During which phase of the project are the client's requirements transformed into physical, architectural form?
During which phase of the project are the client's requirements transformed into physical, architectural form?
- Schematic design phase (correct)
- Construction phase
- Pre-design phase
- Design development phase
What is the purpose of the schematic design phase?
What is the purpose of the schematic design phase?
- To transform the results of pre-design investigations into a concept of what will be built (correct)
- To develop a well-thought-out program
- To test the client's program
- To explore how the building will be constructed
Why is it important to complete the pre-design phase before initiating schematic design?
Why is it important to complete the pre-design phase before initiating schematic design?
- To ensure a well-thought-out program (correct)
- To synthesize various requirements
- To explore planning and massing relationships
- To avoid cost overruns
Which one of the following is a key characteristic of the integrated design team (IDT) approach?
Which one of the following is a key characteristic of the integrated design team (IDT) approach?
During the schematic design stage, what is the benefit of integrating sensitive site development, building envelope characteristics, and mechanical and electrical systems?
During the schematic design stage, what is the benefit of integrating sensitive site development, building envelope characteristics, and mechanical and electrical systems?
What is one method to document design decisions during the schematic design stage?
What is one method to document design decisions during the schematic design stage?
What is the purpose of the schematic design phase?
What is the purpose of the schematic design phase?
According to the text, what is the role of the architect in managing communication during the design process?
According to the text, what is the role of the architect in managing communication during the design process?
According to the text, why might some clients be reluctant to sign off on design decisions?
According to the text, why might some clients be reluctant to sign off on design decisions?
According to the text, what is the responsibility of the client in a fast-tracked project?
According to the text, what is the responsibility of the client in a fast-tracked project?
According to the text, what is the architect's role if the client does not have all the pre-design documentation?
According to the text, what is the architect's role if the client does not have all the pre-design documentation?
Which of the following is a key requirement of the integrated design process (IDP)?
Which of the following is a key requirement of the integrated design process (IDP)?
During the schematic design phase, the architect coordinates with which of the following disciplines?
During the schematic design phase, the architect coordinates with which of the following disciplines?
What is the purpose of design alternatives in the schematic design phase?
What is the purpose of design alternatives in the schematic design phase?
What is an important aspect of building information modeling (BIM) processes?
What is an important aspect of building information modeling (BIM) processes?
According to the text, why might the architect request that the client retain independent specialists?
According to the text, why might the architect request that the client retain independent specialists?
What should be the understanding between the architect and the client if some information remains unknown?
What should be the understanding between the architect and the client if some information remains unknown?
Why might a client want all services related to a project to be provided by a single source?
Why might a client want all services related to a project to be provided by a single source?
What is the general principle the architect should reinforce to the owner regarding risks associated with ownership?
What is the general principle the architect should reinforce to the owner regarding risks associated with ownership?
During the schematic design phase, the architect prepares preliminary cost evaluations based on the area or volume of the proposed building multiplied by the appropriate regional unit costs. If the client's expectations cannot be met within the proposed budget, the architect may need to adjust the scope of work and/or the quality, or the client may decide to increase the budget or abandon the project.
During the schematic design phase, the architect prepares preliminary cost evaluations based on the area or volume of the proposed building multiplied by the appropriate regional unit costs. If the client's expectations cannot be met within the proposed budget, the architect may need to adjust the scope of work and/or the quality, or the client may decide to increase the budget or abandon the project.
What is the purpose of the design presentation documents during the schematic design phase?
What is the purpose of the design presentation documents during the schematic design phase?
Which document should the architect obtain formal, written approval from the client before beginning design development?
Which document should the architect obtain formal, written approval from the client before beginning design development?
What is the purpose of the Canadian Standard Forms of Contract for Architectural Services RAIC Document Six?
What is the purpose of the Canadian Standard Forms of Contract for Architectural Services RAIC Document Six?