Podcast
Questions and Answers
Which of the following best describes a project?
Which of the following best describes a project?
- An activity with a unique objective (correct)
- A project has no objective
- A continuous production process
- A repetitive production process
Which of the following is NOT a phase of the project development cycle?
Which of the following is NOT a phase of the project development cycle?
- Operational phase
- Pre-investment phase
- Investment phase
- Planning phase (correct)
During which phase of the project development cycle do important industrial activities take place?
During which phase of the project development cycle do important industrial activities take place?
- Pre-investment phase
- Investment phase (correct)
- Operational phase
- Planning phase
What are the major tools used to combat overruns in a project?
What are the major tools used to combat overruns in a project?
Which of the following is NOT a general cause of project overruns during the Evaluation Phase?
Which of the following is NOT a general cause of project overruns during the Evaluation Phase?
What is the time overrun of the Vizag Steel Project?
What is the time overrun of the Vizag Steel Project?
Which of the following is NOT a factor responsible for the failure of the Power Sector projects mentioned?
Which of the following is NOT a factor responsible for the failure of the Power Sector projects mentioned?
What is the cost overrun of the Polystaple Fibre Plant project in Bongaigaon?
What is the cost overrun of the Polystaple Fibre Plant project in Bongaigaon?
Which one of these is a main component of project management?
Which one of these is a main component of project management?
What is the purpose of project management?
What is the purpose of project management?
What are the general causes of overruns in projects?
What are the general causes of overruns in projects?
What are the different phases of the project development cycle?
What are the different phases of the project development cycle?
Which sector has suffered from a significant delay and cost overrun in the Moonidih Underground Project?
Which sector has suffered from a significant delay and cost overrun in the Moonidih Underground Project?
What is the major objective of this unit?
What is the major objective of this unit?
What is the total outlay of the Eighth Plan (1992-97)?
What is the total outlay of the Eighth Plan (1992-97)?
When did the development process in India, using science, technology, engineering, and construction, begin?
When did the development process in India, using science, technology, engineering, and construction, begin?
Which stage of a large engineering and construction project involves obtaining various clearances and approvals?
Which stage of a large engineering and construction project involves obtaining various clearances and approvals?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
Which stage of UNIDO's project coincides with the Government of India's practice of three stage project scrutiny?
Which stage of UNIDO's project coincides with the Government of India's practice of three stage project scrutiny?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
Which of the following documents are necessary for the preparation of a Detailed Project Report (DPR)?
Which of the following documents are necessary for the preparation of a Detailed Project Report (DPR)?
What is the time limit for submitting the DPR after TEFR clearance?
What is the time limit for submitting the DPR after TEFR clearance?
What is the main difference between a TEFR and a DPR?
What is the main difference between a TEFR and a DPR?
What is one of the requirements for developing a DPR from a TEFR?
What is one of the requirements for developing a DPR from a TEFR?
What must be indicated in a Detailed Project Report?
What must be indicated in a Detailed Project Report?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
Which of the following is NOT an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
Which of the following is NOT an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
Which of the following is NOT a financial viability factor to be examined closely before deciding on investment?
Which of the following is NOT a financial viability factor to be examined closely before deciding on investment?
Which of the following is NOT a phase of the project development cycle?
Which of the following is NOT a phase of the project development cycle?
What is the main objective of project management?
What is the main objective of project management?
What are the general causes of overruns in projects?
What are the general causes of overruns in projects?
During which phase of the project development cycle do important industrial activities take place?
During which phase of the project development cycle do important industrial activities take place?
Which of the following is NOT a general cause of overruns in projects?
Which of the following is NOT a general cause of overruns in projects?
What is the cost overrun of the Bokaro expansion project?
What is the cost overrun of the Bokaro expansion project?
What is the time overrun of the Dulhasti project?
What is the time overrun of the Dulhasti project?
What is the estimated cost of the Panchat II project?
What is the estimated cost of the Panchat II project?
Which of the following is NOT a factor considered in the pre-feasibility report for a project?
Which of the following is NOT a factor considered in the pre-feasibility report for a project?
What is the accuracy level of the definitive estimate in a project?
What is the accuracy level of the definitive estimate in a project?
Which government organization provides guidance and assistance to entrepreneurs in India?
Which government organization provides guidance and assistance to entrepreneurs in India?
What is the purpose of the project formulation report or pre-feasibility report?
What is the purpose of the project formulation report or pre-feasibility report?
Which of the following is NOT a reason why a feasibility study is important for the success of a project?
Which of the following is NOT a reason why a feasibility study is important for the success of a project?
What is the main objective of the pre-investment phase of an industrial project?
What is the main objective of the pre-investment phase of an industrial project?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
What is the cost overrun of the Moonidih Underground Project in the Coal Sector?
What is the cost overrun of the Moonidih Underground Project in the Coal Sector?
Which one of the following is NOT a phase of the project development cycle?
Which one of the following is NOT a phase of the project development cycle?
What is the purpose of project management?
What is the purpose of project management?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
What are the general causes of overruns in projects?
What are the general causes of overruns in projects?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
Which of the following best describes a project?
Which of the following best describes a project?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
Which of the following documents is NOT necessary for the preparation of a Detailed Project Report (DPR)?
Which of the following documents is NOT necessary for the preparation of a Detailed Project Report (DPR)?
What is the time limit for submitting the Detailed Project Report (DPR) after TEFR clearance?
What is the time limit for submitting the Detailed Project Report (DPR) after TEFR clearance?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What must be indicated in a Detailed Project Report (DPR)?
What must be indicated in a Detailed Project Report (DPR)?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
Which sector experienced a significant cost overrun in the Narora Atomic Power Plant project?
Which sector experienced a significant cost overrun in the Narora Atomic Power Plant project?
What was the estimated total cost of the Narora Atomic Power Plant project?
What was the estimated total cost of the Narora Atomic Power Plant project?
What is the capacity of the Moonidih Underground Project in the Coal Sector?
What is the capacity of the Moonidih Underground Project in the Coal Sector?
How many years of delay did the Moonidih Underground Project in the Coal Sector experience?
How many years of delay did the Moonidih Underground Project in the Coal Sector experience?
What are the three major phases of the project development cycle?
What are the three major phases of the project development cycle?
What are the stages that each major phase of the project development cycle is divisible into?
What are the stages that each major phase of the project development cycle is divisible into?
What are the activities involved in implementing a project before the start of construction activity?
What are the activities involved in implementing a project before the start of construction activity?
What distinguishes a project from repetitive or continuous production processes?
What distinguishes a project from repetitive or continuous production processes?
Which of the following is NOT a general cause of project overruns during the Contracting and Procurement Phase?
Which of the following is NOT a general cause of project overruns during the Contracting and Procurement Phase?
What is the time overrun of the Dulhasti project?
What is the time overrun of the Dulhasti project?
What are the major causes of overruns in the Steel sector projects?
What are the major causes of overruns in the Steel sector projects?
What are the main factors responsible for the overruns in the Power Sector projects?
What are the main factors responsible for the overruns in the Power Sector projects?
Which of the following is a component of project management?
Which of the following is a component of project management?
What is the purpose of project management?
What is the purpose of project management?
What are the different phases of the project development cycle?
What are the different phases of the project development cycle?
What is the importance of feasibility study?
What is the importance of feasibility study?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
Which of the following is an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
Which of the following is an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
What are the financial viability factors to be examined closely before deciding on investment?
What are the financial viability factors to be examined closely before deciding on investment?
Which documents are necessary for the preparation of a Detailed Project Report (DPR)?
Which documents are necessary for the preparation of a Detailed Project Report (DPR)?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
What is the time limit for submitting the DPR after TEFR clearance?
What is the time limit for submitting the DPR after TEFR clearance?
What is one of the requirements for developing a DPR from a TEFR?
What is one of the requirements for developing a DPR from a TEFR?
What must be indicated in a Detailed Project Report (DPR)?
What must be indicated in a Detailed Project Report (DPR)?
What is the level of accuracy required for preparing filmed-up estimates with about 15 percent accuracy for DPR?
What is the level of accuracy required for preparing filmed-up estimates with about 15 percent accuracy for DPR?
Which stage of project development involves obtaining various clearances and approvals?
Which stage of project development involves obtaining various clearances and approvals?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
What is the accuracy level of the definitive estimate in a project?
What is the accuracy level of the definitive estimate in a project?
What is the purpose of a pre-feasibility report?
What is the purpose of a pre-feasibility report?
Which of the following accurately describes a project?
Which of the following accurately describes a project?
What are the three major phases of the project development cycle?
What are the three major phases of the project development cycle?
What is the purpose of a Detailed Project Report (DPR)?
What is the purpose of a Detailed Project Report (DPR)?
What is the main cause of overruns in projects?
What is the main cause of overruns in projects?
Which sector experienced a cost overrun of Rs. 535 crore and a delay of more than 10 years in the Narora Atomic Power Plant project?
Which sector experienced a cost overrun of Rs. 535 crore and a delay of more than 10 years in the Narora Atomic Power Plant project?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
What is the capacity of the Moonidih Underground Project in the Coal Sector?
What is the capacity of the Moonidih Underground Project in the Coal Sector?
What is the estimated cost of the Panchat II project?
What is the estimated cost of the Panchat II project?
Which of the following is NOT a phase of the project development cycle?
Which of the following is NOT a phase of the project development cycle?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
What are the general causes of overruns in projects?
What are the general causes of overruns in projects?
Why do you think project management is essential to achieve project success?
Why do you think project management is essential to achieve project success?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
What is the purpose of a Techno-economic feasibility report?
What is the purpose of a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in a Techno-economic feasibility report?
What are the angles from which the total financial viability of a project is examined closely?
What are the angles from which the total financial viability of a project is examined closely?
Which factor contributed to the delay in finalizing technology and equipment in the recordbreaking project failure example mentioned in the text?
Which factor contributed to the delay in finalizing technology and equipment in the recordbreaking project failure example mentioned in the text?
What were the root causes of the colossal overruns experienced by the Vizag Steel Project in the Steel sector?
What were the root causes of the colossal overruns experienced by the Vizag Steel Project in the Steel sector?
Which two expansion projects had significant time overruns and cost overruns in the Steel sector?
Which two expansion projects had significant time overruns and cost overruns in the Steel sector?
What were the main factors responsible for the delay and cost overruns in the hydroelectric projects mentioned in the Power sector?
What were the main factors responsible for the delay and cost overruns in the hydroelectric projects mentioned in the Power sector?
Which of the following is NOT a stage in the project development cycle?
Which of the following is NOT a stage in the project development cycle?
What are the three stages of project scrutiny according to the Government of India?
What are the three stages of project scrutiny according to the Government of India?
What is the objective of appraisals in the various stages of project evolution and decision-making?
What is the objective of appraisals in the various stages of project evolution and decision-making?
What is the accuracy level required for preparing detailed estimates in the project development cycle?
What is the accuracy level required for preparing detailed estimates in the project development cycle?
Which of the following is NOT a requirement for developing a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
Which of the following is NOT a requirement for developing a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
What is the time limit for submitting a DPR after TEFR clearance?
What is the time limit for submitting a DPR after TEFR clearance?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy for a DPR?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy for a DPR?
What must be indicated in a Detailed Project Report (DPR) regarding procurement of materials?
What must be indicated in a Detailed Project Report (DPR) regarding procurement of materials?
What are the vital aspects that need to be reported on in a Detailed Project Report (DPR)?
What are the vital aspects that need to be reported on in a Detailed Project Report (DPR)?
Which of the following is NOT a stage in the project development cycle?
Which of the following is NOT a stage in the project development cycle?
What is the accuracy level of the definitive estimate in a project?
What is the accuracy level of the definitive estimate in a project?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
What are the major causes of overruns in the Steel sector projects?
What are the major causes of overruns in the Steel sector projects?
What is the cost overrun of the Bokaro expansion project?
What is the cost overrun of the Bokaro expansion project?
What is the time overrun of the Dulhasti project in J & K in the Power Sector?
What is the time overrun of the Dulhasti project in J & K in the Power Sector?
What are the main factors responsible for the failure of the Power Sector projects mentioned?
What are the main factors responsible for the failure of the Power Sector projects mentioned?
What is the time overrun of the Panchat II project in Bihar in the Power Sector?
What is the time overrun of the Panchat II project in Bihar in the Power Sector?
Which of the following is NOT a requirement for the success of a project?
Which of the following is NOT a requirement for the success of a project?
What is the purpose of a feasibility study?
What is the purpose of a feasibility study?
What is the major objective of the unit on pre-investment phase?
What is the major objective of the unit on pre-investment phase?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
What is the total financial outlay invested in development projects from 1951 to 1989-90?
Which of the following is NOT a phase of the project development cycle?
Which of the following is NOT a phase of the project development cycle?
What are the three stages of project scrutiny according to the Government of India?
What are the three stages of project scrutiny according to the Government of India?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
Which of the following is NOT an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
Which of the following is NOT an incentive offered by the Industries and Commerce Department of several State Governments for rapid industrial development?
What is the purpose of project management in achieving project success?
What is the purpose of project management in achieving project success?
What are the main components of project management?
What are the main components of project management?
What are the general causes of cost overruns in projects?
What are the general causes of cost overruns in projects?
What are the different phases of the project development cycle?
What are the different phases of the project development cycle?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
Which of the following is NOT a component typically included in a Techno-economic feasibility report?
What is the purpose of the project formulation report or pre-feasibility report?
What is the purpose of the project formulation report or pre-feasibility report?
What are the general causes of overruns in projects?
What are the general causes of overruns in projects?
What is the accuracy level of the definitive estimate in a project?
What is the accuracy level of the definitive estimate in a project?
Which of the following documents are necessary for the preparation of a Detailed Project Report (DPR)?
Which of the following documents are necessary for the preparation of a Detailed Project Report (DPR)?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What is the time limit for submitting a Detailed Project Report (DPR) after TEFR clearance?
What is the time limit for submitting a Detailed Project Report (DPR) after TEFR clearance?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What must be indicated in a Detailed Project Report (DPR) regarding procurement of materials?
What must be indicated in a Detailed Project Report (DPR) regarding procurement of materials?
What are the three main requirements to develop a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
What are the three main requirements to develop a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
Which of the following is NOT a phase in the project development cycle?
Which of the following is NOT a phase in the project development cycle?
What is the purpose of a feasibility study?
What is the purpose of a feasibility study?
What is the estimated cost of the Polystaple Fibre Plant project in Bongaigaon?
What is the estimated cost of the Polystaple Fibre Plant project in Bongaigaon?
What are the main components of project management?
What are the main components of project management?
Which of the following is NOT a general cause of overruns in projects?
Which of the following is NOT a general cause of overruns in projects?
What is the time overrun of the Vizag Steel Project mentioned in the text?
What is the time overrun of the Vizag Steel Project mentioned in the text?
What is the cost overrun of the Polystaple Fibre Plant construction in Bongaigaon mentioned in the text?
What is the cost overrun of the Polystaple Fibre Plant construction in Bongaigaon mentioned in the text?
What is the estimated cost of the Dulhasti project in J & K mentioned in the text?
What is the estimated cost of the Dulhasti project in J & K mentioned in the text?
Which sector in India has seen substantial economic growth through industrial and infrastructural development projects since independence?
Which sector in India has seen substantial economic growth through industrial and infrastructural development projects since independence?
What is the estimated cost overrun for the Narora Atomic Power Plant project in the Atomic Energy Sector?
What is the estimated cost overrun for the Narora Atomic Power Plant project in the Atomic Energy Sector?
What is the purpose of a feasibility study in the pre-investment phase of a project?
What is the purpose of a feasibility study in the pre-investment phase of a project?
What is the total financial outlay invested in development projects in India from 1951 till 1989-90?
What is the total financial outlay invested in development projects in India from 1951 till 1989-90?
Which stage of the project development cycle is the Techno-economic Feasibility Report (TEFR) prepared?
Which stage of the project development cycle is the Techno-economic Feasibility Report (TEFR) prepared?
What is the purpose of the Techno-economic Feasibility Report (TEFR)?
What is the purpose of the Techno-economic Feasibility Report (TEFR)?
What are the major components typically included in a Techno-economic feasibility report?
What are the major components typically included in a Techno-economic feasibility report?
What is the usual practice to prepare capital cost estimates in the Techno-economic Feasibility Report (TEFR) stage?
What is the usual practice to prepare capital cost estimates in the Techno-economic Feasibility Report (TEFR) stage?
Which of the following is NOT a phase of the project development cycle?
Which of the following is NOT a phase of the project development cycle?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What are the angles from which the total financial viability of a project is examined closely?
What are the angles from which the total financial viability of a project is examined closely?
Which of the following is the most accurate estimate of cost accuracy for a preliminary control estimate?
Which of the following is the most accurate estimate of cost accuracy for a preliminary control estimate?
What is the purpose of a pre-feasibility report?
What is the purpose of a pre-feasibility report?
What are the major activities involved in a large engineering and construction project?
What are the major activities involved in a large engineering and construction project?
What are the stages of project development according to UNIDO?
What are the stages of project development according to UNIDO?
Which of the following is the main purpose of preparing a Detailed Project Report (DPR)?
Which of the following is the main purpose of preparing a Detailed Project Report (DPR)?
What is the difference between a Detailed Project Report (DPR) and a Techno-Economic Feasibility Report (TEFR)?
What is the difference between a Detailed Project Report (DPR) and a Techno-Economic Feasibility Report (TEFR)?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What is the accuracy level required for preparing filmed-up estimates with about 15 percent accuracy?
What documents are necessary for the preparation of a Detailed Project Report (DPR)?
What documents are necessary for the preparation of a Detailed Project Report (DPR)?
What is the main cause of overruns in projects?
What is the main cause of overruns in projects?
What is the main objective of project management?
What is the main objective of project management?
Which of the following is NOT a phase in the project development cycle?
Which of the following is NOT a phase in the project development cycle?
What is the main purpose of project management?
What is the main purpose of project management?
What is the main difference between a pre-feasibility report and a detailed project report?
What is the main difference between a pre-feasibility report and a detailed project report?
Which of the following is NOT a requirement for developing a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
Which of the following is NOT a requirement for developing a Detailed Project Report (DPR) from a Techno-economic Feasibility Report (TEFR)?
What documents are necessary for DPR preparation?
What documents are necessary for DPR preparation?
What is the level of accuracy required for preparing filmed-up estimates with about 15 percent accuracy?
What is the level of accuracy required for preparing filmed-up estimates with about 15 percent accuracy?
According to the text, what is one of the general causes of overruns during the Evaluation Phase of a project?
According to the text, what is one of the general causes of overruns during the Evaluation Phase of a project?
What is the time overrun of the Bokaro expansion project?
What is the time overrun of the Bokaro expansion project?
What is the cost overrun of the Bhilai expansion project in percentage?
What is the cost overrun of the Bhilai expansion project in percentage?
What is the estimated cost of the Panchat II project in Bihar?
What is the estimated cost of the Panchat II project in Bihar?
Which of the following is NOT a phase in the project development cycle?
Which of the following is NOT a phase in the project development cycle?
What are the different phases of project development cycle?
What are the different phases of project development cycle?
What is the purpose of the Techno-economic Feasibility Report (TEFR)?
What is the purpose of the Techno-economic Feasibility Report (TEFR)?
What is the main objective of the pre-investment phase of an industrial project?
What is the main objective of the pre-investment phase of an industrial project?
Which sector suffered a significant cost overrun and delay in the Narora Atomic Power Plant project?
Which sector suffered a significant cost overrun and delay in the Narora Atomic Power Plant project?
What is the estimated cost overrun for the Moonidih Underground Project in the Coal Sector?
What is the estimated cost overrun for the Moonidih Underground Project in the Coal Sector?
In which year did the development process in India, using science, technology, engineering, and construction, begin?
In which year did the development process in India, using science, technology, engineering, and construction, begin?
What was the total financial outlay for development projects in India from 1951 to 1989-90?
What was the total financial outlay for development projects in India from 1951 to 1989-90?
Which stage of project development involves analyzing social, financial, economic, and technical cost-benefits and feasibility?
Which stage of project development involves analyzing social, financial, economic, and technical cost-benefits and feasibility?
What is the purpose of a pre-feasibility report in project formulation?
What is the purpose of a pre-feasibility report in project formulation?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
What is the main difference between a Techno-economic Feasibility Report (TEFR) and a Detailed Project Report (DPR)?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
Which of the following is NOT a component generally contained in a Techno-economic feasibility report?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
What is the main difference between a Detailed Project Report (DPR) and a Techno-economic Feasibility Report (TEFR)?
What is the time limit for submitting the Detailed Project Report (DPR) after TEFR clearance?
What is the time limit for submitting the Detailed Project Report (DPR) after TEFR clearance?
What are the angles from which the total financial viability of a project is examined closely?
What are the angles from which the total financial viability of a project is examined closely?