Commissioning of Electric Locomotives and EMUs
80 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What document is required to be issued by the Chief Engineer to obtain sanction from the CRS?

  • Operating license
  • Safety approval declaration
  • Provisional Speed Certificate (correct)
  • Dynamic performance report
  • Which of the following trials is NOT typically conducted by RDSO during testing?

  • Load Testing Trials (correct)
  • Performance Trials
  • Braking Distance Trials
  • Oscillation Trials
  • What information does the Final Speed Certificate provide?

  • Cost analysis for maintenance
  • The overall efficiency ratings of the locomotive
  • Safety recommendations for future operations
  • Maximum speed for which the stock is considered fit (correct)
  • Which entity is responsible for conducting tests regarding interference with signalling circuits?

    <p>RDSO</p> Signup and view all the answers

    Who signs the speed certificate issued by the user Railway?

    <p>Chief Engineer, Chief Electrical Engineer, Chief Mechanical Engineer, and Chief Signal and Telecom Engineer</p> Signup and view all the answers

    What is a key parameter assessed during the Oscillation Trials?

    <p>Dynamic augment</p> Signup and view all the answers

    Which of the following best describes the role of the Engineering Directorate at the Railway Board?

    <p>Communicating sanctions based on safety certifications</p> Signup and view all the answers

    What aspects are measured in the braking distance trials?

    <p>Braking distance with varying load and speed</p> Signup and view all the answers

    The final commercial exploitation sanction for the rolling stock is granted by which authority?

    <p>Railway Board</p> Signup and view all the answers

    What kind of certificate accompanies the application for sanction submitted by the Chief Engineer?

    <p>Safety Certificate</p> Signup and view all the answers

    What is the primary condition under which trial runs on the open line can be undertaken?

    <p>The operation has received the sanction of the CRS.</p> Signup and view all the answers

    Who should drive the locomotive during trial runs to ensure proper performance feedback?

    <p>A senior and experienced driver.</p> Signup and view all the answers

    What should be tested specifically during the trial runs of the locomotive?

    <p>The brakes' function under normal and emergency conditions.</p> Signup and view all the answers

    How long should new rolling stock initially run before being called back for inspection?

    <p>15 to 20 days.</p> Signup and view all the answers

    What specific checks should be made during the thorough inspection of new rolling stock?

    <p>Loosening of bolts and re-tightening them.</p> Signup and view all the answers

    What type of testing is conducted by manufacturers before locomotives and EMUs are dispatched?

    <p>Tests based on RDSO prescribed procedures.</p> Signup and view all the answers

    What should a report contain after testing a locomotive or EMU?

    <p>Records of defects and actions taken to rectify them.</p> Signup and view all the answers

    What documentation should be available in duplicate for new electric rolling stock?

    <p>Test certificates issued by manufacturers.</p> Signup and view all the answers

    What is an essential focus during the detailed inspection of rolling stock after running for a period?

    <p>Temperature rise, lubrication, and protective devices.</p> Signup and view all the answers

    What is the purpose of the inspection report sent to manufacturers and RDSO?

    <p>To improve design and testing procedures.</p> Signup and view all the answers

    What certification is required for the one-time movement of new prototype rolling stock?

    <p>Certification from the locomotive manufacturer</p> Signup and view all the answers

    Which of the following factors does NOT need to be considered for alterations affecting existing rolling stock?

    <p>Weight distribution</p> Signup and view all the answers

    What document does RDSO provide for the provisional running of a locomotive?

    <p>Provisional Speed Certificate</p> Signup and view all the answers

    The term 'New Type' for locomotives includes which of the following?

    <p>Any alteration affecting riding characteristics</p> Signup and view all the answers

    What is NOT included in the application made to the Chief Operations Manager (COM) for the movement of rolling stock?

    <p>Estimated travel time</p> Signup and view all the answers

    What is necessary before a new electric locomotive can be brought into service at higher speeds than previously sanctioned?

    <p>Sanction from the CRS</p> Signup and view all the answers

    Which document must be obtained if the locomotive is over dimensional during provisional running?

    <p>Board's condonation</p> Signup and view all the answers

    What condition is necessary for the Chief Operations Manager (COM) to authorize locomotive movement?

    <p>Supporting documentation including fitness certificates</p> Signup and view all the answers

    Which aspect is NOT part of the RDSO's Provisional Speed Certificate?

    <p>Fuel consumption rate</p> Signup and view all the answers

    What is the first stage in the process of inducting new prototype rolling stock into services?

    <p>One-time movement of the rolling stock</p> Signup and view all the answers

    What is required to be preserved one copy for reference in the loco shed?

    <p>Test and measurement results</p> Signup and view all the answers

    When is the manufacturer required to furnish operation and maintenance instructions?

    <p>Prior to dispatch of the locomotive</p> Signup and view all the answers

    Which components should be subjected to detailed examination for leakage detection in electric multiple units?

    <p>Pneumatic pipe connections and brake equipment</p> Signup and view all the answers

    What should be monitored during trial runs of a new loco or EMU?

    <p>Performance of the equipment</p> Signup and view all the answers

    Who should accompany the loco or EMU during the first few runs?

    <p>Driving Inspector and key personnel</p> Signup and view all the answers

    What should be ready well in advance of the introduction of a new type of loco or EMU?

    <p>Trouble-shooting directory</p> Signup and view all the answers

    What must be checked for proper sealing between coaches?

    <p>Control cable connections</p> Signup and view all the answers

    What should each circuit in the electric multiple units provide?

    <p>Individual fuses of correct rating</p> Signup and view all the answers

    What is the purpose of maintaining a separate History Sheet for each locomotive or EMU?

    <p>To document performance and maintenance</p> Signup and view all the answers

    What is the main focus of testing conducted with the EMU before passenger loading?

    <p>Safety and operational integrity</p> Signup and view all the answers

    What is the primary purpose of the Oscillation trials conducted by RDSO?

    <p>To evaluate riding quality and stability on tracks</p> Signup and view all the answers

    During which stage is the Final Speed Certificate issued by RDSO?

    <p>Fourth stage after trials results</p> Signup and view all the answers

    Which of the following is NOT included in the parameters measured during the Oscillation trials?

    <p>Fuel consumption rates</p> Signup and view all the answers

    What is required alongside the application made by the Chief Engineer to the CRS for sanction?

    <p>A Safety Certificate from various engineering officers</p> Signup and view all the answers

    Which trials assesses the braking capability of a locomotive?

    <p>Braking Distance Trials</p> Signup and view all the answers

    Who ultimately grants the sanction for commercial exploitation of rolling stock?

    <p>Railway Board</p> Signup and view all the answers

    During the tests on interference with signalling circuits, what is primarily measured?

    <p>Interference to signal and communication circuits</p> Signup and view all the answers

    What does the Final Speed Certificate specifically indicate?

    <p>The maximum operational speed and special precautions</p> Signup and view all the answers

    What distinguishes the role of the RDSO during the testing phase?

    <p>Conducting performance and interference trials</p> Signup and view all the answers

    What must be preserved for reference in the locomotive shed according to the process described?

    <p>A copy of the Speed Certificate</p> Signup and view all the answers

    What procedure should be performed immediately after a trial run of a new locomotive?

    <p>Make a detailed examination of the equipment.</p> Signup and view all the answers

    Which statement correctly reflects the requirement for the inspection of new electric rolling stock before commercial operation?

    <p>A thorough check of each equipment part must be documented.</p> Signup and view all the answers

    What key component is emphasized during the initial inspection of new rolling stock after the trial period?

    <p>Lubrication and protective devices.</p> Signup and view all the answers

    Why is it important for the driver of a new locomotive to be experienced?

    <p>To provide valuable feedback on the locomotive's performance.</p> Signup and view all the answers

    What is the significance of re-tightening bolts after a new rolling stock has been run for a period?

    <p>It ensures safety and reliability in operation.</p> Signup and view all the answers

    What documentation must be provided by manufacturers for new electric rolling stock?

    <p>Test certificates available in duplicate.</p> Signup and view all the answers

    What should be checked specifically to assess brake functionality during locomotive trials?

    <p>The braking system under both normal and emergency conditions.</p> Signup and view all the answers

    Which components specifically require detailed examination for leakage detection in electric multiple units?

    <p>Interconnecting pneumatic pipe connections and brake equipment</p> Signup and view all the answers

    What formal feedback should be provided after testing a locomotive or EMU?

    <p>A report must be forwarded to manufacturers and RDSO.</p> Signup and view all the answers

    What is necessary for the operation and maintenance of new equipment before dispatching the locomotive?

    <p>Provision of instructions by the manufacturer</p> Signup and view all the answers

    What aspect of the new electric rolling stock is crucial during the testing conducted at the manufacturing units?

    <p>Adherence to tests prescribed by RDSO.</p> Signup and view all the answers

    What is one of the primary focuses of checks performed before commissioning a locomotive or EMU?

    <p>Detailed inspection based on IC schedules.</p> Signup and view all the answers

    During trial runs of a new loco or EMU, who must accompany the operation to observe performance?

    <p>A Driving Inspector and key personnel</p> Signup and view all the answers

    In electric multiple units, what aspect of wiring should be inspected and recorded?

    <p>The insulation resistance of the through wiring</p> Signup and view all the answers

    What requirement is specified for storage of test results and measurements related to locomotive components?

    <p>One copy for reference in the loco shed and one in CEE's office</p> Signup and view all the answers

    What precautions should be taken before the commencement of commercial operation of a new loco or EMU?

    <p>A close watch on performance should be maintained</p> Signup and view all the answers

    What is included in the requirements for the new electric multiple units aside from the driving unit?

    <p>Inspection of inter-coach connection seals</p> Signup and view all the answers

    What should each circuit in electric multiple units be equipped with?

    <p>Individual fuses of correct rating</p> Signup and view all the answers

    Which document is required to assist in troubleshooting new types of locomotives or EMUs before their introduction?

    <p>A trouble-shooting directory</p> Signup and view all the answers

    What factor is essential to monitor during the first few runs of a new loco or EMU?

    <p>The performance of the equipment</p> Signup and view all the answers

    Which of the following conditions are necessary when applying for the authorization of moving new prototype rolling stock?

    <p>Details of the route including special speed and escort conditions.</p> Signup and view all the answers

    What is included in the certificate issued by RDSO for the provisional running of a new locomotive type?

    <p>Provisional speed, type of bridges, and nature of curvature.</p> Signup and view all the answers

    Which of the following factors does NOT influence the classification of a locomotive as a 'New Type'?

    <p>Changes to the locomotive's paint scheme.</p> Signup and view all the answers

    What is required if the new prototype locomotive is over dimensional during its provisional running?

    <p>An appeal for condonation from the Railway Board.</p> Signup and view all the answers

    Which document must support the application to the Chief Operations Manager (COM) for movement authorization of new rolling stock?

    <p>Certification regarding overall dimensions and axle loads from RDSO.</p> Signup and view all the answers

    What role does the Chief Operations Manager (COM) play in the process of inducting new rolling stock?

    <p>Issuing a movement order for the locomotive based on fitness certificates.</p> Signup and view all the answers

    What aspect is crucial in evaluating the new rolling stock's readiness for operation during the first inspection?

    <p>The operational capability under various load conditions.</p> Signup and view all the answers

    What is NOT typically covered by the Provisional Speed Certificate issued by RDSO?

    <p>The expected life cycle of the locomotive.</p> Signup and view all the answers

    Which of these is essential when certifying new rolling stock for movement on Indian Railways (IR) tracks?

    <p>Confirmation of fitness from the manufacturer at unloading.</p> Signup and view all the answers

    What is the primary focus of alterations classified under a 'New Type' of locomotive?

    <p>Enhancing the riding characteristics and electrical system performance.</p> Signup and view all the answers

    Study Notes

    Commissioning of New Electric Locomotives and EMUs

    • Sanction required from CRS for introducing electric traction on any railway or section
    • New type of electric locomotive or EMU includes any alteration affecting riding characteristics (axle load, unsprung mass, suspension systems, load transfer) or signalling system alterations
    • New prototype locomotives/EMUs require certification for safe movement
    • First Stage: One-time movement, requires certification from RDSO (overall dimensions, axle loads, curve radius), manufacturer (fitness to move), and a note on conditions (origin, destination, route, speed, escort)
    • Commissioning of New Type Rolling Stock: COM (Railway) issues movement order based on application and other conditions
    • Second Stage (Provisional Running): RDSO issues Provisional Speed Certificate indicating max speed, track type, curvature, bridge type, axle load, length, ODC dimensions etc.
    • Third Stage (Instrumented Trials): RDSO specifies oscillation (speed, riding quality, stability on straight/curved tracks), braking distance (loads and speeds), interference with signalling, and performance trials
    • Fourth Stage: RDSO issues Final Speed Certificate specifying max speed, precautions. Railway issues speed certificate signed by officials (CE, CEE, CME, CSTE).
    • Final Stage: Railway Board sanctions commercial exploitation
    • Trial Runs on Open Line: Subject to CRS sanction, trial runs are conducted with precautions (senior drivers, low speeds, frequency checks and rectifications)
    • Commissioning of New Electric Rolling Stock: Detailed inspections of newly manufactured locomotives/EMUs by staff; test certificates (results of actual tests), signed by inspecting officers; and manufacturer guarantee/warranty.
    • Electric Multiple Units (EMUs): Similar to locomotives, but also includes interconnecting pneumatic pipe connections and brake equipment checks for each coach, control cable connections, insulation resistance within coaches, and use of individual fuses.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    This quiz focuses on the procedures and requirements for the commissioning of new electric locomotives and EMUs. It covers the steps needed for certification, including movement orders and provisional running conditions. Test your knowledge on the important regulations and technical specifications essential for introducing electric traction in railways.

    More Like This

    Electric Locomotives
    6 questions

    Electric Locomotives

    FresherElectricOrgan avatar
    FresherElectricOrgan
    Electric Locomotives Quiz
    6 questions

    Electric Locomotives Quiz

    FresherElectricOrgan avatar
    FresherElectricOrgan
    Electric Rolling Stock Classification
    82 questions
    Electric Locomotive Maintenance Schedules
    82 questions