25 Questions
Which view of requirements considers data and the process that transform the data as connected entities?
Object oriented analysis
What is an indicator in the context of software processes?
Indicator
Earned value analysis computes which aspect of a project?
The total amount of work accomplished for a task at a particular point in time
What does software scope describe?
The function and features to be delivered to end users
How many person-months will the project take with an average productivity of 800 LOC person-month and an estimate of 30,000 LOC?
44
What is the estimated cost of the project with a labor rate of $12152 per month and the given parameters?
$412,500
Is the statement true or false: The cost per line of code on this project is $15.19.
False
What is the function point (FP) for this project with a count-total of 320 and a value adjustment factor (Σ Fi) of 30?
304
What was the main cause of the Y2K potential software disaster?
Using a two digit year field in COBOL programs
Which is a common problem associated with software maintenance?
The software is written in older, unfamiliar language
Which phase of a software’s lifecycle is considered the most expensive?
Most expensive
Which type of software maintenance requires the largest percentage of effort?
Corrective
In peer to peer networks, what is the role of a server?
Control communication among nodes
What term was coined due to a moth causing a defect in early electro-mechanical computers?
'Bug'
What is the primary difference between analysis classes and data objects?
Analysis classes can have operations, and data objects cannot.
What does PERT technique primarily determine?
The critical path for a project
What does Earned Value Analysis compute?
Both projects progress and uses known from previous projects
What is an important factor in estimation for Object-Oriented projects?
Determining the number of key classes
Which is not a risk due to 'business impact'?
Are CASE tools used for analysis, design, and testing
(T/F) Corrective maintenance is aimed at adding missing functionality.
False
In software project scheduling, what is crucial for the success of the project?
Every task having a defined outcome
How many person-months will a project take if it has 30,000 lines of code and an average productivity of 800 LOC person-month?
37.5
What is the estimated cost of a project based on the given information?
$277,200
What does a generic software development process model require?
Iteration to ensure all requirements are captured
Which is not a part of the 4P's of a software project?
Planning
Test your knowledge on software project scope and monitoring with questions related to defining software scope, creating software architecture, use cases, and project status monitoring.