CIAP Doc 102: Contract Procedures

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

In the event of conflicting stipulations among contract documents, which document takes precedence?

  • Specifications
  • Daywork Schedule
  • Contract Agreement (correct)
  • Drawings

A contractor discovers a discrepancy in the drawings but performs the affected work before receiving clarification from the Owner/Engineer. What is the likely outcome regarding responsibility for this work?

  • The costs will be shared equally between the contractor and the Owner/Engineer.
  • The Owner/Engineer is responsible for the costs, as they should have provided clearer drawings.
  • The contractor is entitled to compensation for the extra work involved in correcting the discrepancy.
  • The contractor assumes full responsibility for the work and any associated costs. (correct)

Under what condition can a contractor claim for unforeseen physical conditions encountered on-site?

  • If the cost of addressing the conditions exceeds 5% of the original contract value.
  • If the conditions could not have been reasonably foreseen by an experienced contractor after inspecting the site and reviewing available data. (correct)
  • If the conditions cause a minor delay to the project timeline.
  • If the contractor failed to conduct a thorough site inspection before bidding.

What is the timeframe within which a contractor must provide written notice to the Owner/Engineer upon discovering unforeseen physical conditions to maintain their claim?

<p>Within 15 calendar days of discovering the condition. (D)</p> Signup and view all the answers

If a contractor requests an extension of time due to varied work, what is the deadline for submitting this request relative to the cause of the delay?

<p>No later than 30 calendar days after the cause of the delay. (A)</p> Signup and view all the answers

In cases of disagreement regarding contract execution, what is the initial mandatory step both parties should undertake as per CIAP Document 102?

<p>Seek amicable resolution through negotiation. (C)</p> Signup and view all the answers

Under what circumstance can the Owner/Engineer order the Contractor to suspend work, according to Section 9 of CIAP Document 102?

<p>If the Owner/Engineer identifies conditions that warrant such action or if the contractor fails to correct unsafe conditions. (A)</p> Signup and view all the answers

If a work suspension ordered by the Owner/Engineer exceeds 90 calendar days, what recourse does the contractor have if an agreement on adjustments cannot be reached?

<p>The contractor can treat the suspension as a termination by the Owner. (B)</p> Signup and view all the answers

Under what conditions can a contractor terminate a contract, according to CIAP Document 102?

<p>If the Owner suspends the whole work for more than 90 calendar days for their convenience. (A)</p> Signup and view all the answers

Which of the following scenarios would NOT be grounds for the Owner to terminate a contract with a contractor?

<p>The contractor experiences a minor delay due to weather conditions. (A)</p> Signup and view all the answers

If a contract is terminated by the Owner due to the contractor's default, what happens to the materials and equipment the contractor has on-site?

<p>The Owner may take over the materials, equipment, and plant on site for the purpose of completing the Work (B)</p> Signup and view all the answers

What happens if, after the Owner terminates a contract, it is determined that the termination was improper and not justified?

<p>The termination is converted to a termination for convenience of the Owner. (C)</p> Signup and view all the answers

According to CIAP Document 102, what is the interpretation of contract terms and conditions?

<p>Interpreted to maintain its validity; give words their ordinary or technical meaning, and consider trade customs. (A)</p> Signup and view all the answers

When interpreting an ambiguous clause in a construction contract, how is the ambiguity typically resolved?

<p>The ambiguity is interpreted against the party who prepared the contract. (D)</p> Signup and view all the answers

If the Owner/Engineer directs the Contractor to perform varied or extra work, what procedural requirement must be met before the Contractor commences the work?

<p>No varied or extra work will be undertaken by the Contractor without written instruction from the Owner/Engineer. (B)</p> Signup and view all the answers

If the Owner/Engineer and the Contractor cannot reach an agreement on the cost of variations to the work, how is the value of the variations determined?

<p>The Owner/Engineer determines the value, which is final unless the Contractor proves the determination was manifestly wrong. (C)</p> Signup and view all the answers

What happens to a contractor's right to claim an extension of time if they fail to comply with the 30-day notice requirement?

<p>Their right to claim an extension of time is deemed waived. (D)</p> Signup and view all the answers

According to Section 8, what must the contractor ensure in regards to the works?

<p>The contractor is responsible for ensuring the works are not damaged. (A)</p> Signup and view all the answers

In what order of preference should the parties seek to resolve a construction disagreement?

<p>Amicable negotiations, CIAC mediation, and arbitration. (D)</p> Signup and view all the answers

When is the contractor entitled to compensation for increases in the cost of performance caused by the suspension?

<p>Adjustments will be made for increases in the cost of performance caused by the suspension, unless the fault lies within the contractor. (D)</p> Signup and view all the answers

Flashcards

Contract Document Consistency

Contract documents should be consistent and work well together.

Priority of Contract Documents

  1. Contract Agreement, 2. Bid Form, 3. Conditions, 4. Drawings, 5. Specifications, 6. Daywork Schedule, 7. Other Documents

Contract Interpretation Rules

Interpret the contract to keep it valid, words have ordinary/technical meaning, consider trade customs.

Authority to Order Variations

The Owner/Engineer can make changes to the project scope.

Signup and view all the flashcards

Requirement for Written Instructions

Written instruction from the Owner/Engineer is required before starting varied/extra work.

Signup and view all the flashcards

Variation Cost Agreement

The value of variations should be agreed upon with the Owner/Engineer before work begins.

Signup and view all the flashcards

Extension of Time Request Deadline

Contractor has 30 calendar days to request an extension of time after a cause of delay.

Signup and view all the flashcards

Claim for Unforeseen Conditions

Contractor gets extra time/money for unforeseen site issues after site inspection and data review.

Signup and view all the flashcards

Responsibility for Works Protection

Contractor is responsible for protecting the works from damages.

Signup and view all the flashcards

Dispute Resolution Process

Both parties must seek to resolve disagreements amicably, then refer to CIAC for mediation/conciliation, and then initiate arbitration if unsuccessful.

Signup and view all the flashcards

Authority to Suspend Work

The Owner/Engineer can halt the project for safety or contract violations.

Signup and view all the flashcards

Compensation for Suspension Costs

Contractor can get paid more if suspension raises costs, unless contractor is at fault.

Signup and view all the flashcards

Suspension Exceeding 90 Days

If suspension exceeds 90 days and no agreement is reached, contractor can treat it as termination by Owner.

Signup and view all the flashcards

Contractor's Right to Terminate

Contractor can terminate if the work stops for 90+ days without their fault.

Signup and view all the flashcards

Reasons for Contractor Termination

Owner defaults payment, obstructs work, suspends work >90 days, or breaches contract.

Signup and view all the flashcards

Owner's Right to Terminate

The Owner can terminate the contract if the Contractor fails to perform or violates the contract.

Signup and view all the flashcards

Reasons for Owner Termination

Neglect, insolvency, abandonment, unapproved subcontracting, or failure to pay subcontractors/suppliers.

Signup and view all the flashcards

Consequences of Termination by Owner

Owner can finish the work and deduct costs from what's owed to the contractor, who pays if costs exceed earnings.

Signup and view all the flashcards

Improper Owner Termination

Contractor will be paid for all work complete including losses sustained and profit.

Signup and view all the flashcards

Resumption of Work after Suspension

If work is suspended, the Contractor must resume when directed by the Owner/Engineer.

Signup and view all the flashcards

Study Notes

  • CIAP document 102 sections 8 and 9 cover contract procedures.

Section 8: Contract Procedures

  • Section 8 of the CIAP Document 102 outlines the procedures that must be followed during the contract period, including contract interpretation, variations, claims, and dispute resolution.
  • The contract documents must be consistent and complementary.
  • The priority of contract documents is as follows
    • Contract Agreement
    • Bid Form incl. appendices
    • Conditions of Contract
    • Drawings
    • Specifications
    • Daywork Schedule
    • Other Documents
  • If a conflict among the contract documents is present, the priority of these documents will settle the conflict.
  • The interpretation of the contract shall maintain it valid, if possible; give words their ordinary meaning or technical meaning in the construction industry, and consider the customs and usages of the trade.
  • If ambiguity exists, it will be interpreted against the party who prepared the contract.
  • Should discrepancies occur in the drawings, the contractor must immediately refer the matter to the Owner/Engineer for clarification and instructions.
  • Any work done by the contractor after discovering discrepancies, but before receiving instructions, will be at the contractors risk.
  • The Owner/Engineer has the power to order variations to the works.
  • These variations may include alterations, additions or omissions to the works.
  • All varied or extra work which the Contractor may be directed to do must be performed in accordance with the contract terms.
  • No varied or extra work will be undertaken by the Contractor without written instruction from the Owner/Engineer.
  • An agreement must be reached between the Owner/Engineer and the Contractor regarding the cost of the variations.
  • The value of the variations must be agreed upon before they are performed if possible.
  • If an agreement cannot be reached, the Owner/Engineer will determine the value.
  • The determination made by the Owner/Engineer will be final and binding, unless the Contractor can prove that determination was manifestly wrong.
  • If instructions for varied/extra work necessitates the postponement of work, the contractor can apply for an extension of time.
  • No extension of time will be given for trifling reasons.
  • Any request for extension must be made no later than 30 calendar days after the cause of the delay.
  • If the Contractor fails to comply with the 30 day requirement, their right to claim an extension of time is deemed waived.
  • The Contractor must prove that completion of the works will be delayed due to the cause.
  • The Owner/Engineer will examine the facts and determine the extension of time warranted.
  • The contractor is entitled to claim for unforeseen physical conditions or artificial obstructions.
  • This unforeseen event could not have been reasonably foreseen by an experienced contractor, after inspecting the site and reviewing the data given to them.
  • The contractor must give written notice to the Owner/Engineer within 15 calendar days of discovering the condition.
  • The Owner/Engineer will investigate the condition.
  • If the claim is valid, the Owner/Engineer will determine the additional payment and/or extension of time due to the contractor.
  • Any claim for payment must be set out in detail and submitted to the Owner/Engineer.
  • The contractor is responsible for ensuring the works are not damaged.
  • Following completion of the project, the contractor must deliver the works to the Owner in accordance with the contract.
  • In case of disagreement, both parties must seek to resolve it amicably.
  • Either party can request referral of the dispute to the CIAC (Construction Industry Arbitration Commission) for mediation/conciliation.
  • If unsuccessful, either party may initiate arbitration in accordance with the Construction Industry Arbitration Law.

Section 9: Suspension of Work, Termination and Resumption

  • Section 9 of CIAP Document 102 specifies the conditions and procedures for suspension of work, termination of the contract, and resumption of work following a suspension or termination.

Suspension of Work

  • The Owner/Engineer has the authority to order the Contractor to suspend the work, wholly or in part, for a reason and period considered necessary.
  • Reasons for suspension:
    • Failure by the Contractor to correct conditions which are unsafe.
    • Failure to carry out provisions of contract or failure to follow orders.
    • Conditions that warrant such action
  • Adjustments will be made for increases in the cost of performance caused by the suspension.
  • No adjustment of compensation shall be made if performance would have been suspended by other causes, or if the fault lies within the contractor.
  • If the suspension was caused by the contractor, the contractor must pay the owner the amount of expenses caused by the delay to the project completion.
  • If the suspension exceeds 90 calendar days, adjustments should be determined by mutual agreement. Should they fail to agree, the contractor can treat the suspension as a termination by the Owner.

Termination by the Contractor

  • Occurs if the work is completely stopped for more than 90 calendar days through no act or fault of the Contractor or Subcontractors.
  • The contractor can terminate the contract by written notice to the Owner/Engineer.
  • The owner must be paid for reasonable costs of demobilization.
  • The contractor can terminate for the following reasons
    • Owner defaults in paying contractor.
    • Owner interferes with or obstructs the progress of work.
    • Owner suspends the whole work for more than 90 calendar days for their convenience.
    • Owner fails to make payments in accordance with the contract.

Termination by the Owner

  • Occurs if the Contractor neglects or fails to perform the work.
  • Occurs when the contractor violates any provisions of the contract.
  • Contractor becomes insolvent or bankrupt.
  • Contractor makes a general assignment for the benefit of creditors.
  • A receiver is appointed due to the contractor's insolvency.
  • Contractor performs work contrary to the instructions of the Owner/Engineer.
  • Contractor abandons the contract.
  • Contractor subcontracts any part of the contract without approval.
  • Contractor fails to proceed with the work as directed by the Owner/Engineer.
  • Contractor fails to provide sufficient, qualified personnel or materials.
  • Contractor fails to make prompt payments to subcontractors or suppliers.
  • Contractor is found guilty of any offense involving moral turpitude in relation to the contract.
  • Upon termination, the Owner can take over the work and complete it.
  • The contractor is not entitled to receive further payment until the work is finished.
  • All costs of the works completion will be deducted from the contractors earnings.
  • If the expenses exceed the sum which would have been payable, the contractor is liable for the difference.
  • The Owner may take over materials, equipment, and plant on site for the purpose of completing the Work.
  • Termination does not prejudice any rights or remedies available to the Owner.
  • Owner can still go after the contractor to recover damages.
  • If there is sufficient evidence that the contractor was not in default, or that the termination was improper, the termination shall be converted to a termination for convenience of the Owner.
  • In this case, the Contractor will be paid for all work executed and any loss sustained, including reasonable profit.

Resumption of Work

  • If the work is suspended, the Contractor must resume as directed in writing by the Owner/Engineer.
  • If the contract was terminated but later found to be unjustified, the work can be resumed under conditions agreed upon by both the Owner and Contractor.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Like This

Police Contract NON-SUPERVISORS
24 questions
Contract Compliance and Driver Safety Procedures
48 questions
Contract Regulations and Procedures Quiz
10 questions
Use Quizgecko on...
Browser
Browser