Building Construction Preparation Quiz
7 Questions
0 Views

Building Construction Preparation Quiz

Created by
@AdaptiveEllipsis

Questions and Answers

What is the purpose of staking-out a building?

  • To measure the height of the building
  • To drive stakes for batter boards (correct)
  • To lay the brick foundation
  • To construct the building walls
  • What should be done before staking-out?

    Relocate the point of boundaries and property line of the site.

    Batter boards are nailed horizontally at the stake to establish the __________ of the building.

    horizontal plane

    A spirit level is used for vertical line checking.

    <p>False</p> Signup and view all the answers

    What instrument is used for vertical line checks?

    <p>Plumb Bob</p> Signup and view all the answers

    What must be equal when marking the rear corners of a building?

    <p>C-D must be equal to A-B.</p> Signup and view all the answers

    To represent the front building line, a string is stretched between two __________.

    <p>stakes</p> Signup and view all the answers

    Study Notes

    Preparation for Construction Overview

    • Preparation for construction involves several steps to ensure a building is properly erected and conforms to design specifications.

    Staking-Out the Building

    • Staking-out consists of driving stakes into the ground to outline building corners and foundations for excavation.
    • Establish property boundaries before starting the staking process.
    • Required steps:
      • Measure setbacks from front corner monuments.
      • Drive stakes to represent front building line.
      • Measure side setbacks and mark the first and second front corners with stakes.
      • Create right angles using temporary stakes to mark rear corners.
      • Ensure equal measurements in diagonals to maintain proper layout.
    • Tools used: wooden stakes and strings (plastic cords or galvanized wires).

    Laying the Batterboards

    • Batterboards are horizontal boards that define footing trench heights and finish floor levels.
    • The leveling process can be performed with a line level, carpenter’s level, or transit.
    • Batter boards establish a reference point for construction measurements.
    • They should be set level with or slightly above the intended finished foundation height.

    Key Tools for Construction

    • Spirit Level: Ensures lines are both vertical and horizontal during construction.
    • Plumb Bob: Utilized for vertical line checks, consists of a weight on a string.

    Site Preparation Essentials

    • Major parts of a building include foundation bed, formwork, and shoring equipment.
    • Soil mechanics and site drainage play critical roles in site investigation.
    • Excavation and earthworking lay the groundwork for subsequent construction phases.
    • Protective measures for slopes and retaining structures are essential to prevent erosion.

    Pavements

    • Pavement planning is crucial during the early construction stages to ensure proper access and drainage.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz covers essential topics in building construction preparation, including staking out, laying batterboards, and excavation. Test your knowledge on formwork, construction tools, and major parts of a building. Perfect for construction students looking to solidify their understanding of foundational concepts.

    More Quizzes Like This

    Use Quizgecko on...
    Browser
    Browser