AON and AOA Network Diagrams

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

What is an example of lag between two activities in an Activity-on-Node (AON) network?

Waiting for concrete to cure

What are common errors when drawing Activity-on-Node (AON) diagrams?

Not numbering nodes vertically and not putting the arrow on the side of the node.

What are the four main types of logical relationships between construction activities?

Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF).

Describe the Finish-to-Start (FS) relationship between activities.

<p>The following activity cannot start until the previous activity has been completely accomplished.</p> Signup and view all the answers

What is the most common type of relationship between construction activities?

<p>Finish-to-Start (FS)</p> Signup and view all the answers

Describe the Start-to-Start (SS) relationship between activities.

<p>A successor task cannot start until its predecessor task has also started.</p> Signup and view all the answers

Describe the Finish-to-Finish (FF) relationship between activities.

<p>A successor task cannot be completed until its predecessor task has been completed.</p> Signup and view all the answers

Which relationship type abbreviation represents 'Activity A must finish for Activity B to start'?

<p>FS</p> Signup and view all the answers

Which relationship type abbreviation represents 'Activity A must start for Activity B to start'?

<p>SS</p> Signup and view all the answers

Which relationship type abbreviation represents 'Activity A must finish before Activity B can finish'?

<p>FF</p> Signup and view all the answers

What are the key guidelines for building an Activity-on-Node (AON) network diagram?

<p>Use squares or rectangles for activities (nodes). Connect nodes only from the sides, not top or bottom. Do not combine relationship lines. Design the network flowing from left to right. Minimize line crossing for clarity. Start and finish with single, distinct nodes.</p> Signup and view all the answers

What are the four scheduling dates typically calculated for each activity in both AON and AOA networks?

<p>Early Start (ES), Late Start (LS), Early Finish (EF), and Late Finish (LF).</p> Signup and view all the answers

What is the critical path in an AON or AOA network?

<p>The longest sequence of activities through the network diagram.</p> Signup and view all the answers

What are the different types of activity float?

<p>Total Float (TF), Free Float (FF), Interfering Float (INTF), and Independent Float (INDF).</p> Signup and view all the answers

Which types of activity float are most commonly used in construction scheduling?

<p>Total Float and Free Float.</p> Signup and view all the answers

Which type of activity float is rarely used in construction practice?

<p>Independent Float (INDF)</p> Signup and view all the answers

Define Total Float (TF).

<p>The amount of time a task can be delayed without impacting the project's overall completion date.</p> Signup and view all the answers

What are the formulas for calculating Total Float (TF)?

<p>TF = LS - ES or TF = LF - EF</p> Signup and view all the answers

What is the main difference between Total Float and Free Float?

<p>Total Float focuses on the potential delay relative to the overall 'project finish date', whereas Free Float focuses on the potential delay relative to the 'Early Start (ES) date of any successor activity'.</p> Signup and view all the answers

What does 'activity float' represent in project scheduling?

<p>The amount of time an activity can be delayed without delaying the completion date of the project.</p> Signup and view all the answers

What are the advantages of Activity-on-Node (AON) networks compared to Activity-on-Arrow (AOA) networks?

<p>AON allows for more accurate scheduling (especially with complex relationships like SS, FF, SF) and does not require the use of dummy activities. AON often improves project management visualization and communication.</p> Signup and view all the answers

What advantages do network diagrams (AON and AOA) offer compared to simple Bar Charts (Gantt Charts)?

<p>Network diagrams provide a more detailed and visual representation of project dependencies (logical relationships) and scheduling calculations (like float and critical path). This allows for better planning, resource allocation, and risk management.</p> Signup and view all the answers

Name a well-known computer software package used for project scheduling.

<p>Primavera P6</p> Signup and view all the answers

Describe the basic format of an Activity-on-Node (AON) network.

<p>Activities are represented by nodes (typically boxes or circles). Arrows connecting the nodes represent the logical relationships and dependencies between activities.</p> Signup and view all the answers

What are key recommendations for building an Activity-on-Arrow (AOA) network diagram?

<p>Represent the start and end points of activities with nodes (Events). Use arrows to represent the activities, labeled with activity identifiers and duration. Draw arrows to reflect precedence relationships accurately. Use dummy activities (dashed arrows) to show dependencies not representable by regular activity arrows. Number the nodes sequentially after the diagram is completed, ensuring terminal nodes have higher numbers than initial nodes.</p> Signup and view all the answers

What is 'lag' in the context of project scheduling?

<p>A delay or required waiting time imposed between the linked aspects (start or finish) of two related tasks.</p> Signup and view all the answers

What are the primary outputs or purposes of performing forward pass calculations on a project network?

<p>To determine the minimum duration of the project and the earliest time each activity can possibly start (Early Start - ES) and finish (Early Finish - EF).</p> Signup and view all the answers

What is the consequence of a delay occurring in an activity on the critical path?

<p>A delay in any critical path activity will delay the entire project's completion date.</p> Signup and view all the answers

Provide an example of lag between two activities in an Activity-on-Node (AON) network.

<p>Waiting for concrete to cure.</p> Signup and view all the answers

What are the four main types of relationships between construction activities?

<p>Finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), start-to-finish (SF).</p> Signup and view all the answers

Define the finish-to-start (FS) relationship in construction activities.

<p>The successor activity cannot start until the predecessor activity has been completely accomplished.</p> Signup and view all the answers

Define the start-to-start (SS) relationship in construction activities.

<p>A successor task cannot start until its predecessor task has also started.</p> Signup and view all the answers

Define the finish-to-finish (FF) relationship in construction activities.

<p>A successor task cannot be completed until its predecessor task has been completed.</p> Signup and view all the answers

Which relationship abbreviation corresponds to the statement: 'Activity A must finish for Activity B to start'?

<p>FS</p> Signup and view all the answers

Which relationship abbreviation corresponds to the statement: 'Activity A must start for Activity B to start'?

<p>SS</p> Signup and view all the answers

Which relationship abbreviation corresponds to the statement: 'Activity A must finish before Activity B can finish'?

<p>FF</p> Signup and view all the answers

What are the guidelines for constructing an Activity-on-Node (AON) network diagram?

<p>Use squares or rectangles for nodes (activities); connect nodes only from the sides, not top or bottom; do not combine relationship lines; design the network flow from left to right; minimize line crossings; start and finish the network with a single node.</p> Signup and view all the answers

What are the four key dates associated with each activity in construction network scheduling (AON and AOA)?

<p>Early Start (ES), Late Start (LS), Early Finish (EF), Late Finish (LF).</p> Signup and view all the answers

What is the critical path in a project network (AON or AOA)?

<p>The longest sequence of activities through the network diagram.</p> Signup and view all the answers

What are the different types of activity floats calculated in project scheduling?

<p>Total float, free float, interfering float, independent float.</p> Signup and view all the answers

Which two types of activity float are most commonly used in construction project management?

<p>Total float and free float.</p> Signup and view all the answers

Which type of activity float is rarely used in practical construction scheduling?

<p>Independent float.</p> Signup and view all the answers

How does total float differ from free float in terms of focus?

<p>Total float focuses on the potential delay relative to the 'project finish date,' whereas free float focuses on the potential delay relative to the 'Early Start (ES) date of any successor activity.'</p> Signup and view all the answers

In general terms, what is activity float?

<p>The amount of time an activity can be delayed without delaying the completion date of the project.</p> Signup and view all the answers

Compared to simple Bar Charts (Gantt Charts), what advantages do network diagrams like AON and AOA offer?

<p>Network diagrams provide a more detailed and visual representation of project dependencies (precedence relationships) and the critical path, which Bar Charts often don't explicitly show. This allows for better planning, resource allocation, risk management, and understanding of how delays impact the overall schedule.</p> Signup and view all the answers

Name a well-known computer software package used extensively for project scheduling.

<p>Primavera P6.</p> Signup and view all the answers

Describe the basic format of an Activity-on-Arrow (AOA) network.

<p>In AOA networks, activities are represented by arrows, and the nodes (typically circles) at the beginning and end of the arrows represent events (the start or completion of activities).</p> Signup and view all the answers

What are some key recommendations for constructing an Activity-on-Arrow (AOA) network diagram?

<p>Represent the start and end of each activity with nodes (events); use arrows to represent the activities, labeling them with activity identifiers and durations; draw arrows to accurately reflect precedence relationships; use dummy activities (dashed arrows) where necessary to show dependencies without representing actual work; number the event nodes sequentially after the diagram logic is complete (typically left-to-right).</p> Signup and view all the answers

What key information is determined through forward pass calculations in network analysis?

<p>The minimum duration of the project and the earliest time each activity can start (Early Start - ES) and finish (Early Finish - EF).</p> Signup and view all the answers

What is the direct consequence of a delay occurring in any activity on the critical path?

<p>It will delay the completion date of the entire project.</p> Signup and view all the answers

What are common errors made when constructing Activity-on-Node (AON) diagrams?

<p>Not numbering nodes correctly (e.g., not vertically or sequentially) and not placing relationship arrows on the sides of the nodes.</p> Signup and view all the answers

What are the four types of precedence relationships between construction activities?

<p>Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF).</p> Signup and view all the answers

Describe the Finish-to-Start (FS) relationship between construction activities.

<p>The successor activity cannot begin until the predecessor activity is fully completed.</p> Signup and view all the answers

Describe the Start-to-Start (SS) relationship between construction activities.

<p>A successor activity cannot begin until its predecessor activity has also started.</p> Signup and view all the answers

Describe the Finish-to-Finish (FF) relationship between construction activities.

<p>A successor activity cannot be completed until its predecessor activity has also been completed.</p> Signup and view all the answers

Which type of relationship is described by: "Activity A must finish for Activity B to start"?

<p>Finish-to-Start (FS).</p> Signup and view all the answers

Which type of relationship is described by: "Activity A must start for Activity B to start"?

<p>Start-to-Start (SS).</p> Signup and view all the answers

Which type of relationship is described by: "Activity A must finish before Activity B can finish"?

<p>Finish-to-Finish (FF).</p> Signup and view all the answers

List the key guidelines for constructing an Activity-on-Node (AON) network diagram.

<p>Use squares or rectangles for nodes (activities), connect nodes only from the sides, do not combine relationship lines, design the diagram flowing from left to right, minimize line crossings, and ensure the network starts and finishes with a single node.</p> Signup and view all the answers

What are the four key schedule dates associated with each activity in AON and AOA networks?

<p>Early Start (ES), Late Start (LS), Early Finish (EF), and Late Finish (LF).</p> Signup and view all the answers

What is the critical path in an AON or AOA network diagram?

<p>It is the sequence of activities that determines the longest path through the network, representing the minimum project duration.</p> Signup and view all the answers

List the different types of activity float used in project scheduling.

<p>Total Float, Free Float, Interfering Float, and Independent Float.</p> Signup and view all the answers

Which type of activity float is rarely used in construction scheduling?

<p>Independent Float.</p> Signup and view all the answers

Explain the difference between Total Float and Free Float.

<p>Total Float measures the delay possible without affecting the <strong>project finish date</strong>, whereas Free Float measures the delay possible without affecting the <strong>Early Start (ES) date of any successor activity</strong>.</p> Signup and view all the answers

What is activity float in general terms?

<p>It is the amount of time an activity can be delayed beyond its earliest start or earliest finish time without delaying the overall project completion date.</p> Signup and view all the answers

Describe the basic format of an Activity-on-Node (AON) network diagram.

<p>In AON diagrams, activities are represented by nodes (typically rectangles or circles), and the arrows connecting the nodes represent the logical dependencies or relationships between the activities.</p> Signup and view all the answers

In project scheduling, what is lag?

<p>Lag is a mandatory delay or waiting period inserted between the finish or start of a predecessor activity and the start or finish of its successor activity.</p> Signup and view all the answers

What information is determined by performing forward pass calculations on a project network diagram?

<p>Forward pass calculations determine the minimum overall project duration and the earliest possible start (ES) and finish (EF) times for each activity in the network.</p> Signup and view all the answers

What is the consequence of a delay in any activity on the critical path?

<p>A delay in any activity on the critical path will delay the completion date of the entire project.</p> Signup and view all the answers

Flashcards

Lag Example

Waiting for concrete to cure between two activities in an AON network.

AON Diagram Errors

Common mistakes include incorrect vertical node numbering and misplaced arrows.

Activity types

Finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), start-to-finish (SF).

Finish-to-start (FS)

The following activity cannot start until the previous activity is completed.

Signup and view all the flashcards

Common Activity Relationship

Finish-to-start.

Signup and view all the flashcards

Start-to-start (SS)

A successor task cannot start until the predecessor task has also started.

Signup and view all the flashcards

Finish-to-finish (FF)

A successor task cannot be completed until its predecessor task has been completed.

Signup and view all the flashcards

A must finish for B's start

Finish-to-start (FS)

Signup and view all the flashcards

A must start for B's start

Start-to-start (SS)

Signup and view all the flashcards

A must finish before B's finish

Finish-to-finish (FF)

Signup and view all the flashcards

Building AON

Use squares/rectangles for activities, connect only from sides, avoid combining lines, design left to right, minimize crossing lines, and start/finish with one node.

Signup and view all the flashcards

Four Dates of AON/AOA

Early Start (ES), Late Start (LS), Early Finish (EF), Late Finish (LF).

Signup and view all the flashcards

Critical Path

The longest sequence of activities in AON or AOA.

Signup and view all the flashcards

Activity Floats

Total float, free float, interfering float, independent float.

Signup and view all the flashcards

Most Common Activity Floats

Total and free floats.

Signup and view all the flashcards

Rarely Used Float Type

Independent float.

Signup and view all the flashcards

Total Float

The amount of time a task can be delayed without impacting the project's overall completion date.

Signup and view all the flashcards

Total Float Equation

LS-ES or LF-EF.

Signup and view all the flashcards

Total vs. Free Float

Total float concerns 'project finish date,' while free float focuses on the 'ES data of any successor activity.'

Signup and view all the flashcards

Activity Float

Amount of time an activity can be delayed without delaying the project's completion.

Signup and view all the flashcards

Advantages of AON

AON allows for accurate scheduling and you do not have to include dummy activities. AON often improves project management

Signup and view all the flashcards

AON/AOA vs. Bar Charts

Provide detailed visual representation of dependencies and scheduling and allow for better planning and resource allocation

Signup and view all the flashcards

Scheduling Software

Primavera P6.

Signup and view all the flashcards

Format of AOA

Activities are represented by arrows and events are represented by nodes, showing starting and ending points of activities

Signup and view all the flashcards

Building AOA

Represent start/end with nodes, use arrows for activities, label arrows, show precedence, use dummy activities if needed, number nodes after diagram completion.

Signup and view all the flashcards

Lag

Delay or time difference between the completion of one task and the start of a dependent task.

Signup and view all the flashcards

Forward Pass

Calculating the minimum project duration, and earliest start and finish times for each activity.

Signup and view all the flashcards

Backward Pass

Calculating the latest each activity can start and finish without extending the project's duration.

Signup and view all the flashcards

Delay in Critical Path

Delay the entire project.

Signup and view all the flashcards

Study Notes

  • These flashcards cover key concepts related to Activity on Node (AON) and Activity on Arrow (AOA) network diagrams used in project scheduling.

AON Network Basics

  • Activities are represented by nodes (squares or rectangles).
  • Relationships between activities are shown with arrows connecting the nodes.
  • Arrows should connect to the sides of nodes, not the top or bottom.
  • Avoid combining relationship lines and minimize line crossing for clarity.
  • Design the diagram from left to right.
  • Start and finish the network with a single node.
  • Number nodes vertically.

Relationships Between Activities

  • Finish-to-Start (FS): An activity cannot start until the previous activity has finished.
  • Start-to-Start (SS): A successor task cannot start until its predecessor task has also started.
  • Finish-to-Finish (FF): A successor task cannot be completed until its predecessor task has been completed.
  • Start-to-Finish (SF): A must start for B to finish.
  • Finish-to-start is the most common relationship between construction activities.
  • Waiting for concrete to cure is an example of lag between two activities in an AON network.

Dates Associated with Activities

  • Early Start (ES): The earliest time an activity can start.
  • Late Start (LS): The latest time an activity can start without delaying the project.
  • Early Finish (EF): The earliest time an activity can finish.
  • Late Finish (LF): The latest time an activity can finish without delaying the project.

Critical Path

  • The longest sequence of activities in a project network.
  • A delay in the critical path will delay the entire project.

Activity Float (Slack)

  • The amount of time an activity can be delayed without delaying the project completion date.
  • Total Float: The amount of time a task can be delayed without impacting the project's overall completion date.
  • Free Float: The amount of time a task can be delayed without impacting the early start date of any successor activity.
  • Interfering Float
  • Independent Float: Rarely used in construction.
  • Total float focuses on "project finish date".
  • Free float focuses on "ES data of any successor activity".
  • Total Float Equation: LS-ES or LF-EF.

AOA Network Basics

  • Activities are represented by arrows.
  • Events (start and end points of activities) are represented by nodes (circles).
  • Label each arrow with the activity letter and estimated time.
  • Reflect the dependencies between activities with arrows, ensuring the flow of activities is logical and accurate.
  • If needed, use dummy activities (dashed arrows) to show dependencies that are not strictly sequential.
  • Number the nodes after the diagram is completed.

Forward and Backward Pass

  • Forward Pass: Calculates the minimum project duration and the earliest start and finish times for each activity.
  • Backward Pass: Calculates the latest start and finish times for each activity without exceeding the project duration.

Lag

  • Delay or time difference between the completion of one task and the start of a dependent task.

Advantages of AON and AOA Networks

  • Compared to Bar Charts: AON and AOA provide a more detailed and visual representation of project dependencies and scheduling, which allows for better planning, resource allocation, and risk management.
  • AON vs. AOA: AON allows for more accurate scheduling and you do not have to include dummy activities; AON often improves project management.

Scheduling Software

  • Primavera P6 is a well-known computer package for scheduling.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Like This

Aon Malaysia Call Script
40 questions

Aon Malaysia Call Script

SpiritedHammeredDulcimer avatar
SpiritedHammeredDulcimer
Finanza Aziendale: AON e EBITDA
12 questions

Finanza Aziendale: AON e EBITDA

UnequivocalTinWhistle avatar
UnequivocalTinWhistle
Use Quizgecko on...
Browser
Browser