Systems Engineering Week 11: Work Breakdown Structure

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the primary purpose of the Work Breakdown Structure (WBS) in systems engineering?

  • To structure integrated teams for program management purposes
  • To organize system development activities based on system and product decompositions (correct)
  • To identify high-cost and high-risk elements for management and reporting
  • To define the physical and systems architectures

What is the relationship between the WBS and the systems engineering process?

  • The WBS is not related to the systems engineering process
  • The WBS is an input to the systems engineering process
  • The WBS is an output of the systems engineering process (correct)
  • The WBS is a standalone tool for program management

What is the purpose of extending the WBS as the program proceeds through development?

  • To increase the budget for the program
  • To simplify the WBS structure
  • To reduce the scope of the program
  • To identify all high-cost and high-risk elements for management and reporting (correct)

What is one of the organizational purposes of the WBS?

<p>To provide a coordinated, complete, and comprehensive view of program management (A)</p> Signup and view all the answers

What is the business purpose of the WBS?

<p>To provide a structure for budgets and cost estimates (A)</p> Signup and view all the answers

How many levels of the WBS are developed initially?

<p>Three levels (D)</p> Signup and view all the answers

What is the purpose of the WBS in systems analysis and control?

<p>To provide a means of structuring development activities, identifying data and documents, and organizing integrated teams (D)</p> Signup and view all the answers

What is the flexibility provided to the contractor in extending the WBS?

<p>To extend the WBS below the reporting requirement to reflect how work will be accomplished (A)</p> Signup and view all the answers

What is the primary purpose of the Work Breakdown Structure (WBS)?

<p>To organize and analyze detailed costs for earned value reports (A)</p> Signup and view all the answers

What is one of the technical purposes of the WBS?

<p>To identify products, processes, and data (C)</p> Signup and view all the answers

What is used to prepare the WBS?

<p>Physical and system architectures (C)</p> Signup and view all the answers

What is the purpose of Level 1 in the WBS?

<p>To establish the overall system (D)</p> Signup and view all the answers

What is the purpose of the WBS in developing Statements of Work (SOW)?

<p>To group product items for SOW development (A)</p> Signup and view all the answers

Why should the physical and system architectures be reviewed during WBS development?

<p>To ensure all necessary products and services are identified (A)</p> Signup and view all the answers

What is the purpose of the WBS in organizing risk management analysis and tracking?

<p>To enable configuration and data management (D)</p> Signup and view all the answers

What is the purpose of the WBS in developing work packages for work orders and material/part ordering?

<p>To develop work packages for work orders and material/part ordering (B)</p> Signup and view all the answers

Flashcards are hidden until you start studying

Study Notes

Work Breakdown Structure (WBS)

  • The Work Breakdown Structure (WBS) is a means of organizing system development activities based on system and product decompositions.
  • WBS is a direct derivative of the physical and systems architectures and is an output of the systems engineering process.

Characteristics of WBS

  • Organizes system and product descriptions, and associated services (e.g., program management, systems engineering) in a hierarchical tree-like structure.
  • Essential for all aspects of the systems engineering process.
  • Used to structure development activities, identify data and documents, organize integrated teams, and for other non-technical program management purposes.

Development of WBS

  • Initially developed to define the top three levels.
  • Extended to identify high-cost and high-risk elements for management and reporting as the program proceeds through development.

Purposes of WBS

Organizational

  • Provides a coordinated, complete, and comprehensive view of program management.
  • Establishes a structure for organizing system development activities.

Business

  • Provides a structure for budgets and cost estimates.
  • Used to organize collection and analysis of detailed costs for earned value reports.

Technical

  • Establishes a structure for identifying products, processes, and data.
  • Organizes risk management analysis and tracking.
  • Enables configuration and data management, interface identification and control.
  • Used to group product items for specification development, develop Statements of Work (SOW), and identify specific contract deliverables.