What is the main purpose of a Resource Histogram in project management?
What is the main purpose of a Resource Histogram in project management?
- To represent the critical path of a project.
- To identify interdependent tasks in a project.
- To allocate specific time frames to project events.
- To plan and coordinate the required staff over time. (correct)
In Critical Path Analysis, what does the term 'critical path' refer to?
In Critical Path Analysis, what does the term 'critical path' refer to?
- The path with the highest resource allocation.
- The path with the most number of tasks.
- The path that has no dependencies.
- The shortest path to complete a project. (correct)
How is a Resource Histogram generally represented?
How is a Resource Histogram generally represented?
- As a pie chart.
- As a Gantt chart. (correct)
- As a PERT chart.
- As a network diagram.
What type of tools are Critical Path Analysis and Resource Histogram in software engineering?
What type of tools are Critical Path Analysis and Resource Histogram in software engineering?
Which aspect of a project do interdependent tasks focus on in Critical Path Analysis?
Which aspect of a project do interdependent tasks focus on in Critical Path Analysis?
In what way does Critical Path Analysis help in project management?
In what way does Critical Path Analysis help in project management?