What is the primary objective of schedule compression?
What is the primary objective of schedule compression?
- To allocate more resources to the project
- To improve the project quality
- To increase the project scope
- To reduce the project duration (correct)
What is the main characteristic of fast-tracking activities?
What is the main characteristic of fast-tracking activities?
- Activities are performed in parallel for their entire duration
- Activities are performed simultaneously with resource allocation
- Activities are performed in a sequence
- Activities are performed in parallel for at least a portion of their duration (correct)
What is the primary benefit of fast-tracking activities?
What is the primary benefit of fast-tracking activities?
- Increased project scope
- Improved project quality
- Reduced project duration (correct)
- Better resource allocation
What is the main difference between fast-tracking and sequential activities?
What is the main difference between fast-tracking and sequential activities?
What is the outcome of fast-tracking activities in a project?
What is the outcome of fast-tracking activities in a project?
What is the primary concern in determining the FS relation?
What is the primary concern in determining the FS relation?
Under what condition do we maintain the FS relation?
Under what condition do we maintain the FS relation?
What is the consequence of task B having to wait for task A to finish?
What is the consequence of task B having to wait for task A to finish?
What is the relationship between tasks A and B in the context of FS relation?
What is the relationship between tasks A and B in the context of FS relation?
When does task B start in the context of FS relation?
When does task B start in the context of FS relation?
What is the primary objective of using schedule compression techniques?
What is the primary objective of using schedule compression techniques?
Which of the following is NOT a schedule compression technique mentioned in the text?
Which of the following is NOT a schedule compression technique mentioned in the text?
What is the key constraint when using schedule compression techniques?
What is the key constraint when using schedule compression techniques?
Which two schedule compression techniques are mentioned in the text?
Which two schedule compression techniques are mentioned in the text?
What is the expected outcome of using schedule compression techniques?
What is the expected outcome of using schedule compression techniques?
What is the primary purpose of having clear metrics in a project?
What is the primary purpose of having clear metrics in a project?
What is the main goal of schedule compression techniques in a project?
What is the main goal of schedule compression techniques in a project?
Which two schedule compression techniques can be used to decrease a project's duration?
Which two schedule compression techniques can be used to decrease a project's duration?
What is the benefit of having clear metrics in a project for team members?
What is the benefit of having clear metrics in a project for team members?
What is the primary focus of Agile development projects?
What is the primary focus of Agile development projects?
What is the ideal situation when completing activity A and activity B?
What is the ideal situation when completing activity A and activity B?
What does lag represent in the context of activities?
What does lag represent in the context of activities?
What is the consequence of lag in a sequence of activities?
What is the consequence of lag in a sequence of activities?
What is the relationship between the completion of activity A and the start of activity B in an ideal situation?
What is the relationship between the completion of activity A and the start of activity B in an ideal situation?
What is the primary characteristic of lag in the context of activities?
What is the primary characteristic of lag in the context of activities?