Workplace Health Hazards and Controls
37 Questions
4 Views

Workplace Health Hazards and Controls

Created by
@LuxuriousPeridot8071

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the initial step in the construction bidding process?

  • Bid Solicitation (correct)
  • Bid Submission
  • Contract Negotiation
  • Bid Evaluation and Selection
  • Which of the following decisions is NOT made before issuing the bid solicitation?

  • Procurement Method
  • Project Delivery Method
  • Contract Type
  • Bid Evaluation Method (correct)
  • What type of information is essential for the owner or general contractors to provide during bid solicitation?

  • Historical data unrelated to the project
  • Estimate of future project costs
  • Complete and accurate project information (correct)
  • Personal preferences and opinions
  • Which document is commonly issued to initiate the bidding process?

    <p>Request for Proposals (RFP)</p> Signup and view all the answers

    In bid solicitation, what should be evaluated to assess bidders effectively?

    <p>Financial statements and personnel resumes</p> Signup and view all the answers

    Which method of tendering allows anyone to submit a tender?

    <p>Open Tendering</p> Signup and view all the answers

    Which of the following is NOT a physical health hazard mentioned?

    <p>Flammable</p> Signup and view all the answers

    What is a control measure recommended for managing psychological health hazards?

    <p>Report bullying and harassment</p> Signup and view all the answers

    Which of the following is a control measure for chemical health hazards?

    <p>Proper storage and handling</p> Signup and view all the answers

    Which statement about COVID-19 control measures is FALSE?

    <p>Always wear a mask covering mouth only</p> Signup and view all the answers

    Which type of tendering is used when a contractor is invited specifically by the employer?

    <p>Negotiated Tendering</p> Signup and view all the answers

    What are the control measures suggested to combat COVID-19 risks?

    <p>Wash hands regularly and get vaccinated</p> Signup and view all the answers

    Which psychological health hazard relates specifically to workplace interactions?

    <p>Work-related stress</p> Signup and view all the answers

    What is the primary characteristic of a Cost Plus Fixed Fee (CPFF) contract?

    <p>The fee is fixed at the inception of the contract and does not vary with actual costs.</p> Signup and view all the answers

    In a Cost Plus Incentive Fee (CPIF) contract, how is the fee adjusted?

    <p>It is adjusted by a formula based on the relationship of total allowable costs to total target costs.</p> Signup and view all the answers

    Which statement best describes a Cost Plus Award Fee (CPAF) contract?

    <p>A base amount is fixed at contract inception with an additional award based on judgmental evaluation.</p> Signup and view all the answers

    What is a major benefit of cost-reimbursable contracts?

    <p>There is no risk of losing money on materials.</p> Signup and view all the answers

    What does a Time and Material (T&M) contract typically involve?

    <p>Payment for materials plus a predetermined hourly wage for labor.</p> Signup and view all the answers

    What is a potential drawback of cost-plus contracts?

    <p>They may require excessive labor costs to track expenses.</p> Signup and view all the answers

    What does the 'plus' in cost-plus contracts typically refer to?

    <p>An agreed-upon amount for profit added to the total costs.</p> Signup and view all the answers

    Which aspect is NOT considered a cost in cost-reimbursable contracts?

    <p>Fixed profit percentages.</p> Signup and view all the answers

    What is the primary benefit of incentive contracts for contractors?

    <p>Extra payments for completing projects early or under budget.</p> Signup and view all the answers

    What is a key drawback associated with incentive contracts?

    <p>They can lead to disputes if terms are unclear.</p> Signup and view all the answers

    What delivery model is characterized by a shared risk/reward system among stakeholders?

    <p>Integrated project delivery contract.</p> Signup and view all the answers

    Which of the following describes a benefit of Integrated Project Delivery (IPD)?

    <p>It promotes teamwork and collaborative culture.</p> Signup and view all the answers

    What is a significant challenge faced by Integrated Project Delivery in the construction industry?

    <p>Some firms may resist participation due to its novelty.</p> Signup and view all the answers

    How do incentive contracts encourage a contractor's performance?

    <p>They reward contractors based on project completion efficiency.</p> Signup and view all the answers

    Which aspect of incentive contracts may require more focus during project initiation?

    <p>Determining achievable terms and conditions.</p> Signup and view all the answers

    What is the primary goal of Integrated Project Delivery (IPD) contracts?

    <p>To ensure all parties pursue common objectives with shared risks.</p> Signup and view all the answers

    What is a significant drawback of time-based contracts?

    <p>They can lead to disputes if prices rise.</p> Signup and view all the answers

    What is a key advantage of using unit price contracts?

    <p>They simplify invoicing and share risks between parties.</p> Signup and view all the answers

    Which of the following correctly describes a disadvantage of unit price contracts?

    <p>They can lead to profit loss if initial estimates are inaccurate.</p> Signup and view all the answers

    What does the BOT scheme involve primarily?

    <p>A private firm building and operating a project before returning it to the government.</p> Signup and view all the answers

    What is a potential risk of the BOT scheme for governments?

    <p>The risk and cost are transferred to a private firm.</p> Signup and view all the answers

    Which projects are likely unsuitable for unit price contracts?

    <p>Highly complex projects with varying tasks and materials.</p> Signup and view all the answers

    What can be a consequence of inaccurate estimates in construction contracts?

    <p>Disputes and potential loss of profit for contractors.</p> Signup and view all the answers

    For what type of project scenarios do time-based contracts often prove to be the most challenging?

    <p>Projects with fluctuating material costs and time variables.</p> Signup and view all the answers

    Study Notes

    Physical Health Hazards

    • Noise, vibration, and slipping/falling are physical health hazards.

    Physical Health Hazards Control Measures

    • Wear headphones to reduce noise exposure, wear anti-vibration gloves, and mop the floor with proper signage to combat physical health risks.

    Chemical Health Hazards

    • Flammable, toxic, and corrosive substances are chemical health hazards.

    Chemical Health Hazards Control Measures

    • Place proper signage, ensure proper storage and handling, and always wear protective equipment to mitigate chemical health risks.

    Psychological Health Hazards

    • Work-related stress, bullying, and sexual harassment are psychological health hazards.

    Psychological Health Hazards Control Measures

    • Manage time properly, report bullying and harassment to management, and discuss the problem to manage psychological health risks.

    COVID-19 Control Measures

    • Monitor and practice social distancing.
    • Sanitize surfaces regularly.
    • Conduct temperature checks upon entry.
    • Sanitize hands regularly.
    • Wear face masks properly, covering both mouth and nose.
    • Wash hands properly and regularly.
    • Get vaccinated.
    • Get booster shots.

    Tendering Methods

    • Open Tendering: Allows anyone to submit a tender; used by both government and private sectors.
    • Selective Tendering: Bidders are invited to submit tenders; suitable for specialized work or equipment.
    • Negotiated Tendering: Employer invites a contractor of their choice; preferred for unique projects or extensions.
    • Serial Tendering: Tenders based on a bill of quantities or schedule of works; used to value results for multiple projects.

    The Construction Bidding Process

    • Step 1: Bid Solicitation: The owner/project team issues a Request for Proposals (RFP) or an Invitation for Bid (IFB).
    • Step 2: Bid Preparation: Bidders prepare their proposals based on the RFP/IFB requirements.
    • Step 3: Bid Submission: Bidders submit their proposals to the owner/project team by the deadline.
    • Step 4: Bid Evaluation & Selection: The owner/project team evaluates bids and selects the best proposal.
    • Step 5: Contract Negotiation & Awarding: The owner/project team negotiates the contract terms with the selected bidder and awards the contract.

    Category of Contract

    • Cost-Reimbursable Contract: Contractor is paid for all actual incurred costs plus a fee for profit.
      • Cost Plus Fixed Fee (CPFF): Contractor receives a fixed fee that doesn't vary with actual cost.
      • Cost Plus Incentive Fee (FPIF): Fee adjusted based on the relationship between actual and target costs.
      • Cost Plus Award Fee (CPAF): Fee consists of a fixed base amount and an award based on evaluation.

    Time and Material Contract (T&M)

    • A hybrid contract combining elements of cost-reimbursable and fixed-price contracts; used when costs are uncertain.

    Cost-Plus Contract

    • Contractor is paid for all expenses plus a profit margin.
      • Benefits: No risk of losing money on materials, guaranteed profit.
      • Drawbacks: Can include "not to exceed" clauses for costs, requiring extra labor to track expenses.

    Incentive Construction Contract

    • Contractor receives an agreed-upon payment if the project is delivered by a certain date and at a specific point.
      • Benefits: Encourages cost control and on-time delivery, promotes collaboration.
      • Drawbacks: Requires negotiation to determine incentives, unclear terms can lead to disputes.

    Integrated Project Delivery (IPD) Contract

    • A multi-party agreement with a shared risk/reward model, guaranteed costs, and collaborative culture.
      • Benefits: Prioritizes innovation and collaboration, spreads risk and reward fairly.
      • Drawbacks: Relatively new, may not be embraced by all design firms and subcontractors, less transparency on final cost.

    Unit Price Contract

    • Details prices per unit, including materials, labor, overhead, and profit.
      • Benefits: Works well with projects easily divided into units, simple invoicing, shared risk.
      • Drawbacks: Not suitable for complex projects with varied tasks, doesn't incentivize contractors.

    Build-Operate-Transfer (BOT) Contract

    • A public entity grants a private firm the rights to build and operate a project and then transfers control back after a set timeframe.
      • Benefits: Enables governments to transfer project costs and risks to private entities, potential for profit for the private firm.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    This quiz covers various health hazards in the workplace, including physical, chemical, and psychological risks. It also outlines effective control measures to mitigate these hazards, including precautions for COVID-19. Test your knowledge on maintaining a safe work environment!

    More Like This

    Hospitality Industry Terminology
    15 questions
    Contingencias en Salud Ocupacional
    10 questions
    Segurança no Trabalho
    4 questions
    Use Quizgecko on...
    Browser
    Browser