Podcast
Questions and Answers
In the event of conflicting stipulations among contract documents, which document takes precedence?
In the event of conflicting stipulations among contract documents, which document takes precedence?
- Specifications
- Daywork Schedule
- Contract Agreement (correct)
- Drawings
A contractor discovers a discrepancy in the drawings but performs the affected work before receiving clarification from the Owner/Engineer. What is the likely outcome regarding responsibility for this work?
A contractor discovers a discrepancy in the drawings but performs the affected work before receiving clarification from the Owner/Engineer. What is the likely outcome regarding responsibility for this work?
- The costs will be shared equally between the contractor and the Owner/Engineer.
- The Owner/Engineer is responsible for the costs, as they should have provided clearer drawings.
- The contractor is entitled to compensation for the extra work involved in correcting the discrepancy.
- The contractor assumes full responsibility for the work and any associated costs. (correct)
Under what condition can a contractor claim for unforeseen physical conditions encountered on-site?
Under what condition can a contractor claim for unforeseen physical conditions encountered on-site?
- If the cost of addressing the conditions exceeds 5% of the original contract value.
- If the conditions could not have been reasonably foreseen by an experienced contractor after inspecting the site and reviewing available data. (correct)
- If the conditions cause a minor delay to the project timeline.
- If the contractor failed to conduct a thorough site inspection before bidding.
What is the timeframe within which a contractor must provide written notice to the Owner/Engineer upon discovering unforeseen physical conditions to maintain their claim?
What is the timeframe within which a contractor must provide written notice to the Owner/Engineer upon discovering unforeseen physical conditions to maintain their claim?
If a contractor requests an extension of time due to varied work, what is the deadline for submitting this request relative to the cause of the delay?
If a contractor requests an extension of time due to varied work, what is the deadline for submitting this request relative to the cause of the delay?
In cases of disagreement regarding contract execution, what is the initial mandatory step both parties should undertake as per CIAP Document 102?
In cases of disagreement regarding contract execution, what is the initial mandatory step both parties should undertake as per CIAP Document 102?
Under what circumstance can the Owner/Engineer order the Contractor to suspend work, according to Section 9 of CIAP Document 102?
Under what circumstance can the Owner/Engineer order the Contractor to suspend work, according to Section 9 of CIAP Document 102?
If a work suspension ordered by the Owner/Engineer exceeds 90 calendar days, what recourse does the contractor have if an agreement on adjustments cannot be reached?
If a work suspension ordered by the Owner/Engineer exceeds 90 calendar days, what recourse does the contractor have if an agreement on adjustments cannot be reached?
Under what conditions can a contractor terminate a contract, according to CIAP Document 102?
Under what conditions can a contractor terminate a contract, according to CIAP Document 102?
Which of the following scenarios would NOT be grounds for the Owner to terminate a contract with a contractor?
Which of the following scenarios would NOT be grounds for the Owner to terminate a contract with a contractor?
If a contract is terminated by the Owner due to the contractor's default, what happens to the materials and equipment the contractor has on-site?
If a contract is terminated by the Owner due to the contractor's default, what happens to the materials and equipment the contractor has on-site?
What happens if, after the Owner terminates a contract, it is determined that the termination was improper and not justified?
What happens if, after the Owner terminates a contract, it is determined that the termination was improper and not justified?
According to CIAP Document 102, what is the interpretation of contract terms and conditions?
According to CIAP Document 102, what is the interpretation of contract terms and conditions?
When interpreting an ambiguous clause in a construction contract, how is the ambiguity typically resolved?
When interpreting an ambiguous clause in a construction contract, how is the ambiguity typically resolved?
If the Owner/Engineer directs the Contractor to perform varied or extra work, what procedural requirement must be met before the Contractor commences the work?
If the Owner/Engineer directs the Contractor to perform varied or extra work, what procedural requirement must be met before the Contractor commences the work?
If the Owner/Engineer and the Contractor cannot reach an agreement on the cost of variations to the work, how is the value of the variations determined?
If the Owner/Engineer and the Contractor cannot reach an agreement on the cost of variations to the work, how is the value of the variations determined?
What happens to a contractor's right to claim an extension of time if they fail to comply with the 30-day notice requirement?
What happens to a contractor's right to claim an extension of time if they fail to comply with the 30-day notice requirement?
According to Section 8, what must the contractor ensure in regards to the works?
According to Section 8, what must the contractor ensure in regards to the works?
In what order of preference should the parties seek to resolve a construction disagreement?
In what order of preference should the parties seek to resolve a construction disagreement?
When is the contractor entitled to compensation for increases in the cost of performance caused by the suspension?
When is the contractor entitled to compensation for increases in the cost of performance caused by the suspension?
Flashcards
Contract Document Consistency
Contract Document Consistency
Contract documents should be consistent and work well together.
Priority of Contract Documents
Priority of Contract Documents
- Contract Agreement, 2. Bid Form, 3. Conditions, 4. Drawings, 5. Specifications, 6. Daywork Schedule, 7. Other Documents
Contract Interpretation Rules
Contract Interpretation Rules
Interpret the contract to keep it valid, words have ordinary/technical meaning, consider trade customs.
Authority to Order Variations
Authority to Order Variations
Signup and view all the flashcards
Requirement for Written Instructions
Requirement for Written Instructions
Signup and view all the flashcards
Variation Cost Agreement
Variation Cost Agreement
Signup and view all the flashcards
Extension of Time Request Deadline
Extension of Time Request Deadline
Signup and view all the flashcards
Claim for Unforeseen Conditions
Claim for Unforeseen Conditions
Signup and view all the flashcards
Responsibility for Works Protection
Responsibility for Works Protection
Signup and view all the flashcards
Dispute Resolution Process
Dispute Resolution Process
Signup and view all the flashcards
Authority to Suspend Work
Authority to Suspend Work
Signup and view all the flashcards
Compensation for Suspension Costs
Compensation for Suspension Costs
Signup and view all the flashcards
Suspension Exceeding 90 Days
Suspension Exceeding 90 Days
Signup and view all the flashcards
Contractor's Right to Terminate
Contractor's Right to Terminate
Signup and view all the flashcards
Reasons for Contractor Termination
Reasons for Contractor Termination
Signup and view all the flashcards
Owner's Right to Terminate
Owner's Right to Terminate
Signup and view all the flashcards
Reasons for Owner Termination
Reasons for Owner Termination
Signup and view all the flashcards
Consequences of Termination by Owner
Consequences of Termination by Owner
Signup and view all the flashcards
Improper Owner Termination
Improper Owner Termination
Signup and view all the flashcards
Resumption of Work after Suspension
Resumption of Work after Suspension
Signup and view all the flashcards
Study Notes
- CIAP document 102 sections 8 and 9 cover contract procedures.
Section 8: Contract Procedures
- Section 8 of the CIAP Document 102 outlines the procedures that must be followed during the contract period, including contract interpretation, variations, claims, and dispute resolution.
- The contract documents must be consistent and complementary.
- The priority of contract documents is as follows
- Contract Agreement
- Bid Form incl. appendices
- Conditions of Contract
- Drawings
- Specifications
- Daywork Schedule
- Other Documents
- If a conflict among the contract documents is present, the priority of these documents will settle the conflict.
- The interpretation of the contract shall maintain it valid, if possible; give words their ordinary meaning or technical meaning in the construction industry, and consider the customs and usages of the trade.
- If ambiguity exists, it will be interpreted against the party who prepared the contract.
- Should discrepancies occur in the drawings, the contractor must immediately refer the matter to the Owner/Engineer for clarification and instructions.
- Any work done by the contractor after discovering discrepancies, but before receiving instructions, will be at the contractors risk.
- The Owner/Engineer has the power to order variations to the works.
- These variations may include alterations, additions or omissions to the works.
- All varied or extra work which the Contractor may be directed to do must be performed in accordance with the contract terms.
- No varied or extra work will be undertaken by the Contractor without written instruction from the Owner/Engineer.
- An agreement must be reached between the Owner/Engineer and the Contractor regarding the cost of the variations.
- The value of the variations must be agreed upon before they are performed if possible.
- If an agreement cannot be reached, the Owner/Engineer will determine the value.
- The determination made by the Owner/Engineer will be final and binding, unless the Contractor can prove that determination was manifestly wrong.
- If instructions for varied/extra work necessitates the postponement of work, the contractor can apply for an extension of time.
- No extension of time will be given for trifling reasons.
- Any request for extension must be made no later than 30 calendar days after the cause of the delay.
- If the Contractor fails to comply with the 30 day requirement, their right to claim an extension of time is deemed waived.
- The Contractor must prove that completion of the works will be delayed due to the cause.
- The Owner/Engineer will examine the facts and determine the extension of time warranted.
- The contractor is entitled to claim for unforeseen physical conditions or artificial obstructions.
- This unforeseen event could not have been reasonably foreseen by an experienced contractor, after inspecting the site and reviewing the data given to them.
- The contractor must give written notice to the Owner/Engineer within 15 calendar days of discovering the condition.
- The Owner/Engineer will investigate the condition.
- If the claim is valid, the Owner/Engineer will determine the additional payment and/or extension of time due to the contractor.
- Any claim for payment must be set out in detail and submitted to the Owner/Engineer.
- The contractor is responsible for ensuring the works are not damaged.
- Following completion of the project, the contractor must deliver the works to the Owner in accordance with the contract.
- In case of disagreement, both parties must seek to resolve it amicably.
- Either party can request referral of the dispute to the CIAC (Construction Industry Arbitration Commission) for mediation/conciliation.
- If unsuccessful, either party may initiate arbitration in accordance with the Construction Industry Arbitration Law.
Section 9: Suspension of Work, Termination and Resumption
- Section 9 of CIAP Document 102 specifies the conditions and procedures for suspension of work, termination of the contract, and resumption of work following a suspension or termination.
Suspension of Work
- The Owner/Engineer has the authority to order the Contractor to suspend the work, wholly or in part, for a reason and period considered necessary.
- Reasons for suspension:
- Failure by the Contractor to correct conditions which are unsafe.
- Failure to carry out provisions of contract or failure to follow orders.
- Conditions that warrant such action
- Adjustments will be made for increases in the cost of performance caused by the suspension.
- No adjustment of compensation shall be made if performance would have been suspended by other causes, or if the fault lies within the contractor.
- If the suspension was caused by the contractor, the contractor must pay the owner the amount of expenses caused by the delay to the project completion.
- If the suspension exceeds 90 calendar days, adjustments should be determined by mutual agreement. Should they fail to agree, the contractor can treat the suspension as a termination by the Owner.
Termination by the Contractor
- Occurs if the work is completely stopped for more than 90 calendar days through no act or fault of the Contractor or Subcontractors.
- The contractor can terminate the contract by written notice to the Owner/Engineer.
- The owner must be paid for reasonable costs of demobilization.
- The contractor can terminate for the following reasons
- Owner defaults in paying contractor.
- Owner interferes with or obstructs the progress of work.
- Owner suspends the whole work for more than 90 calendar days for their convenience.
- Owner fails to make payments in accordance with the contract.
Termination by the Owner
- Occurs if the Contractor neglects or fails to perform the work.
- Occurs when the contractor violates any provisions of the contract.
- Contractor becomes insolvent or bankrupt.
- Contractor makes a general assignment for the benefit of creditors.
- A receiver is appointed due to the contractor's insolvency.
- Contractor performs work contrary to the instructions of the Owner/Engineer.
- Contractor abandons the contract.
- Contractor subcontracts any part of the contract without approval.
- Contractor fails to proceed with the work as directed by the Owner/Engineer.
- Contractor fails to provide sufficient, qualified personnel or materials.
- Contractor fails to make prompt payments to subcontractors or suppliers.
- Contractor is found guilty of any offense involving moral turpitude in relation to the contract.
- Upon termination, the Owner can take over the work and complete it.
- The contractor is not entitled to receive further payment until the work is finished.
- All costs of the works completion will be deducted from the contractors earnings.
- If the expenses exceed the sum which would have been payable, the contractor is liable for the difference.
- The Owner may take over materials, equipment, and plant on site for the purpose of completing the Work.
- Termination does not prejudice any rights or remedies available to the Owner.
- Owner can still go after the contractor to recover damages.
- If there is sufficient evidence that the contractor was not in default, or that the termination was improper, the termination shall be converted to a termination for convenience of the Owner.
- In this case, the Contractor will be paid for all work executed and any loss sustained, including reasonable profit.
Resumption of Work
- If the work is suspended, the Contractor must resume as directed in writing by the Owner/Engineer.
- If the contract was terminated but later found to be unjustified, the work can be resumed under conditions agreed upon by both the Owner and Contractor.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.