p> Signup and view all the answers

    Which certificate is specifically issued regarding the energization of systems?

    <p>Sanction of CEE and Electrical Inspector for energisation</p> Signup and view all the answers

    Which of the following documents is NOT listed amongst the certificates issued?

    <p>Safety Compliance Certificate</p> Signup and view all the answers

    What type of document is the 'Public Notification regarding level crossing' categorized as?

    <p>Notification</p> Signup and view all the answers

    Who needs to countersign the certificate issued to the Contractor?

    <p>The head of the Construction Organisation</p> Signup and view all the answers

    What phase of training is included for Steam/Diesel Drivers?

    <p>Basic theoretical and practical training in electric rolling-stock</p> Signup and view all the answers

    What does the Construction Organization ensure regarding installation design?

    <p>All installations must follow approved standards and gain necessary approvals for any deviations.</p> Signup and view all the answers

    Which document should be handed over to the CEE for safe custody upon completion of construction?

    <p>Approved specifications, contract documents, and important letters</p> Signup and view all the answers

    When is the procurement of special stores and tools required to be handed over?

    <p>In two stages: minimum required before tests and the rest after installation.</p> Signup and view all the answers

    What is the responsibility of the Construction Organization's interaction with the CEE?

    <p>To consult with the CEE on commissioning program and dates.</p> Signup and view all the answers

    What should be done with the 'as made' drawings during the construction process?

    <p>They must be countersigned and handed over to the CEE.</p> Signup and view all the answers

    What type of training will maintenance staff undergo due to electrification?

    <p>Screening and conversion training due to surplus from electrification.</p> Signup and view all the answers

    What is a primary duty of the Construction Organization regarding works execution?

    <p>To ensure all works are executed to a high standard and comply with target dates.</p> Signup and view all the answers

    What type of training is emphasized for electric rolling-stock operation?

    <p>A combination of both theoretical and practical training.</p> Signup and view all the answers

    What is the primary purpose of conducting an overall confirmatory test on circuit breakers?

    <p>To ensure proper tripping of circuit breakers against dead-short circuits.</p> Signup and view all the answers

    How should the supervision of energized transformers be managed in the initial stages?

    <p>An experienced supervisory official should observe closely for the first three days.</p> Signup and view all the answers

    What should be done if a circuit breaker trips during the initial observation period?

    <p>Investigate the cause of the tripping meticulously.</p> Signup and view all the answers

    What potential issue can cause the Buchholz relay to operate when a transformer is first energized?

    <p>Air bubbles released from oil when heated.</p> Signup and view all the answers

    What is required before the 25 kV power supply can be extended to feeding posts?

    <p>All work on feeders and feeding posts must be completely finished.</p> Signup and view all the answers

    What does the application for energization require to accompany it?

    <p>Certificates and copies of public notifications.</p> Signup and view all the answers

    What type of approval is needed prior to energization of high voltage equipment?

    <p>Formal design and layout approval from authorities.</p> Signup and view all the answers

    Which certificate is NOT explicitly mentioned as part of the application for energization?

    <p>Certificate of equipment purchase.</p> Signup and view all the answers

    What should an official do if they suspect an issue with the transformer after energization?

    <p>Consult the operator and check the Buchholz relay.</p> Signup and view all the answers

    What is the frequency of inspections required for energized transformers after the first three days?

    <p>Weekly inspections thereafter.</p> Signup and view all the answers

    What is the usual guarantee period for suppliers' responsibility under a supply contract for heavy equipment?

    <p>12 months from date of commissioning or 18 months from date of supply, whichever is earlier</p> Signup and view all the answers

    What documentation should be maintained regarding heavy equipment?

    <p>Receipts of the equipment and dates of energization</p> Signup and view all the answers

    What should be done if a defect is noticed during the guarantee period?

    <p>Notify the supplier immediately and document the defect</p> Signup and view all the answers

    Who is responsible for operating and maintaining the equipment during the guarantee period?

    <p>Open Line Railway Engineers</p> Signup and view all the answers

    What is the supplier's liability if the equipment becomes irreparable during the guarantee period?

    <p>To replace the equipment entirely</p> Signup and view all the answers

    What should Electrical Officers and Supervisors do regarding the contract documents?

    <p>Study them carefully to determine necessary actions</p> Signup and view all the answers

    What kind of defects should be recorded in the register by the Open Line Officer?

    <p>Any defects and deficiencies noticed</p> Signup and view all the answers

    What must be strictly followed by the Railway regarding the equipment?

    <p>Instructions for operation and maintenance</p> Signup and view all the answers

    What happens if modifications to the equipment are required?

    <p>Manufacturers' approval must be obtained first</p> Signup and view all the answers

    What is not covered by the standard Guarantee Clause?

    <p>Improvements to the equipment design</p> Signup and view all the answers

    What is the primary responsibility of the CEE of the Open Line regarding electrification works?

    <p>Arranging for the timely takeover of installations upon commissioning.</p> Signup and view all the answers

    Which of the following actions is NOT recommended during the final stages of erection for electrification?

    <p>Complete isolation of the Open Line Officers from the process.</p> Signup and view all the answers

    What is an essential requirement for the organization at the CEE level before commissioning electric traction?

    <p>Creation of an organization with trained personnel for operation and maintenance.</p> Signup and view all the answers

    What key aspect must the Administrative Officers inspect before the energization of substations?

    <p>Sanction for the energization of substations, switching stations, and OHE.</p> Signup and view all the answers

    What is involved in the post-commissioning work of electric traction?

    <p>Operation and maintenance of the newly electrified sections.</p> Signup and view all the answers

    In terms of staff training, what must be prioritized before the commissioning of electric traction?

    <p>Recruitment and training of operating and maintenance staff.</p> Signup and view all the answers

    What is required for the final tests prior to the commissioning of electric traction?

    <p>Trial runs with rolling-stock to ensure functionality.</p> Signup and view all the answers

    What is the primary purpose of creating a nucleus setup at the headquarters when introducing electrification?

    <p>To ensure effective collaboration with construction organization.</p> Signup and view all the answers

    Why is it important to recruit maintenance and operating staff a year before energization?

    <p>To ensure readiness for operational challenges.</p> Signup and view all the answers

    How should the staff be organized to prepare for the maintenance and operation of rolling stock?

    <p>They must undergo specialized training in electric systems.</p> Signup and view all the answers

    What action should be taken regarding the Inspectorial cadre three months before commissioning?

    <p>They should ensure compliance and conduct training.</p> Signup and view all the answers

    What preliminary step should be taken if a loco-shed is part of the RE project?

    <p>Post staff to establish shed facilities six months ahead.</p> Signup and view all the answers

    What is one of the essential roles of the officers regarding workforce selection for new electrification services?

    <p>Select individuals based on a diverse range of qualifications.</p> Signup and view all the answers

    How should the organizational setup be augmented prior to commissioning?

    <p>By adding more staff for detailed checks and rectification.</p> Signup and view all the answers

    What is a critical requirement when setting up facilities for OHE and PSI depots?

    <p>Expediting the equipping of emergency vans and inspection cars.</p> Signup and view all the answers

    What is necessary for the construction unit regarding the maintenance of specialized equipment?

    <p>They need to ensure adequate preparations for major plant and machinery.</p> Signup and view all the answers

    What is the clear height specified by the height gauges erected at level crossings for road users to observe?

    <p>4.67m</p> Signup and view all the answers

    Which danger is NOT listed as a risk associated with loads of excessive height?

    <p>Obstruction to pedestrian traffic</p> Signup and view all the answers

    In which circumstance can infringements to the Schedule of Dimensions occur according to the certification requirements?

    <p>Only if Railway Board approval is obtained</p> Signup and view all the answers

    What is the purpose of the bonding and earthing certification mentioned in the document?

    <p>To ensure compliance with railway safety standards</p> Signup and view all the answers

    What is one of the primary dangers listed that could occur due to contact with live traction wires?

    <p>Risk of life</p> Signup and view all the answers

    What is the main purpose of conducting an overall confirmatory test on circuit breakers?

    <p>To ensure proper coordination of relay settings between grid and traction substations</p> Signup and view all the answers

    What should be done in case of a tripped circuit breaker during the initial observation period?

    <p>Conduct a careful investigation of the cause</p> Signup and view all the answers

    What is the significance of monitoring the transformers for the first three days of energization?

    <p>To detect potential electrical faults early on</p> Signup and view all the answers

    Which relay may potentially operate when a transformer is energized for the first time due to air entrapment?

    <p>Buchholz relay</p> Signup and view all the answers

    What document must accompany the application for energization approval?

    <p>Certification regarding bonding and earthing</p> Signup and view all the answers

    What is the minimum notice period for submitting an application for energization to the appropriate authority?

    <p>Fortnight (two weeks)</p> Signup and view all the answers

    What should be checked to ascertain which relays operated after a circuit breaker trips?

    <p>The annunciator panel</p> Signup and view all the answers

    What condition must be fulfilled before extending the 25 kV power supply to feeding posts?

    <p>Completion of all feeder installations and safety precautions</p> Signup and view all the answers

    What is the recommended inspection frequency for energized transformers after the initial monitoring period?

    <p>Once after a week and then every fortnight</p> Signup and view all the answers

    What is necessary before energizing high voltage installations like substations and feeders?

    <p>Formal approval of design and safety measures</p> Signup and view all the answers

    What is the maximum duration for the supplier's responsibility under the guarantee clause?

    <p>18 months from the date of commissioning</p> Signup and view all the answers

    Which of the following actions is NOT recommended if a defect is noticed during the guarantee period?

    <p>Attempt to repair the defect without supplier approval</p> Signup and view all the answers

    Which type of equipment maintenance should strictly follow the manufacturer's guidelines according to the guarantee clause?

    <p>Operational and maintenance procedures</p> Signup and view all the answers

    What liability does the supplier have if the equipment becomes irreparable during the guarantee period?

    <p>Replace the equipment in its entirety</p> Signup and view all the answers

    What must be accurately recorded to define the period of responsibility of the contractor?

    <p>Dates of receipt and dates of energization of equipment</p> Signup and view all the answers

    What is a requirement before any modifications to the equipment are made?

    <p>Approval from the Manufacturers</p> Signup and view all the answers

    Which practice should be followed if a defect is identified during the warranty period?

    <p>Enter details in a defect register and notify the supplier</p> Signup and view all the answers

    What type of defects are the supplier liable for according to the guarantee clause?

    <p>Defects due to faulty design and manufacturing</p> Signup and view all the answers

    What should Electrical Officers and Supervisors do regarding the contract documents?

    <p>Study them carefully for appropriate actions</p> Signup and view all the answers

    During the guarantee period, who operates and maintains the equipment?

    <p>Open Line Railway Engineers</p> Signup and view all the answers

    Study Notes

    Commissioning of Electric Traction

    • Electric traction introduction requires a clear action plan for high standards in departmental and contractor work.
    • The organization for running the services must be prepared.
    • Sections must be ready for prompt operation and efficient management as soon as 25 kV installations are energized.

    Preparation by Open Line

    • Electrification work separation from Open Line (CEE) relieves them of detailed design, supervision, and execution.

    • The Open Line (CEE) plays a crucial role in timely installation takeover.

    • Organization creation with trained personnel is essential for operation and maintenance, beginning on the commissioning date.

    • Recruitment and training for operating and maintenance staff are necessary.

    • Close collaboration between Open Line Officers/staff and those during erection and adjustment is necessary.

    • Detailed inspections by lower and higher-ranking officers ensure work quality and identify rectifications.

    • Tests using rolling stock confirm functionality.

    • Administrative officers approve substation and OHE (Overhead Equipment) energization.

    • Final inspections (CRS) by electrical inspectors ensure proper commissioning and commercial service.

    • Post-commissioning operations and maintenance are essential.

    Organization for Inspection and Taking Over

    • Officers/staff positions are created 6 months in advance.

    • A nucleus is created at the headquarters during zonal railway electrification,

    • Maintenance training schools should be created a year in advance to train staff for electric traction operation and maintenance.

    • Suitable staff from steam and diesel cadres are recruited and undergo conversion training a year prior to energization.

    • The organizational set-up should be enhanced three months prior to commissioning.

    • Expedite OHE and PSI depot and workshop facilities completion.

    • Essential tools, equipment and other resources are made available.

    • If a loco-shed is part of the RE (Railway electrification) project, staff will be in place six months prior to the receiving of locos.

    • Staff will organize facilities for maintenance equipment, jigs, and accessories.

    Duties of Senior Divisional Electrical Engineer (TrD)

    • The senior engineer is responsible for ensuring smooth construction work completion.
    • The necessary accommodations (office and related facilities).
    • Equipment, tools, spare parts and emergency vehicles must be available.
    • Power supply systems are verified and officers are trained.

    Duties of Senior Divisional Electrical Engineer (RS)

    • Ensuring additional office/equipment accommodations and facilities, like loco sheds for inspection and maintenance
    • Ensures the availability of full machinery, tools, testing equipment
    • Necessary posts for operation and maintenance of rolling stock should be authorized.
    • Training for steam/diesel drivers in electric rolling stock operation and related rules is arranged.
    • Maintenance staff training and recruitment is ensured.
    • Clearances, approvals and reports from responsible authorities must be obtained.

    Commissioning of Traction Substations

    • Power supply readiness and satisfactory substation and connected RC equipment inspection are pre-conditions.
    • Essential communication facilities are ensured.
    • Substations are usually commissioned well before OHE (Overhead Equipment) energisation.

    Sanction of CEE and Electrical Inspector to the Railway

    • Applications for design and layout approvals must be submitted (high voltage equipment is included, including traction substation and others)
    • The application should include press cuttings of the public notification (and other relevant documents).
    • Necessary clearances and documents needed for OHE, bonding/ earthing and safety instructions and safety precautions.
    • Required data, test results, certificates (insulation resistance test results of OHE, data on sub/stations and safety related certificates).
    • The sanction is issued in a specific form.

    Notification Regarding Energization of OHE

    • A notification regarding OHE energization is issued to several concerned authorities at least a month in advance.
    • The notification mentions when the line will be energized (and related locations).

    Application to CRS

    • CRS sanction is required for electric traction introduction on the railway.
    • Necessary certificates are also submitted to obtain the sanction.
    • Certificates related to electrical work, rolling stock safety, and staff awareness of safety rules for electrified sections should be submitted to CRS.

    Procedure for Energization

    • Comprehensive inspections of the entire section are conducted during commissioning
    • CRS, CEE and their associated officers will conduct a full inspection of the OHE, for operation and safety-related aspects.
    • Train movements and staff are ensured to have relevant documentation
    • Wide publicity should be given through the Press and posters in advance by the Railway to avoid accidents.
    • Special safety precautions for energized parts of the overhead line.

    Precautions for Progressive Energization of OHE

    • Energization should be done progressively, maintaining separation between live and working areas or other safety measures.
    • Safety measures for workers and passengers should be enforced and maintained when work is ongoing.

    Final Inspection by CRS for the Introduction of Commercial Services

    • Special trains are organized for inspection of safety and operational aspects by CRS, CEE, project managers, and divisional officers.
    • CRS verifies knowledge of safety rules, operation, and related documentation by staff in different positions.

    Sanction of CRS

    • CRS issues an "all-concerned" message for commercial service start-up after trial operation success.
    • Defective parts are rectified and proper handling of the OHE is ensured by the Open Line.
    • Joint inspection confirmation of proper commercial operation is obtained.

    Responsibility for Maintenance and Provisional Acceptance Certificate

    • Construction organizations take charge of OHE and power supply during the initial period until commercial operations launch.

    • Open Line's divisional officers are responsible for maintenance and operation after commercial service launch

    • A provisional acceptance letter is issued by the construction organization after maintenance and test completion.

    • Deficiencies in installations are reported and an extension is given until all the work is completed.

    • Contractor's responsibility during the guarantee period includes maintenance (along with support and assistance from trained personnel)

    • Defect reporting and investigation procedures for electrical equipment during the guarantee period are described in detail.

    History Sheet

    • Detailed maintenance of a history sheet for major equipment is recommended to track failures and required repairs.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    This quiz covers the essential steps and preparations required for the commissioning of electric traction systems. Topics include organizational readiness, the role of Open Line (CEE), and the importance of staff training and inspections. Test your knowledge on the processes involved in ensuring efficient operation and management of electrified sections.

    More Like This

    TRACCION ELECTRICA
    7 questions

    TRACCION ELECTRICA

    NicestSavannah avatar
    NicestSavannah
    Electric Traction System
    16 questions

    Electric Traction System

    FortuitousElectricOrgan avatar
    FortuitousElectricOrgan
    Electric Traction Systems Overview
    40 questions
    Power Supply for Traction: Indian Railways
    81 questions
    Use Quizgecko on...
    Browser
    Browser