SPM-500 Flash Tank Operator Training
24 Questions
0 Views

SPM-500 Flash Tank Operator Training

Created by
@SweetHorse

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the initial adjustment for the flash tank feed flow controller FIC-401 during the manual setup?

  • Setpoint to 50.0 GPM
  • Output to 50.0 %
  • Output to 0.0 % (correct)
  • Setpoint to 100.0 GPM
  • In setting up the flash tank level controller LIC-501, what is the first output adjustment made?

  • Output to 100.0 % (correct)
  • Output to 0.0 %
  • Output to 50.0 %
  • Output to 75.0 %
  • During the emergency shutdown procedure, how long is the entire process expected to take?

  • Approximately 5 minutes
  • Approximately 10 minutes
  • Approximately 4 minutes (correct)
  • Approximately 2 minutes
  • What action must be taken after adjusting the flash tank pressure controller PIC-501 output to 0.0 %?

    <p>Close vapor block hand valve HV-501</p> Signup and view all the answers

    Which controller is adjusted to 0.0 GPM as part of the flash tank control procedures?

    <p>Feed flow controller FIC-401</p> Signup and view all the answers

    What is the setpoint value for the flash tank level controller LIC-501 after the initial adjustments?

    <p>0.0 % LVL</p> Signup and view all the answers

    What is one of the key procedures to follow during an emergency operation?

    <p>Follow specific emergency procedures for the process plant</p> Signup and view all the answers

    What happens after the flash tank pressure controller PIC-501 is placed in MANUAL mode?

    <p>Output must be adjusted to 100.0 %</p> Signup and view all the answers

    What is the purpose of modulating the setpoints of the feed temperature controller (TIC-406) and flash tank pressure controller (PIC-501)?

    <p>To smoothen changes in product compositions</p> Signup and view all the answers

    Which of the following best describes a potential cause of alarms in the flash tank simulation?

    <p>Fluctuations in upstream feed composition</p> Signup and view all the answers

    Which instrument is associated with monitoring the flow rate of vapor in the system?

    <p>FI-501</p> Signup and view all the answers

    What should be the initial step before beginning any startup procedures?

    <p>Perform pre-startup procedures</p> Signup and view all the answers

    What is one potential consequence of not responding appropriately to an alarm?

    <p>A dangerous condition may develop</p> Signup and view all the answers

    In terms of process safety management, how should alarms be interpreted?

    <p>As conditions that require understanding of process variables</p> Signup and view all the answers

    Which controller is primarily used for adjusting product flow rates in the system?

    <p>FIC-401</p> Signup and view all the answers

    Which of the following is not included in the normal pre-startup procedures?

    <p>Conducting routine maintenance tasks</p> Signup and view all the answers

    What is the main objective of the SPM-500 Flash Tank Process?

    <p>To separate a mixture of hexane and heptane</p> Signup and view all the answers

    At what temperature is the mixture supplied to the SPM-500 for separation?

    <p>85 Deg F</p> Signup and view all the answers

    What is produced from the SPM-500 Flash Tank Process in terms of heptane?

    <p>Heptane liquid at 220 GPM</p> Signup and view all the answers

    What is the pressure of the hexane rich vapor produced by the SPM-500?

    <p>80 PSIG</p> Signup and view all the answers

    Which aspect of process safety management is crucial in the event of an emergency during operations?

    <p>Immediate evacuation of personnel</p> Signup and view all the answers

    Which control procedure is vital for maintaining the separation process in the flash tank?

    <p>Temperature control procedures</p> Signup and view all the answers

    What is a critical step in the emergency shutdown protocol of the SPM-500?

    <p>Isolate the system from power sources</p> Signup and view all the answers

    What type of diagrams are included in the SPM-500 manual to assist with process flow understanding?

    <p>ID diagrams</p> Signup and view all the answers

    Study Notes

    SPM-500 Flash Tank Operator Training Manual

    • Version: 6.3
    • Revision: 2
    • Contact Information:
      • Phone: 1-800-730-0760, +1-732-747-0322, 1-732-224-0009 (fax)
      • Technical Support: 1-800-730-0760, +1-732-869-6651
      • Email: [email protected]
      • Address: P.O. Box 38, Little Silver, NJ 07739-0038, USA
      • Website: www.simtronics.com
    • Copyright © 1992-2013 Simtronics Corporation
    • All rights reserved.
    • Simtronics name and products are trademarks or registered trademarks.
    • Simtronics Corporation is a privately held, independent New Jersey corporation.
    • All materials developed by Simtronics Corporation

    Business Hours

    • 8 a.m. to 5 p.m. Eastern Time, Monday through Friday

    SPM-500 Flash Tank Contents

    • Process Description: Separates hexane (C6) and heptane (C7) based on boiling points.
    • Equipment Specifications: Feed preheater, flash tank, overhead vapor line, bottoms liquid line; details listed on page 5.
    • Process Flow and ID Diagrams: Diagrams of flow and instruments, listed on page 6.
    • Instrumentation: Includes composition analyzers, flow controllers, pressure controllers, and level controllers. Includes detailed information about component functions. Listed on page 7.
    • Normal Operations: Table of tagging IDs, descriptions, values, and percentages. Includes detailed functions. Listed on page 8. Also includes specific production monitoring parameters and details on adjusting parameters.
    • Pre-Startup: Procedures to be undertaken before startup procedures, like flushing, cleaning, and testing. Listed on page 10.
    • Startup: Step-by-step procedures for initiating the process, timing detailed. Listed on page 11.
    • Shutdown: Step-by-step procedures for ending the process, timing detailed. Listed on page 12.
    • Emergency Operations: Procedures for handling emergencies and shutdowns. Listed on page 13.

    Product Specifications

    • Mix of approximately 300 GPM of 46 wt% hexane and 54 wt% heptane
    • ~420 ACFM of hexane-rich vapor at 80 PSIG and 319°F
    • ~220 GPM of heptane-rich liquid at 80 PSIG and 319°F

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    This quiz is designed for operators using the SPM-500 Flash Tank. It covers process descriptions, equipment specifications, and operational guidelines necessary for effective training. Enhance your understanding of hexane and heptane separation techniques through this detailed assessment.

    More Like This

    Use Quizgecko on...
    Browser
    Browser