Urgency Certificate in Construction

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Who can issue an urgency certificate?

  • Any governmental body
  • Any individual
  • The authority ordering to undertake a work (correct)
  • A local merchant

What is the purpose of an urgency certificate?

  • To prevent work from starting
  • To allocate more funds than necessary
  • To delay a work
  • To start a work immediately without preparation (correct)

For what reasons may an urgency certificate be issued?

  • To reduce costs
  • To cover up delays
  • To improve worker efficiency
  • To safeguard life or property or to prevent damage to the track (correct)

Who needs to be informed about the commencement of work under an urgency certificate?

<p>The authority competent to give administrative approval (C)</p> Signup and view all the answers

What is required to be included in the report made in form no. 1104?

<p>Description of the work, date of commencement, and circumstances (B)</p> Signup and view all the answers

What form is used for preparing the report after the issue of an urgency certificate?

<p>Form no. 1104 (A)</p> Signup and view all the answers

Flashcards are hidden until you start studying

Study Notes

Urgency Certificate

  • Issued by the authority to undertake work before preparing and sanctioning detailed estimates, when necessary.
  • Explains the urgency necessitating immediate action.
  • May be issued for works that are urgently necessary to:
    • Safeguard life or property.
    • Prevent damage to the track caused by:
      • Flood.
      • Accident.
      • Other unforeseen contingencies.
  • Executive authority may permit commencement of work, but must:
    • Send a report to the authority competent to give administrative approval.
    • Request allocation of required funds.
  • Report (Form No. 1104) must contain:
    • Description of the work.
    • Date of commencement.
    • Circumstances.
    • Maximum probable unit with an abstract of calculations.
    • Date by which the detailed estimate can be submitted.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Like This

Construction Project Management Fundamentals
10 questions
17 questions

IllustriousConstellation avatar
IllustriousConstellation
Construction Project Planning Quiz
32 questions