Questions and Answers

What must be displayed at prominent places at each station before energisation?

  • Maintenance schedules of locomotives
  • General caution notices (correct)
  • Energisation plans for public review
  • Historical data on railway safety

What is one of the certifications required before the work is considered complete?

  • Certificate from the environmental agency
  • Certificate from Dy.CEE(G) regarding L.T.& H.T. infringements (correct)
  • Safety compliance certificate from the public
  • Certificate regarding locomotive maintenance

Which of the following notifications should be published at least a month in advance of energisation?

  • Notification for minor track repairs
  • Notification to railway engineers only
  • Notification concerning new train schedules
  • General notification to users of railway lines (correct)

What should be done regarding loco drivers and firemen prior to energisation?

<p>They should be warned against climbing on the roof (B)</p> Signup and view all the answers

Which certificate is specifically required for the anti-theft energisation process?

<p>DOT clearance certificate for 2.2 kV energisation (B)</p> Signup and view all the answers

What is included in the safety certificates that must be obtained?

<p>Joint certificate regarding safety to traffic (C)</p> Signup and view all the answers

What is the purpose of the application to EIG before energisation?

<p>To seek approval for the energisation proposal at 2.2 kV (D)</p> Signup and view all the answers

What must be obtained prior to energisation of the works?

<p>EIG's formal sanction (C)</p> Signup and view all the answers

Who may be nominated for joint checks and tests before energisation of the section?

<p>One of the officers preferably Sr.DEE (TRD) (D)</p> Signup and view all the answers

Which check is required regarding the height of contact wire at level crossings?

<p>It is required to be proper with height gauges provided (B)</p> Signup and view all the answers

What type of tests are conducted on the section after certification for 2.2 kV energisation?

<p>Fault tests on the energized section (B)</p> Signup and view all the answers

What must be ensured during the earth fault tests?

<p>The fuse at the supply point must be blown (A)</p> Signup and view all the answers

What is required regarding earthing and bonding of the OHE?

<p>It must follow the Bonding and Earthing code (A)</p> Signup and view all the answers

Which component must have protective screens provided?

<p>FOB, ROBs, and signalling structures (A)</p> Signup and view all the answers

What is the role of the Dy.CEE(OHE)/RE in the checking process?

<p>To conduct checks and tests prior to energisation (B)</p> Signup and view all the answers

What is the recommended procedure for conducting megger tests?

<p>For continuity and insulation of the OHE (C)</p> Signup and view all the answers

What is required before the OHE can be energised?

<p>All certificates specified in paras 4.2 and 4.3 are obtained (B)</p> Signup and view all the answers

What action should be taken when an abnormality is indicated by the red light?

<p>Direct the operator to take necessary measures (A)</p> Signup and view all the answers

Who is responsible for maintaining the attendance of the operator/lineman?

<p>Assistant Station Master (ASM) (C)</p> Signup and view all the answers

What happens when a defect occurs in the OHE system?

<p>An audible alarm and red light activate (A)</p> Signup and view all the answers

What must personnel possess to approach within 2 meters of the OHE?

<p>Permit to work issued by authorized personnel (C)</p> Signup and view all the answers

Why must the OHE be kept energised continuously?

<p>To deter theft of overhead equipment (D)</p> Signup and view all the answers

What is the initial action that should be taken after energisation?

<p>Issue a notification of energisation (D)</p> Signup and view all the answers

What is the role of the Assistant Station Master (ASM) during an incident?

<p>Coordinate emergency responses and direct actions (C)</p> Signup and view all the answers

What indication confirms normal operation of the OHE?

<p>On green light (B)</p> Signup and view all the answers

What must occur immediately when the OHE contacts earth?

<p>The line must be patrolled and defects quickly rectified (B)</p> Signup and view all the answers

What must the party requiring the 'permit to work' do after completing their work near the OHE?

<p>Return the 'permit to work' in writing to the authorised RE representative. (A)</p> Signup and view all the answers

What action should the ASM take when the L.T. fuse of the transformer blows off due to an accident?

<p>Call for the authorised representative of RE and report the incident. (B)</p> Signup and view all the answers

Which of the following is true about the 'permit to work' in relation to the OHE?

<p>It must be obtained from an authorised supervisor of RE before any work can begin. (D)</p> Signup and view all the answers

What must the supervisor do before energising the OHE after receiving the 'permit to work' back from the patrolling parties?

<p>Ensure that all permits have been handed back to him. (C)</p> Signup and view all the answers

What does the sounding of a buzzer indicate in the ASM room?

<p>An abnormality has occurred with the OHE. (A)</p> Signup and view all the answers

What action should the ASM take when an alarm indicates an abnormality?

<p>Inform the operator and the Supervisor of RE. (A)</p> Signup and view all the answers

What is the role of the RE Controller when a breakdown message is received?

<p>Notify DOM/RE and other relevant personnel. (D)</p> Signup and view all the answers

What must the ASM do after the Supervisor of RE declares the OHE defective?

<p>Advise the Section Controller to issue a caution order. (A)</p> Signup and view all the answers

Who assists the section controller during a breakdown or abnormality?

<p>The RE Controller. (C)</p> Signup and view all the answers

What is the ASM's responsibility when a message is received about a fault location?

<p>Immediately inform the Supervisor of RE and RE controller. (B)</p> Signup and view all the answers

What action should the RE Controller take upon detecting wire cutting?

<p>Inform the ASI/RPF and local police. (B)</p> Signup and view all the answers

What is the primary consideration for the RE Controller when coordinating for the breakdown gang?

<p>Arranging transport with the Section Controller. (C)</p> Signup and view all the answers

What must be executed once the Supervisor of RE verifies an OHE defect?

<p>Alert drivers to watch for track infringements. (C)</p> Signup and view all the answers

Upon which channels should the RE Controller communicate about a breakdown?

<p>Autophone and P&amp;T phone, if necessary. (A)</p> Signup and view all the answers

What is the ASM expected to do regarding sending staff for abnormality repairs?

<p>Send a lineman/operator with contractor staff. (C)</p> Signup and view all the answers

What is the primary time frame during which the 2.2 kV anti-theft energisation is restricted?

<p>7 PM to 7 AM (A)</p> Signup and view all the answers

Which of the following works must be completed before the 2.2 kV anti-theft energisation of OHE?

<p>Provision of automatic tensioning devices (A)</p> Signup and view all the answers

What is the purpose of energising the OHE at 2.2 kV in theft-prone areas?

<p>To avoid theft of contact and catenary wire (B)</p> Signup and view all the answers

In stations with incomplete Bonding and Earthing work, what can be used as an earth wire?

<p>Return conductor (RC) (A)</p> Signup and view all the answers

Which modification is required to comply with 2.2 kV standards before energisation?

<p>Modification of all HT crossings (D)</p> Signup and view all the answers

What safety measure must be taken regarding existing semaphore signals?

<p>Provide protective wire mesh screens (A)</p> Signup and view all the answers

What is necessary for the stringing of catenary and contact wire prior to energisation?

<p>Completion of droppering, clipping, and insulation (B)</p> Signup and view all the answers

What should a Driver do if the hanging OHE wires infringe the standard moving dimensions?

<p>Stop short of the infringement and report to the nearest ASM. (A)</p> Signup and view all the answers

What is the responsibility of the organization manning the 2.2 kV power supply arrangement?

<p>To monitor the operation and ensure safety round the clock (D)</p> Signup and view all the answers

How should a section controller respond to a reported defect in overhead equipment (OHE)?

<p>Issue caution orders to drivers to be alert for obstructions and report findings. (C)</p> Signup and view all the answers

Which of the following is a requirement for personnel approaching within 2 meters of the OHE?

<p>Possess a 'permit to work' issued by an authorized representative (A)</p> Signup and view all the answers

What is prohibited for the crew on the energized sections of the track?

<p>Riding on the top of the engine or tender. (C)</p> Signup and view all the answers

What type of notification is required to be issued for attending to breakdowns?

<p>A joint procedure order outlining specific actions (B)</p> Signup and view all the answers

What action must be taken if a Driver or Guard informs the section controller about hanging OHE wires?

<p>The section controller should immediately inform the RE controller. (B)</p> Signup and view all the answers

What precaution must be taken when conducting works on the OHE?

<p>All works should comply with Indian Electricity Rules (D)</p> Signup and view all the answers

What must be done before any construction work is carried out within two meters of energized OHE?

<p>Obtain a 'permit to work' and ensure the OHE is switched off. (C)</p> Signup and view all the answers

What is included in the provisions for safety at stations and related buildings?

<p>Caution boards and first-aid boxes (C)</p> Signup and view all the answers

Which structure must have protective screens and 25 kV caution boards?

<p>Foot Over Bridges (FOBs) and Rail Over Bridges (ROBs) (C)</p> Signup and view all the answers

What arrangement is required to facilitate 2.2 kV energisation?

<p>A step-up transformer with appropriate fuses (B)</p> Signup and view all the answers

What must occur if an abnormality is detected in the OHE system?

<p>The RE Controller must coordinate a response plan (B)</p> Signup and view all the answers

What indication confirms the normal operation of the OHE?

<p>A steady green light signal in the ASM room (C)</p> Signup and view all the answers

Which of the following statements is NOT a requirement for checking the overhead equipment (OHE) before energisation?

<p>Height gauges for contact wires must be installed at all locations. (A)</p> Signup and view all the answers

What is the purpose of the earth fault tests conducted on the section after the certification for energisation?

<p>To verify the integrity of the OHE under fault conditions. (A)</p> Signup and view all the answers

Which of the following is a step that must be performed prior to the energisation of the section at 2.2 kV?

<p>Obtaining EIG sanction confirming safety measures. (B)</p> Signup and view all the answers

What role does the Dy.CEE(OHE)/RE play in the checks and tests prior to energisation?

<p>He oversees and may authorize the checks and tests, or perform them himself. (A)</p> Signup and view all the answers

Which of the following checks is NOT directly mentioned as part of the required checks before the OHE is energised?

<p>Calibration of the height gauges for overhead sections. (B)</p> Signup and view all the answers

What would NOT be an acceptable method for creating earth faults during testing?

<p>Using an insulated tool to test at the nearest section. (D)</p> Signup and view all the answers

What must be assured when conducting the earth fault tests on the OHE?

<p>That the fuse provided at the supply point blows. (B)</p> Signup and view all the answers

Which procedure must be adhered to when a certification for 2.2 kV energisation is granted?

<p>Fault tests are required even after certification for energisation. (B)</p> Signup and view all the answers

Which of the following statements best describes the necessity for the checks related to earthing and isolation?

<p>They are essential to avoid potential hazards of energised OHE. (B)</p> Signup and view all the answers

What specific type of relay should be ensured as part of the checks before commissioning?

<p>AC immunised track relays. (B)</p> Signup and view all the answers

What should the ASM do if an abnormality is indicated by an alarm or red light?

<p>Immediately notify the operator and inform the Supervisor of RE (D)</p> Signup and view all the answers

What is one of the responsibilities of the RE Controller after receiving a breakdown message?

<p>Assist the Section Controller in informing all concerned (D)</p> Signup and view all the answers

When the Supervisor of RE declares the OHE defective, what is the next immediate action required from the ASM?

<p>Advise the Section Controller to issue a caution order (A)</p> Signup and view all the answers

What must the ASM inform the Section Controller about when a fault location message is received?

<p>To notify the Supervisor of RE and RE Controller (C)</p> Signup and view all the answers

What should the RE Controller do upon receiving information about wire cutting?

<p>Immediately inform the ASI/RPF and local Police (A)</p> Signup and view all the answers

If the Supervisor of RE needs the ASM to arrange transportation for staff, what must the ASM do?

<p>Arrange a light engine or train as required (A)</p> Signup and view all the answers

What should the RE Controller do in coordination with the Section Controller amidst a breakdown?

<p>Assist the breakdown gang in reaching the site (C)</p> Signup and view all the answers

Upon reporting an abnormality, what aspect is critical for the ASM to convey to the Supervisor of RE?

<p>The nature of the abnormality/breakdown immediately (A)</p> Signup and view all the answers

How does the RE Controller ensure comprehensive communication regarding a breakdown?

<p>Using multiple communication methods, including autophone and P&amp;T phone (D)</p> Signup and view all the answers

What action indicates that the ASM is effectively managing an abnormality situation?

<p>Taking immediate orientational steps to relay necessary information (A)</p> Signup and view all the answers

Flashcards

Energization Procedure

A step-by-step process for energizing sections of railway lines, including notification, warnings, and certificate acquisitions.

Public Notifications

Notices published in newspapers (English, Hindi, local languages) about upcoming energization, targeting railway users and level crossing personnel.

Caution Notices

Visible warnings displayed at railway stations and on locomotives to prevent accidents.

Loco Driver Warnings

Specific warnings given to locomotive drivers about climbing on top of engines in energized sections.

Signup and view all the flashcards

Certificates for Energization

Formal documents from different officers confirming completion of work and safety procedures for 2.2 kV energization.

Signup and view all the flashcards

EIG Sanction

Formal approval from the Electrical Infrastructure Group (EIG) for the 2.2 kV energization proposal.

Signup and view all the flashcards

2.2 kV Energization

Process of activating 2.2 kV electrical power as an anti-theft measure on railway infrastructure.

Signup and view all the flashcards

Energization Status

The current state of work completion before energizing a 2.2kV system, including certificates and safety documents.

Signup and view all the flashcards

OHE Energization

Activating overhead electrical equipment (OHE) in a railway section to deter theft.

Signup and view all the flashcards

Prior Requirements for Energization (OHE)

Necessary certificates, DOTs clearance, and EIG sanction are needed before energizing the OHE.

Signup and view all the flashcards

Joint Check & Tests

A coordinated inspection by Railway officials (Sr.DEE and Dy.CEE) before 2.2kV energization to ensure safety standards are met.

Signup and view all the flashcards

Anti-theft Energization

Continuous energization of the OHE wires as a security measure in certain sections.

Signup and view all the flashcards

Live/Earthed Structure Clearance

Checking the space between energized parts and grounded parts, following precise specifications.

Signup and view all the flashcards

Energization Notification

A notification is issued after successful energization of the section (25 kV), following standard procedure.

Signup and view all the flashcards

OHE Earthing & Bonding

Ensuring proper grounding and connection of Overhead Equipments (OHE), according to specific codes, with station area exceptions.

Signup and view all the flashcards

Level Crossing Contact Wire Height

Verifying the correct height of the contact wire above level crossings and having height-gauges available.

Signup and view all the flashcards

Visual and Audible Indicators

Arrangements are made to provide warnings of OHE defects (e.g., red light/buzzer) to controlling staff.

Signup and view all the flashcards

Protective Screens

Checking the presence of protective screens at bridges and signal structures for preventing accidental contact with power lines.

Signup and view all the flashcards

ASM Duties (Anti-theft energization)

Assistant Station Master (ASM) at control stations monitors alarms, directs operators, and maintains staff records.

Signup and view all the flashcards

Defect Handling (OHE)

Damaged equipment must not obstruct traffic, while causes of earthing and defects need immediate rectification.

Signup and view all the flashcards

Adjacent OHE Earthing/Isolation

Ensuring proper grounding and isolation of overhead equipment near the section to be energized.

Signup and view all the flashcards

No Unauthorized Access (energized OHE)

Only authorized personnel with 'permit to work' from the RE (Railway Electrification) are allowed near or on energized OHE within a specific distance (2 meters).

Signup and view all the flashcards

Fault Tests at 2.2kV

Testing the system at 2.2kV by introducing simulated ground faults to ensure the protection system works correctly.

Signup and view all the flashcards

Megger Tests

Measuring continuity and insulation of Overhead Line Equipment (OHE) using a megger.

Signup and view all the flashcards

ASM Action on OHE Defect

ASM (Assistant Station Master) directs operator/lineman when OHE (Overhead Electric Equipment) alarm activates. They inform the RE Supervisor, who then declares the OHE defective. The ASM advises previous stations and all train drivers (up and down) about the defect to take preventive action.

Signup and view all the flashcards

ASM Action on Faulty Section

The ASM at the fault's opposite end dispatches repair staff (lineman/operator & contractor) to address the OHE issue. ASM also informs the Section Controller and RE Controller.

Signup and view all the flashcards

RE Supervisor's Role

Responsible for assessing and confirming OHE faults. They direct ASM actions and initiate train caution orders upon OHE defect confirmation.

Signup and view all the flashcards

RE Controller's Role

The RE Controller supports the Section Controller in the case of a breakdown or anomaly. They inform relevant personnel (DOM/RE, DEE/OHE). They also assist repair crews getting to the site.

Signup and view all the flashcards

ASM Response to Fault Location

If a Section Controller or driver provides a fault location, the ASM immediately informs the RE Supervisor and RE Controller.

Signup and view all the flashcards

ASM Train Stopping for Staff

The ASM arranges a train or light engine stoppage for worker transportation when instructed by the RE Supervisor.

Signup and view all the flashcards

RE Controller's Role in Fault Resolution

The RE Controller stays in contact with Section Controller and ASM to monitor fault resolution. If it's a wire cut, the controller also informs concerned authorities (ASI(RPF), police).

Signup and view all the flashcards

OHE Breakdown Response

When an OHE breakdown happens, specific roles and responsibilities are triggered to identify the affected area and initiate repair and safety precautions in coordination between different departments(RE, Section Controller).

Signup and view all the flashcards

Permit to Work

Formal authorization required for work near overhead equipment (OHE).

Signup and view all the flashcards

OHE Energization

Activating the overhead electrical equipment at 2.2 kV AC.

Signup and view all the flashcards

Work Zone Safety

Safety procedures for activities near electrified overhead equipment (OHE).

Signup and view all the flashcards

Permit Return

Returning the 'permit to work' document after task completion.

Signup and view all the flashcards

Abnormal Operations

Procedures for dealing with accidents or anomalies regarding OHE.

Signup and view all the flashcards

Earthed OHE

Overhead equipment grounded; lose electricity.

Signup and view all the flashcards

Transformer Fault

The low voltage (LT) fuse of the transformer blows off.

Signup and view all the flashcards

ASM Notification

The automated system manager (ASM) receives alerts about faults.

Signup and view all the flashcards

Section Controller Alert

The authorities notify the section controller about the faulty area.

Signup and view all the flashcards

Patrolling Parties

Teams sent to inspect and isolate the faulty zone for safe operation.

Signup and view all the flashcards

Anti-theft energization of OHE

Energizing overhead equipment (OHE) at 2.2 kV to deter theft, primarily at night.

Signup and view all the flashcards

Night hours for energization

Energization is restricted to between 7 PM and 7 AM to prevent affecting train operation and signaling.

Signup and view all the flashcards

Catenary and contact wire

The overhead wires for the train's electric contact.

Signup and view all the flashcards

Structure bonding

Connecting railway structures to the ground for safety.

Signup and view all the flashcards

Return conductor (RC)

Used as an earth wire in some station areas during bonding work.

Signup and view all the flashcards

LT modification works

Necessary changes to low voltage (LT) systems before 2.2 kV energization.

Signup and view all the flashcards

HT crossings modifications

Changing high voltage (HT) crossings to meet 2.2 kV standards

Signup and view all the flashcards

Wire mesh screen

Screens installed at platforms, preventing accidental contact with live conductors.

Signup and view all the flashcards

AC-immunized relays

Safety relays that work with alternating current (AC) systems.

Signup and view all the flashcards

Overhead wire removal/cable conversion

Replacing overhead communication wires with cables.

Signup and view all the flashcards

OHE Energization

Activating overhead electrical equipment (OHE) to deter theft or for use in railway systems.

Signup and view all the flashcards

2.2 kV Energization

Activating 2.2 kV electrical power as an anti-theft measure on railway infrastructure.

Signup and view all the flashcards

Permit to Work

Formal authorization for work near overhead equipment (OHE).

Signup and view all the flashcards

Work Zone Safety

Safety procedures for activities near electrified overhead equipment (OHE).

Signup and view all the flashcards

Anti-theft Energization

Continuous energization of the OHE wires as a security measure in certain sections.

Signup and view all the flashcards

No Unauthorized Access (energized OHE)

Only authorized personnel with 'permit to work' from the RE (Railway Electrification) are allowed near or on energized OHE within a specific distance (2 meters).

Signup and view all the flashcards

Overhead Equipment (OHE)

The electrical equipment (e.g. wires, cables) positioned above the railway tracks.

Signup and view all the flashcards

Local Supply

Power supply available at a specific station.

Signup and view all the flashcards

Step-up Transformer

A transformer that increases the voltage supplied from a lower voltage level to a higher voltage level.

Signup and view all the flashcards

Energization Status

Current state of work completion before energizing a 2.2 kV system, including certificates and safety documents.

Signup and view all the flashcards

EIG Sanction

Formal approval from Electrical Infrastructure Group (EIG) for 2.2 kV energization proposal.

Signup and view all the flashcards

2.2 kV Energization

Activating 2.2 kV electrical power on railway infrastructure.

Signup and view all the flashcards

Joint Check & Tests

Coordinated inspection by Railway officials (Sr.DEE and Dy.CEE) before 2.2kV energization.

Signup and view all the flashcards

Live/Earthed Structure Clearance

Checking space between energized and grounded parts, following specific dimensions.

Signup and view all the flashcards

OHE Earthing & Bonding

Ensuring proper grounding and connection of Overhead Equipment (OHE), following specific codes (with station exceptions).

Signup and view all the flashcards

Level Crossing Contact Wire Height

Verifying the correct height of the contact wire above level crossings and having height gauges.

Signup and view all the flashcards

Protective Screens

Checking the presence of screens at bridges, ROBs, and signal structures.

Signup and view all the flashcards

Adjacent OHE Earthing/Isolation

Ensuring proper grounding and isolation of overhead equipment near the energized section.

Signup and view all the flashcards

Fault Tests at 2.2kV

Testing the system at 2.2kV by introducing simulated ground faults to verify protection system.

Signup and view all the flashcards

Megger Tests

Measuring the continuity and insulation of OHE using a megger.

Signup and view all the flashcards

ASM Action on OHE Defect

The ASM (Assistant Station Master) directs operator/lineman when an OHE (Overhead Electric Equipment) alarm activates. They inform the RE Supervisor, and the ASM advises previous stations and all train drivers (up and down) about the defect to take preventive action.

Signup and view all the flashcards

ASM Action on Faulty Section

The ASM at the fault's opposite end dispatches repair staff (lineman/operator & contractor) to address the OHE issue and informs the Section Controller and RE Controller.

Signup and view all the flashcards

RE Supervisor's Role

Responsible for assessing and confirming OHE faults. Directs ASM actions and initiates train caution orders upon OHE defect confirmation.

Signup and view all the flashcards

RE Controller's Role

The RE Controller supports the Section Controller in case of a breakdown or anomaly. Informs relevant personnel (DOM/RE, DEE/OHE) and assists repair crews getting to the site.

Signup and view all the flashcards

ASM Response to Fault Location

If a Section Controller or driver provides a fault location, the ASM immediately informs the RE Supervisor and RE Controller.

Signup and view all the flashcards

ASM Train Stopping for Staff

The ASM arranges a train or light engine stoppage for worker transportation when instructed by the RE Supervisor.

Signup and view all the flashcards

RE Controller's Role in Fault Resolution

The RE Controller stays in contact with Section Controller and ASM to monitor fault resolution. If it's a wire cut, the controller also informs concerned authorities (ASI(RPF), police).

Signup and view all the flashcards

OHE Breakdown Response

When an OHE breakdown happens, specific roles and responsibilities are triggered to identify the affected area and initiate repair and safety precautions in coordination between different departments(RE, Section Controller).

Signup and view all the flashcards

Permit to Work

Formal authorization needed for work near energized overhead equipment (OHE).

Signup and view all the flashcards

OHE Defect

A malfunction in the overhead equipment. (OHE)

Signup and view all the flashcards

ASM Action (OHE Defect)

ASM notifies supervisor, informs drivers, issues safety alerts, and directs repair crews.

Signup and view all the flashcards

Driver Caution (OHE)

Drivers must proceed carefully when OHE is faulty, watch for hanging wires and report to ASM.

Signup and view all the flashcards

Section Controller's Duty

The Section Controller receives reports of OHE defects, directs caution orders & informs related teams.

Signup and view all the flashcards

RE Controller's Role

The RE Controller assists with fault resolution alongside the Section Controller and informs relevant personnel.

Signup and view all the flashcards

Hanging OHE wires (Standard)

Hanging wires which do not infringe on standard moving dimensions.

Signup and view all the flashcards

Hanging OHE wires (Infringement)

Hanging wires which do infringe on standard moving dimensions.

Signup and view all the flashcards

Permit Return

Returning the permit after work on energized equipment is completed.

Signup and view all the flashcards

Caution Orders

Warnings issued by the ASM for drivers to be cautious of OHE defects.

Signup and view all the flashcards

Study Notes

General Guidelines for Anti-theft Charging of OHE

  • Anti-theft energization of OHE at 2.2 kV is used to prevent theft of contact/catenary wire
  • Energization is only for theft prevention, not train operation, so it doesn't interfere with signals or telecommunications
  • Anti-theft energization is limited to night hours (7 PM to 7 AM)

Works to be Completed Before 2.2 kV Energization

  • Stringing of catenary and contact wire, including droppering, clipping, and insulation, with an automatic tensioning device
  • Structure and rail bonding in accordance with the Bonding and Earthing code is needed
  • Necessary LT modification works must be completed
  • All HT crossings must be modified, meeting standards in Appendix IV
  • Wire mesh screens on semaphore signals, preventing 2 meter clearance issues
  • Replace existing DC track relays with AC-immune relays
  • Convert all track crossings of communication lines to cables and remove overhead wires
  • Install height gauges and 25 kV caution boards at all level crossings
  • Provide protective screens with 25000 V caution boards on structures like bridges, overpasses
  • Install public warning boards, shock treatment charts, and first aid boxes in relevant locations
  • Provide insulated tools for maintenance staff
  • Modify carriage watering arrangements and water columns for anti-theft energization

2.2 kV Power Supply Arrangements

  • Energization will use a local step-up transformer at a station
  • Include a schematic diagram of power supply and controls
  • Plan includes audible and visual indication arrangements
  • Submission to EIG for approval is required
  • 2.2 kV supply arrangement will be operated 24 hours by relevant staff
  • Detailed duty plans for normal operations, breakdowns, and abnormal conditions need to be created.

Procedure for Energization

  • Publish notices of the sections to be energized in prominent local media (including English, Hindi, and local languages) at least a month before energization
  • Include announcements to railway line users and level crossing users regarding energized sections
  • Provide caution notices at all relevant locations (stations, locos, etc.) for workers and public
  • Relevant certificates regarding safety (removal of LT/HT infringements, S&T works, 2.2 kV anti-theft energization clearances etc.) must be obtained from appropriate officers.
  • Ensure adequate safety measures (including appropriate personnel and tools) are in place during energized periods
  • Checks must be completed (live/earthed structures, earthing/bonding, clearances, protection on bridges etc.) before energization

Checks and Tests Before Commissioning

  • Relevant railway authorities should nominate officers to oversee safety checks and tests
  • Checks and tests of the energized section are required and must be documented
  • Necessary clearances between live and earthed structures must be maintained
  • Earthing and bonding of the OHE must meet the required code
  • Check height of contact wire at level crossings, provision of height gauges
  • Ensure that protection screens are in place on FOB's, ROB's, and signalling structures
  • Ensure that earthing and insulation of overhead equipment are carried out properly
  • Ensure that Ac-immunized track relays are in place
  • Overhead P&T and Railway crossings will be cabled
  • Megger tests to ensure continuity and insulation of the OHE
  • Tests to be conducted while section energized (creating earth faults) to determine the safety of the system
  • Obtaining appropriate certificates regarding completion of works, especially for safety purposes

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Description

This quiz covers the essential guidelines for the anti-theft energization of Overhead Equipment (OHE) at 2.2 kV. It includes the necessary works to be completed before the energization process, primarily focusing on prevention measures and compliance with safety standards. Review your knowledge of the required installations and modifications outlined for efficient operation.

More Like This

Anti-terrorism Awareness Training Key Points
28 questions
Anti Money Laundering Quiz
35 questions

Anti Money Laundering Quiz

InvulnerableGold2463 avatar
InvulnerableGold2463
Anti-theft Charging of OHE Guidelines
79 questions
Use Quizgecko on...
Browser
Browser